BMD Major Projects Pty Ltd v Victorian Urban Development Authority

Link copied
Case Copied 75 min read

SUPREME COURT OF VICTORIA

COURT OF APPEAL

No 6453 of 2004

BMD MAJOR PROJECTS PTY LTD
(ACN 052 965 394)
Appellant
and
VICTORIAN URBAN DEVELOPMENT AUTHORITY Respondent
And Between
No 3732 of 2008
VICTORIAN URBAN DEVELOPMENT AUTHORITY  Cross-Appellant
and
BMD MAJOR PROJECTS PTY LTD
(ACN 052 965 394)
Cross-Respondent

---

JUDGES BUCHANAN, NETTLE and WEINBERG JJA
WHERE HELD MELBOURNE
DATE OF HEARING 20 March 2009
DATE OF JUDGMENT 7 October 2009
MEDIUM NEUTRAL CITATION [2009] VSCA 221

First revision 13 October 2009. 

Amended orders pursuant to Rule 36.07 of the Supreme Court Rules.

JUDGMENT APPEALED FROM [2008] VSC 566 (Pagone J)

---

CONTRACT – Excavation, filling and rehabilitation of a quarry – Lump sum contract – Contractor entitled to recover extra payment for work to deal with latent conditions different from those which the contractor should reasonably have contemplated – Documents prepared by the operators of the quarry should not have caused the contractor to anticipate levels of excavation differing from those shown in tender documents – Objective test – Notification of latent conditions – Notices complied with the terms of contract – Notice given ‘forthwith’- Need to excavate a greater volume of material capable of being a latent condition – Notice of delay to be given within 28 days after the delay occurs – Notices compliant with the contract – Calculation of additional costs – Costs recoverable only if the costs could not reasonably have been anticipated – Whether additional costs were caused by latent conditions – Reasonable rates or prices – Criteria for the calculation of additional costs – Claim for extra costs caused by delay – Contract required claim to be made when delay first occurred – Instruction by superintendent to contractor relaxed the requirements of the contract and did not entitle the contractor to recover extra costs – Instruction by superintendent was for the convenience of the contractor – Claims for extension of time – Effect of amendment of date for practical completion on calculation of costs occasioned by delay – Costs attributable to delay caused by latent conditions were recoverable – Adjustment of amount allowed for additional excavation

ESTOPPEL – Whether estoppel pleaded or argued – Principal estopped by representation that strict observance of the terms of the contract was not required.

S 52 of the Trade Practices Act 1974 (Cth) – Claim for damages pursuant to s 52 of the Act -Contractor not misled or deceived – No reliance upon any representations by principal – Disclaimers – Effect of qualifications and reservations in the supply of information – Calculation of damages – Contractor failed to establish that it suffered a loss by entering into contract.

INTEREST – Supreme Court Act 1985 – Interest recoverable in respect of damages, not a debt or sum certain.

COSTS – Calderbank letter – Amount recovered exceeded sum stated in letter.

---

Appearances: Counsel Solicitors
For Appellant/Cross-Respondent Dr C L Pannam QC with
Mr G H Golvan QC and
Mr M I Borsky
Rigby Cook, Lawyers as agents for…
CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read BMD Major Projects Pty Ltd v Victorian Urban Development Aut... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details

Case
[2009] VSCA 221
Decision Date

CaseChat Overview and Summary

BMD Major Projects Pty Ltd brought a claim against the Victorian Urban Development Authority in the Supreme Court of Victoria for additional costs incurred during the excavation, filling, and rehabilitation of a quarry. The dispute arose under a lump sum contract where the contractor sought to recover extra payments for work necessitated by latent conditions different from those reasonably contemplated. The primary issues before the court were whether the contractor was entitled to recover the additional costs due to latent conditions, if the claims for additional costs and extensions of time were properly made, and if the contractor suffered loss due to any representations by the principal.

The court found that the contractor was entitled to recover additional costs for latent conditions, provided those costs could not reasonably have been anticipated. The documents prepared by the quarry operators did not lead the contractor to anticipate excavation levels different from those shown in the tender documents. The notices given regarding latent conditions and delays complied with the contractual terms. However, the claim for extra costs due to delays was invalid as the superintendent's instruction relaxed the contract's requirements, and the instruction was for the contractor's convenience. The court also determined that the amendment of the practical completion date did not affect the calculation of costs attributable to delays caused by latent conditions.

In relation to estoppel, the court held that no estoppel was pleaded or argued, and there was no evidence that the principal was estopped by any representation that strict observance of the contract terms was not required. The contractor's claim for damages under the Trade Practices Act 1974 failed as there was no evidence of being misled or deceived, or reliance on any representations by the principal. Regarding interest, the court ruled that interest was recoverable in respect of damages, but not for a debt or sum certain under the Supreme Court Act 1985. Lastly, on costs, the amount recovered exceeded the sum stated in the Calderbank letter, leading to an adjustment in the costs awarded.

Background

Background to the litigation

Decision

Reasons for decision

Ratio Decidendi

Legal principle established