Blackbear (NT) Pty Ltd v Want & Anor [2013] NTSC 63
PARTIES:Blackbear (NT) Pty Ltd
ACN 116 222 005
v
WANT, Gary John and
WANT, Geraldine Elizabeth
TITLE OF COURT: SUPREME COURT OF THE NORTHERN TERRITORY
JURISDICTION: SUPREME COURT OF THE TERRITORY EXERCISING TERRITORY JURISDICTION
FILE NO:18 of 2012 (21207410)
DELIVERED: 4 OCTOBER 2013
HEARING DATES: 26 SEPTEMBER 2013
JUDGMENT OF: KELLY J
REPRESENTATION:
Counsel:
Plaintiff:P Maher
First & Second Defendants: K Sibley
Solicitors:
Plaintiff:Paul Maher
First & Second Defendants: De Silva Hebron
Judgment category classification: C
Judgment ID Number: KEL13016
Number of pages: 11
IN THE SUPREME COURT
OF THE NORTHERN TERRITORY
OF AUSTRALIA
AT DARWINBlackbear (NT) Pty Ltd v Want & Anor [2013] NTSC 63
No. 18 of 2012 (21207410)
BETWEEN:
BLACKBEAR (NT) PTY LTD
CAN 116 222 005
Plaintiff
AND:
GARY JOHN WANT
First Defendant
AND:
GERALDINE ELIZABETH WANT
Second Defendant
CORAM: KELLY J
REASONS FOR JUDGMENT
(Delivered 4 October 2013)
This case concerned a dispute between the plaintiff, a building contractor, and the defendants for whom the plaintiff had contracted to build a house. There were substantial delays in the progress of the work and, on 8 July 2010, the defendants purported to terminate the contract. At the date of the purported termination, the work was almost complete and the plaintiff rendered a final series of invoices for a total of $81,245.55 being the balance of the contract price plus a claim for additional works less an allowance for some work not completed/materials not installed. The defendants refused to pay and eventually the plaintiff instituted these proceedings.
In the proceedings, the plaintiff disputed the validity of the termination and claimed the amount owing under the contract in accordance with the invoices plus interest at 20% per annum, the rate specified in the contract. With some minor exceptions, the defendants did not dispute the calculation of the contract price, but defended the plaintiff’s claim on the basis that they had offsetting claims against the plaintiff for unfinished and defective work, for breach of contract on account of the plaintiff’s delay in completing the work, and for building the house in the wrong position on the block. The defendants did not quantify these claims either before the proceedings were commenced or after and offered no evidence in support of their alleged claims at trial.
Before the matter came on for trial, the defendants proposed that the parties jointly engage an expert to determine the extent of the unfinished work, identify any defects in the work, and give evidence of what it would cost to finish the work and remedy any identified defects. The plaintiff agreed to this highly sensible proposal and the parties engaged Mr John Brears to produce a report working initially from a list supplied by the defendants of aspects of the work they claimed to be either unfinished or defective. On 11 November 2012, Mr Brears produced a draft report which, with some minor amendments, became a final report a short time later. By…
Keep reading for free
Create a free CaseChat account to read Blackbear (NT) Pty Ltd v Want and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Find similar cases
Other decisions on the same topics. Each opens in a new tab.
Details
- Case
- [2013] NTSC 63
- Decision Date
CaseChat Overview and Summary
The court held that the homeowner should pay the contractor's costs on a standard basis up until the date the expert's report was received, and on an indemnity basis thereafter. The court held that the homeowner's failure to make an offer of compromise based on the expert's report was unreasonable, as both parties knew the minimum amount payable by the homeowner was about $90,000. The homeowner's later offers were also unreasonable as they were worse than the contractor's worst possible result at trial. The court held that the homeowner's wilful blindness to the known facts about the quantum of the contractor's claim was the primary cause of the matter proceeding to trial, and the costs incurred in doing so.
Background
Background to the litigation
Decision
Reasons for decision
Ratio Decidendi