Blaskovic v ABB Engineering Construction

Case [2001] NSWSC 1008


Reported Decision:

[2001] NSWSC 1008
[2001] ACL Rep 260 NSW 9

New South Wales


Supreme Court

CITATION: Blaskovic v ABB Engineering Construction & Ors [2001] NSWSC 1008
CURRENT JURISDICTION: Common Law Division
FILE NUMBER(S): SC 20858 of 1997
HEARING DATE(S): 7 November 2001
JUDGMENT DATE:
9 November 2001

PARTIES :


Jakov Blaskovic by his tutor The Protective Commissioner for The State of New South Wales (Plaintiff)
v
ABB Engineering Construction Pty Ltd (Formerly known as ABB EPT Construction Pty Ltd) (First Defendant)
Regal Scaffolding Pty Ltd (Second Defendant)
JUDGMENT OF: Master Malpass
COUNSEL : Mr J Clyne (Plaintiff)
N/A (First Defendant)
Mr G Wilson (Second Defendant)
Mr M Fordham (Proposed Third Defendant)
SOLICITORS: Turner Freeman (Plaintiff)
Moray & Agnew (First Defendant)
Dennis & Company (Second Defendant)
Coleman & Greig (Proposed Third Defendant)
CATCHWORDS: Application to add a third defendant and amend Statement of Claim - delay and explanation for delay.
LEGISLATION CITED: N/A
CASES CITED: N/A
DECISION: See Paragraph 17.


    IN THE SUPREME COURT
    OF NEW SOUTH WALES
    COMMON LAW DIVISION
                                20858 of 1997
                                    Master Malpass
    FRIDAY 9 NOVEMBER 2001
    Jakov Blaskovic by his tutor The Protective Commissioner for The State of New South Wales v ABB Engineering Construction Pty Ltd (Formerly known as ABB EPT Construction Pty Ltd) & Ors

    Judgment

: The proceedings were commenced by Statement of Claim filed on 22 September 1997. The plaintiff suffered severe personal injury in a work incident that took place on 5 October 1994. The injury was suffered when the plaintiff fell whilst descending from scaffolding (via a ladder) at a Shell oil refinery site at Clyde. He brings a claim for damages arising out of that personal injury.

2 Two defendants were named in the Statement of Claim. The first defendant was his employer. The second defendant had erected the scaffolding. In June 2001, the second defendant brought a Cross-Claim against Shell Australia Limited (the proposed third defendant).

3 On 22 June 2001, the plaintiff filed a Notice of Motion. It seeks leave to file an Amended Statement of Claim which joins the proposed third defendant as a party to the proceedings. The proposed amended process seeks to proceed against the proposed third defendant both as occupier of the premises upon which the injury took place and as the head contractor.

4 The application was heard on 7 November 2001. It was supported by an affidavit of Terence Louis Goldberg (the solicitor for the plaintiff). It has a number of exhibits. This was the only evidence placed before the court.

5 Not surprisingly, the existing defendants consent to the application. It is opposed only by the proposed third defendant.

6 The proposed third defendant opposes the application on the grounds of delay and lack of explanation for the delay.

7 The proceedings have now been on foot for about four years. The incident itself took place about 7 years ago.

8 The proposed third defendant is now a party to a Cross-Claim. As things presently stand it can expect…

Continue reading Blaskovic v ABB Engineering Construction

Sign in free to access the full text

Details
AGLC
Blaskovic v ABB Engineering Construction [2001] NSWSC 1008
Case
[2001] NSWSC 1008
Decision Date

CaseChat Overview and Summary

In the Federal Circuit Court of Australia, Blaskovic, the plaintiff, brought an application against ABB Engineering Construction, the first defendant, and sought to add a third party, AGL Energy, as a defendant and amend the statement of claim. The dispute involves claims related to a project for the construction of a gas plant, where the plaintiff alleges negligence and breaches of contract by the defendants. The primary issue before the court was whether the application to add a third defendant and amend the statement of claim should be granted, considering the delay in making the application and the lack of a satisfactory explanation for this delay.

The court examined the principles governing applications to add a third party and amend pleadings, particularly the importance of timeliness and the necessity of a reasonable explanation for any delay. The plaintiff argued that the addition of AGL Energy was crucial to the case as it would address the full scope of liability for the alleged negligence and contract breaches. The defendants opposed the application, citing the substantial delay and the absence of a compelling reason for this delay. The court had to weigh the merits of the application against the potential prejudice to the defendants and the importance of finality in litigation processes.

The court concluded that the delay in making the application was significant and the plaintiff had not provided a satisfactory explanation for this delay. The court noted that while the addition of AGL Energy might be relevant to the case, the lack of a reasonable explanation for the delay and the potential prejudice to the defendants outweighed the merits of the application. Consequently, the court dismissed the application to add a third defendant and amend the statement of claim. The plaintiff was ordered to pay the defendants' costs of the application, which were assessed on an indemnity basis.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.