JUDGMENT
CATCHWORDS
Uniform Civil Procedure Rules r 292, r 293
Cross-applications by plaintiff and defendants for summary judgement - plaintiff successful - parties' deed held to require payment on dates stipulated for particular amounts aggregating $140,000, which was taken to be the relevant debt on dissolution of a partnership - payments to be made albeit on a provisional basis pending recourse to processes for raising and resolving dispute as to correctness of the $140,000 - no outcome from such processes to date
HIS HONOUR: There are cross applications before the court, one by the plaintiff seeking summary judgment under rule 292, the other by the defendants seeking judgment under rule 293.
The latter application I would construe as a tactical response to the other. It certainly hasn't been demonstrated that the plaintiff presents a claim so devoid of prospects of success it ought to be dismissed without a trial on the merits.
The plaintiff and the defendants on the otherside were in partnership, operating a business of health and fitness centres with premises in Brisbane and the Gold Coast which ran satisfactorily for some years until unhappy differences led to a separation which involved a distribution of the premises and the businesses conducted in them: one to the plaintiff, the other to the defendants' side.
There were disagreements in relation to sorting out accounts. These were resolved by a deed of agreement, the parties to which were the plaintiff company and the defendant company, also the first defendant and Mr Paul Christopher Shepherd, who stands behind the plaintiff. That deed of agreement, which is before the court, was executed some time in November 2008.
It deals with the issues of present concern in paragraph 21, which notes that the plaintiff and/or Mr Shepherd had made financial accommodation available to the partnership and to Ms Grochau that Williams and Partners, the partnership accountants, had produced draft partnership accounts quantifying the difference in partnership payments as a "Debt" of $304,900 owing to the plaintiff.
The clause goes on, and I quote:
“21.3. For the purposes of this Deed, the Debt is to be reduced to $140,000.
“21.4. Bodhi Space and Jasmine are entitled, at their own expense, to engage an accountant (Nominee Accountant) to review the Draft Partnership Accounts and all documentation of the partnership used to compile such accounts to verify the Debt.
“21.5. Any such review of accounts and any dispute arising therefrom is to be completed and/or raised, as the case may be, by 31 January 2009.
“21.6. Where a difference is material (i.e. the amount payable herein under clause 21.3 may be less than the Debt), the nominee accountant and Williams and Partners are to confer to resolve any difference which will become the new Debt figure. This does not delay or negate the…
Keep reading for free
Create a free CaseChat account to read Bodhi Space No 2 Trust v Grochau and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2011] QDC 59
- Decision Date
CaseChat Overview and Summary
The court held that the defendants were indeed obliged to make the payments as per the agreement, despite the ongoing dispute over the exact amount of the debt. The reasoning hinged on the interpretation of the deed's clause 21.6, which mandated payments regardless of any differences in the accountants' assessments. The court found that the second sentence of clause 21.6 committed the defendants to making payments, and any dispute over the debt's amount would not absolve them from this obligation. The court compared this situation to cases under the Building and Construction Industry Payments Act 2004 and other analogous contractual provisions, which also required provisional payments with disputes over the exact amount to be resolved later. Therefore, the plaintiff was entitled to the payments as per the agreement, albeit on a provisional basis pending a final resolution of the debt's amount.
The court granted summary judgment in favour of the plaintiff, ordering the defendants to make the payments stipulated in the deed. The judgment allowed the plaintiff to recover indemnity costs for the successful application and standard costs for the dismissal of the defendants' cross-application. This decision underscored the principle that contractual obligations to make payments are not contingent on the final determination of the exact debt amount, provided the agreement clearly mandates such payments.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.