Blue Mountains City Council v Anderson and Anor

Link copied
Case Copied 7 min read

Land and Environment Court


of New South Wales


CITATION: Blue Mountains City Council v Anderson and Anor [2008] NSWLEC 250
PARTIES: APPLICANT
Blue Mountains City Council
FIRST RESPONDENT
Allan Neville Anderson
SECOND RESPONDENT
Rhonda Jean Anderson
FILE NUMBER(S): 40409 of 2008
CORAM: Pain J
KEY ISSUES: Civil Enforcement :- enforcement of s124 order issued under the Local Government Act 1973 requiring work on collapsed retaining wall; ex parte orders made
LEGISLATION CITED: Land and Environment Court Act 1979 s20
Local Government Act 1993 s 124, s672, s673
Uniform Civil Procedure Rules 2005 Pt 36 r 36.16(2)(b)
DATES OF HEARING: 28 August 2008
EX TEMPORE JUDGMENT DATE: 28 August 2008
LEGAL REPRESENTATIVES:

APPLICANT
Ms Linkenbagh (solicitor)
SOLICITOR
Houston Dearn O'Connor

RESPONDENTS
No appearance


JUDGMENT:

      THE LAND AND
      ENVIRONMENT COURT
      OF NEW SOUTH WALES

      Pain J

      28 August 2008

      40409 of 2008 Blue Mountains City Council v Anderson and Anor

      EX TEMPORE JUDGMENT

1 Her Honour: The Council commenced these Class 4 proceedings on 23 April 2008 to enforce an order issued under s 124 of the Local Government Act 1993 (the LG Act) requiring, inter alia, rectification of a collapsed retaining wall in front of the Respondents’ property at 16 Roberts Parade, Hawkesbury Heights. These proceedings are enabled by s 672 and s 673 of the LG Act and s 20(1)(d) of the Land and Environment Court Act 1979 (the Court Act). The order was issued on 12 July 2007 following the provisions of the requisite notice under the LG Act in May 2007. Both Respondents own the property as joint tenants. They received notice of the Council’s intention to commence proceedings from the Council’s solicitors in December 2007.

2 The First Respondent did not appear at Court today and sent a fax to the Registrar saying he was ill and unable to complete the work in time due to his personal circumstances, including ill health and limited finances. Nothing has been heard from Ms Rhonda Anderson, the Second Respondent.

3 The matter has been mentioned before the Court on several occasions including having the matter stood over on 13 June 2008 to allow time for the work required under the s 124 notice to be carried out on the advice of the First Respondent faxed to the Court on 12 June 2008 that the work would take a further four weeks. The order the Council is seeking to enforce is now well over 12 months old. The collapsed rock retaining wall has fallen across public land able to be used as a footpath and the Council is concerned about public safety if the wall is not properly repaired. The Council wishes to proceed with the matter ex parte in light of the time this matter has taken.

4 I consider I should determine the matter today in the absence of the First Respondent given the length of time the matter has taken and given that the order served by the Council has not yet been complied with. Amended orders…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Blue Mountains City Council v Anderson and Anor and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2008] NSWLEC 250
Decision Date

CaseChat Overview and Summary

Blue Mountains City Council initiated legal proceedings against the respondents, Anderson and another party, concerning the condition of a retaining wall on a property located at 16 Roberts Parade, Hawkesbury Heights. The council sought orders to ensure the wall's structural integrity and compliance with local regulations. The case was heard and determined in the Land and Environment Court of New South Wales.

The court was required to decide whether the retaining wall was inadequate and whether the respondents were obligated to repair, replace, or demolish the wall. Additionally, the court needed to consider whether the respondents should be required to provide a structural engineer's report and to establish a timeline for the necessary works. The council argued that the wall posed a risk to public safety and the environment, while the respondents contested the necessity and urgency of the proposed actions.

In its decision, the court found that the retaining wall was indeed inadequate and that the respondents must comply with the council's demands. The court ordered the respondents to obtain a structural engineer's report within sixty days and to carry out the necessary repairs or demolition within specified timeframes. The court also mandated that the respondents maintain sediment control and provide a barrier to protect pedestrians. The court ruled that the respondents were to bear the council's costs, though payment was deferred for six months.

The final orders required the respondents to either repair or demolish the retaining wall, maintain sediment control, and provide a barrier for pedestrian safety. The respondents were also ordered to pay the council's costs, subject to a six-month deferment.

Orders

Orders of the court

1. That the First Respondent provide to Council within sixty (60) days of the date of service of this order a report from a structural engineer as to:

(a) The adequacy of the existing stone retaining wall along the front boundary of 16 Roberts Parade, Hawkesbury Heights and its components.

(b) The work necessary to repair and/or replace and/or reconstruct all or part(s) of the retaining wall along the front boundary of the property so as to achieve structural integrity of the retaining wall along the length of the boundary and to protect against failure of any part of the retaining wall in the future.

2. That within eight (8) months from the date of service of this order on the First Respondent he cause the work referred to in the report provided pursuant to order 1(b) to be done.

3. (a) In the alternative to compliance with orders 1 and 2 on the condition that the First Respondent give written notice to the Council within fourteen (14) days of service of these orders on him of his intention to demolish the whole of the retaining wall along the front boundary of the property known as 16 Roberts Parade, Hawkesbury Heights, the First Respondent shall demolish the retaining wall and remove all rocks, materials and other components of the wall and batter the slope to a ratio of three (3) horizontal to one (1) vertical.

(b) The work referred to in order 3(a) shall be completed within three (3) months of the date of the notice referred to order 3(a).

4. The First Respondent shall maintain adequate sediment control at all times until these orders are complied with.

5. The First Respondent shall provide an adequate barrier between any rocks, materials and equipment remaining on the nature strip relating to work being carried out pursuant to orders 2 or 3 so as not to obstruct pedestrian traffic.

6. That the First Respondent pay the Applicant’s costs and disbursements in the sum of $2,000. These costs are not payable until after six (6) months after the date of service of these orders on the First Respondent.

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established