CITATION: Blanche v North Parkes Limited [2008] NSWDC 175 HEARING DATE(S): 31 July 2008 EX TEMPORE JUDGMENT DATE: 31 July 2008 JURISDICTION: Civil JUDGMENT OF: Sidis DCJ DECISION: On the plaintiff’s motion filed on 11 April 2008:
1 Leave is granted pursuant to s 151D of the Workers Compensation Act 1987 to the plaintiff to commence proceedings against Capena Contracting Pty Limited.
2 The leave granted is to be exercised by not later than 18.8.08.
3 Liberty to apply to vary this date.
4 Costs of the motion will be costs in the cause.
On the fourth defendant’s motion filed on 18 February 2008:
1 Motion dismissed.
2 Costs of the Motion will be costs in the cause.CATCHWORDS: S 151D - delay resulting from delay in stabilisation of injury and assessment of workplace injury - whether explanation satisfactory LEGISLATION CITED: Workers Compensation Act 1987 PARTIES: Michael John Blanche (Plaintiff)
North Parkes Limited being part of the North Parkes Joint Venture t/a North Parkes Mine (First defendant)
SC Mineral Resources Pty Ltd being part of the North Parkes Joint Venture t/a North Parkes Mine (Second defendant)
Sumitomo Metal Mining Oceania Pty Ltd being part of the North Parkes Joint Venture t/a North Parkes Mine (Third defendant)
Capena Contracting Pty Ltd (formerly known as Henry Eltin Walker Contracting Pty Ltd) (Fourth defendant)FILE NUMBER(S): Newcastle 408/06 COUNSEL: I D Roberts SC-P J Kirby (Plaintiff)
P L Perry (Fourth Defendant)SOLICITORS: Adams Leyland (Plaintiff)
Vardenega Roberts (Fourth Defendant)
JUDGMENT
1 There are before the court in this matter two motions. The first in time was filed on behalf of the defendant, the fourth defendant, Capena Contracting Pty Limited, formerly known as Henry Walker Eltin Contracting Pty Limited, seeking orders that the plaintiff’s statement of claim be dismissed as against the fourth defendant. The application is based upon the commencement of proceedings against the fourth defendant outside the time limited by s 151D of the Workers Compensation Act 1987 in the absence of the leave of the court to do so.
2 The application filed on behalf of the plaintiff, recognising that the position taken by the fourth defendant was correct, is an application for leave to commence proceedings pursuant to the relevant section outside the three year time limit provided.
3 The determination of the defendant’s application, of course, depends upon the determination of the application for leave to proceed and, accordingly, I deal with that application first.
4 There are a number of affidavits in evidence before me that set out the circumstances of the claimed injury and the treatment provided to the plaintiff as a consequence of the injury. The material indicates that the plaintiff’s injury was alleged to have been suffered on 3 September 2003 when he was employed by the fourth defendant. He consulted a solicitor in November 2003 and, notwithstanding that he had legal assistance from that early date, action was not taken to pursue a claim for work injury damages until February 2007.
5 The circumstances…
Continue reading Blanche v North Parkes Limited
Sign in free to access the full text
- AGLC
- Blanche v North Parkes Limited [2008] NSWDC 175
- Case
- [2008] NSWDC 175
- Decision Date
CaseChat Overview and Summary
Blanche sought leave to commence proceedings against Capena Contracting Pty Limited, citing delays in the stabilisation of her injury and the assessment of her workplace injury as reasons for the delay. North Parkes Limited opposed the motion, arguing that Blanche's explanation was not satisfactory. The legal issue before the court was whether Blanche's explanation for the delay in instituting proceedings was sufficient under section 151D of the Workers Compensation Act 1987.
The court found that Blanche's explanation for the delay was satisfactory, and therefore granted leave for her to commence proceedings against Capena Contracting Pty Limited. The court noted that Blanche had provided a detailed account of the events leading to the delay, and that the delay was due to circumstances beyond her control. The court also found that North Parkes Limited's opposition to the motion was not well-founded. The court ordered that the leave granted be exercised by a specific date, and that costs of the motion be costs in the cause.
In addition to granting leave to Blanche, the court dismissed a motion brought by the fourth defendant, and ordered that costs of the motion be costs in the cause. The court's decision allows Blanche to proceed with her claim against Capena Contracting Pty Limited, and provides a clear framework for the timing of the proceedings.
Orders
Orders of the court
On the plaintiff's motion filed on 11 April 2008: 1 Leave is granted pursuant to s 151D of the Workers Compensation Act 1987 to the plaintiff to commence proceedings against Capena Contracting Pty Limited. 2 The leave granted is to be exercised by not later than 18.8.08. 3 Liberty to apply to vary this date. 4 Costs of the motion will be costs in the cause. On the fourth defendant's motion filed on 18 February 2008: 1 Motion dismissed. 2 Costs of the Motion will be costs in the cause.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.