SUPREME COURT OF VICTORIA
COURT OF APPEAL
No 6453 of 2004
| BMD MAJOR PROJECTS PTY LTD (ACN 052 965 394) | Appellant |
| and | |
| VICTORIAN URBAN DEVELOPMENT AUTHORITY | Respondent |
| And Between | |
| No 3732 of 2008 | |
| VICTORIAN URBAN DEVELOPMENT AUTHORITY | Cross-Appellant |
| and | |
| BMD MAJOR PROJECTS PTY LTD (ACN 052 965 394) | Cross-Respondent |
---
| JUDGES | BUCHANAN, NETTLE and WEINBERG JJA | |
| WHERE HELD | MELBOURNE | |
| DATE OF HEARING | 20 March 2009 | |
| DATE OF JUDGMENT | 7 October 2009 | |
| MEDIUM NEUTRAL CITATION | [2009] VSCA 221 | First revision 13 October 2009. Amended orders pursuant to Rule 36.07 of the Supreme Court Rules. |
| JUDGMENT APPEALED FROM | [2008] VSC 566 (Pagone J) | |
---
CONTRACT – Excavation, filling and rehabilitation of a quarry – Lump sum contract – Contractor entitled to recover extra payment for work to deal with latent conditions different from those which the contractor should reasonably have contemplated – Documents prepared by the operators of the quarry should not have caused the contractor to anticipate levels of excavation differing from those shown in tender documents – Objective test – Notification of latent conditions – Notices complied with the terms of contract – Notice given ‘forthwith’- Need to excavate a greater volume of material capable of being a latent condition – Notice of delay to be given within 28 days after the delay occurs – Notices compliant with the contract – Calculation of additional costs – Costs recoverable only if the costs could not reasonably have been anticipated – Whether additional costs were caused by latent conditions – Reasonable rates or prices – Criteria for the calculation of additional costs – Claim for extra costs caused by delay – Contract required claim to be made when delay first occurred – Instruction by superintendent to contractor relaxed the requirements of the contract and did not entitle the contractor to recover extra costs – Instruction by superintendent was for the convenience of the contractor – Claims for extension of time – Effect of amendment of date for practical completion on calculation of costs occasioned by delay – Costs attributable to delay caused by latent conditions were recoverable – Adjustment of amount allowed for additional excavation
ESTOPPEL – Whether estoppel pleaded or argued – Principal estopped by representation that strict observance of the terms of the contract was not required.
S 52 of the Trade Practices Act 1974 (Cth) – Claim for damages pursuant to s 52 of the Act -Contractor not misled or deceived – No reliance upon any representations by principal – Disclaimers – Effect of qualifications and reservations in the supply of information – Calculation of damages – Contractor failed to establish that it suffered a loss by entering into contract.
INTEREST – Supreme Court Act 1985 – Interest recoverable in respect of damages, not a debt or sum certain.
COSTS – Calderbank letter – Amount recovered exceeded sum stated in letter.
---
| Appearances: | Counsel | Solicitors |
| For Appellant/Cross-Respondent | Dr C L Pannam QC with Mr G H Golvan QC and Mr M I Borsky | Rigby Cook, Lawyers as agents for… |
Keep reading for free
Create a free CaseChat account to read BMD Major Projects Pty Ltd v Victorian Urban Development Aut... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Find similar cases
Other decisions on the same topics. Each opens in a new tab.
Details
- Case
- [2009] VSCA 221
- Decision Date
CaseChat Overview and Summary
The court found that the contractor was entitled to recover additional costs for latent conditions, provided those costs could not reasonably have been anticipated. The documents prepared by the quarry operators did not lead the contractor to anticipate excavation levels different from those shown in the tender documents. The notices given regarding latent conditions and delays complied with the contractual terms. However, the claim for extra costs due to delays was invalid as the superintendent's instruction relaxed the contract's requirements, and the instruction was for the contractor's convenience. The court also determined that the amendment of the practical completion date did not affect the calculation of costs attributable to delays caused by latent conditions.
In relation to estoppel, the court held that no estoppel was pleaded or argued, and there was no evidence that the principal was estopped by any representation that strict observance of the contract terms was not required. The contractor's claim for damages under the Trade Practices Act 1974 failed as there was no evidence of being misled or deceived, or reliance on any representations by the principal. Regarding interest, the court ruled that interest was recoverable in respect of damages, but not for a debt or sum certain under the Supreme Court Act 1985. Lastly, on costs, the amount recovered exceeded the sum stated in the Calderbank letter, leading to an adjustment in the costs awarded.
Background
Background to the litigation
Decision
Reasons for decision
Ratio Decidendi