Blackbear (NT) Pty Ltd v Want

Link copied
Case Copied 12 min read

Blackbear (NT) Pty Ltd v Want & Anor [2013] NTSC 63

PARTIES:Blackbear (NT) Pty Ltd

ACN 116 222 005

v

WANT, Gary John and

WANT, Geraldine Elizabeth

TITLE OF COURT:  SUPREME COURT OF THE NORTHERN TERRITORY

JURISDICTION:  SUPREME COURT OF THE TERRITORY EXERCISING TERRITORY JURISDICTION

FILE NO:18 of 2012 (21207410)

DELIVERED:  4 OCTOBER 2013

HEARING DATES:  26 SEPTEMBER 2013

JUDGMENT OF:  KELLY J

REPRESENTATION:

Counsel:

Plaintiff:P Maher

First & Second Defendants:        K Sibley

Solicitors:

Plaintiff:Paul Maher

First & Second Defendants:        De Silva Hebron

Judgment category classification:   C

Judgment ID Number:  KEL13016

Number of pages:  11

IN THE SUPREME COURT
OF THE NORTHERN TERRITORY
OF AUSTRALIA
AT DARWIN

Blackbear (NT) Pty Ltd v Want & Anor [2013] NTSC 63

No. 18 of 2012 (21207410)

BETWEEN:

BLACKBEAR (NT) PTY LTD

CAN 116 222 005

Plaintiff

AND:

GARY JOHN WANT

First Defendant

AND:

GERALDINE ELIZABETH WANT

Second Defendant

CORAM:    KELLY J

REASONS FOR JUDGMENT

(Delivered 4 October 2013)

  1. This case concerned a dispute between the plaintiff, a building contractor, and the defendants for whom the plaintiff had contracted to build a house.  There were substantial delays in the progress of the work and, on 8 July 2010, the defendants purported to terminate the contract.  At the date of the purported termination, the work was almost complete and the plaintiff rendered a final series of invoices for a total of $81,245.55 being the balance of the contract price plus a claim for additional works less an allowance for some work not completed/materials not installed.  The defendants refused to pay and eventually the plaintiff instituted these proceedings.

  2. In the proceedings, the plaintiff disputed the validity of the termination and claimed the amount owing under the contract in accordance with the invoices plus interest at 20% per annum, the rate specified in the contract.  With some minor exceptions, the defendants did not dispute the calculation of the contract price, but defended the plaintiff’s claim on the basis that they had offsetting claims against the plaintiff for unfinished and defective work, for breach of contract on account of the plaintiff’s delay in completing the work, and for building the house in the wrong position on the block.  The defendants did not quantify these claims either before the proceedings were commenced or after and offered no evidence in support of their alleged claims at trial.

  3. Before the matter came on for trial, the defendants proposed that the parties jointly engage an expert to determine the extent of the unfinished work, identify any defects in the work, and give evidence of what it would cost to finish the work and remedy any identified defects.  The plaintiff agreed to this highly sensible proposal and the parties engaged Mr John Brears to produce a report working initially from a list supplied by the defendants of aspects of the work they claimed to be either unfinished or defective.  On 11 November 2012, Mr Brears produced a draft report which, with some minor amendments, became a final report a short time later.  By…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Blackbear (NT) Pty Ltd v Want and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details

Case
[2013] NTSC 63
Decision Date

CaseChat Overview and Summary

This case was an action by a building contractor against a homeowner for payment of the contract price plus interest, after the homeowner purported to terminate the contract for delay and defective work. The homeowner defended on the basis of alleged defects and delay in completion and sought to set off these against the contractor's claim. The parties jointly commissioned an expert to determine the extent and cost of the unfinished and defective work, which was found to be minor. The court held that the homeowner had not validly terminated the contract and gave judgment for the contractor for the full contract price plus interest. The court considered whether indemnity costs should be awarded against the homeowner on the basis that they had not quantified their claims, had not responded to settlement offers, and had acted in wilful disregard of known facts. The court held that while the homeowner had acted unreasonably in some respects, it was not prepared to award indemnity costs for the whole proceeding. The court held that indemnity costs should be awarded from the date the expert's report was received, as the homeowner had acted in wilful disregard of known facts by not making an offer of compromise based on the report, and this was the primary cause of the matter proceeding to trial.

The court held that the homeowner should pay the contractor's costs on a standard basis up until the date the expert's report was received, and on an indemnity basis thereafter. The court held that the homeowner's failure to make an offer of compromise based on the expert's report was unreasonable, as both parties knew the minimum amount payable by the homeowner was about $90,000. The homeowner's later offers were also unreasonable as they were worse than the contractor's worst possible result at trial. The court held that the homeowner's wilful blindness to the known facts about the quantum of the contractor's claim was the primary cause of the matter proceeding to trial, and the costs incurred in doing so.

Background

Background to the litigation

Decision

Reasons for decision

Ratio Decidendi

Legal principle established