QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION:
Blank Canvas Solutions Pty Ltd t/as Axiom Access v OzRig Pty Ltd [2018] QCAT 427
PARTIES:
BLANK CANVAS SOLUTIONS PTY LTD
t/as AXIOM ACCESS
(applicant)v OZRIG PTY LTD
(respondent)
APPLICATION NO/S:
BDL 172-17
MATTER TYPE:
Building matters
DELIVERED ON:
12 December 2018
HEARING DATE:
9 October 2018
HEARD AT:
Brisbane
DECISION OF:
Dr Collier, Member
ORDERS:
1. The Applicant is to pay the Respondent $13,521.62 within 30 days.
2. Submissions as to costs may be filed by 31 January 2019. If no submissions as to costs are filed by any party by 31 January 2019 no costs will be ordered and parties bear their own costs.
CATCHWORDS:
CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – THE CONTRACT – CONSTRUCTION OF PARTICULAR CONTRACTS AND IMPLIED CONDITIONS – the terms of the contract arising from an exchange of correspondence – implied term that work is to be performed in a workmanlike manner – The Moorcock (1899) 14 PD 64 – defective work performed by the contractor
CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – PERFORMANCE OF WORK – where implied term that contractor will perform the work in a workmanlike manner – defective work performed by the contractor – appropriate remedy – set-off
Queensland Building and Construction Commission Act 1991 (Qld)
The Moorcock (1899) 14 PD 64
APPEARANCES & REPRESENTATION:
Applicant:
D Benton, director of Blank Canvas Solutions Pty Ltd
Respondent:
P O’Brien, barrister
REASONS FOR DECISION
This dispute concerns the erection of tensioned fabric structures at height on the existing atrium roof of Jupiter’s Hotel and Casino on the Gold Coast (‘Jupiters’). The tensioned fabric structures envisaged were to be both an architectural feature of the building and to provide protection for people and property below from weather and environment.
The principal contractor acting for Jupiters was CPB Contractors Pty Ltd. CPB Contractors engaged MakMax Australia Pty Ltd (‘MakMax’) as the supplier of the product to be erected. MakMax, in turn, engaged OzRig Pty Ltd (‘OzRig’) as the mechanical contractor responsible to perform the safe and proper erection of the tensioned fabric structures.
OzRig, however, did not possess the staff with the qualifications necessary to operate using ropes at the heights involved, so OzRig contracted Blank Canvas Solutions Pty Ltd, which trades as Axiom Access (‘Axiom’), to perform the high-risk tasks involved in the actual erection of the tensioned fabric structures according to MakMax’s designs.
Early negotiations concerning support in erecting the fabric structures were conducted between OzRig and Rope Access and Rescue (not Axiom). It appears that, while Rope Access and Rescue Pty Ltd is still a company registered by the Australian Securities and Investments Commission, Blank Canvas Solutions Pty Ltd, trading as Axiom Access, is a new company established by a director of Rope Access and Rescue with a work colleague. No issue has been raised concerning the proper identity of the Applicant, so this decision proceeds on the basis that Axiom is the appropriate Applicant in this matter.
By what is…
Keep reading for free
Create a free CaseChat account to read Blank Canvas Solutions Pty Ltd t/as Axiom Access v OzRig Pty... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2018] QCAT 427
- Decision Date
CaseChat Overview and Summary
The primary legal issues that the court had to address were whether an implied term existed in the contract that the work was to be performed in a workmanlike manner and what remedies were available for defective work. The court examined the exchange of correspondence between the parties to ascertain the terms of the contract and considered the precedent set by The Moorcock (1899) 14 PD 64, which established that a contractor is impliedly obliged to perform work in a competent and workmanlike manner.
The court concluded that an implied term existed for Axiom to perform the work in a workmanlike manner, which it had failed to do, resulting in defective work. As a remedy, the court determined that OzRig was entitled to recover the costs incurred for remediation of the defective work. The court set off the remediation costs against Axiom's final invoice, resulting in a net payment from Axiom to OzRig of $13,521.62. The court also noted that there was no basis for interest to be paid under the agreement between the parties.
The final orders of the court were that Axiom was to pay OzRig $13,521.62 within 30 days and that submissions on costs could be filed by 31 January 2019. If no submissions on costs were filed by any party by that date, no costs would be ordered, and the parties would bear their own costs.
Orders
Orders of the court
1. The Applicant is to pay the Respondent $13,521.62 within 30 days.
2. Submissions as to costs may be filed by 31 January 2019. If no submissions as to costs are filed by any party by 31 January 2019 no costs will be ordered and parties bear their own costs.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi