PLANNING AND ENVIRONMENT COURT
OF QUEENSLAND
CITATION:
Bilinga Beach Holdings P/L v Western Downs Regional Council & Anor [2018] QPEC 34
PARTIES:
BILINGA BEACH HOLDINGS PTY LTD
(Appellant)
V
WESTERN DOWNS REGIONAL COUNCIL
(Respondent)
ERGON ENERGY CORPORATION LTD
(Co-respondent by election)
FILE NO/S:
BD 2548 of 2016
DIVISION:
Planning and Environment
PROCEEDING:
Appeal
ORIGINATING COURT:
Planning and Environment Court, Brisbane
DELIVERED ON:
6 July 2018
DELIVERED AT:
Brisbane
HEARING DATE:
3, 4, 5 and 6 April 2018, further written submission delivered by the parties on 11 and 13 April 2018
JUDGE:
Williamson QC DCJ
ORDER:
I order that:
(a) by 4 pm on 3 August 2018 the Respondent is to deliver a draft suite of conditions to the Appellant; and
(b) the appeal is to be listed for review at 9:15 am on 24 August 2018.
CATCHWORDS:
PLANNING AND ENVIRONMENT – APPEAL – applicant appeal against refusal – whether use characterised as Transport terminal – whether a decision to approve would conflict with a planning scheme – weight to be given to new planning scheme
LEGISLATION:
Sustainable Planning Act 2009, ss 326, 461 and 495
Planning and Environment Court Act 2016, s 10
CASES:
Boral Resources (Qld) Pty Ltd v Cairns City Council [1997] 2 Qd R 31
Fitzgibbons Hotels Pty Ltd v Logan City Council [1997] QPELR 208
Parmac Investments Pty Ltd v Brisbane City Council & Ors [2008] QPELR 480
SDW Projects Pty Ltd v Gold Coast City Council [2007] QPELR 24
Woolworths Ltd v Maryborough City Council (No.2) [2006] 1 Qd R 273
COUNSEL:
K Wylie for the Appellant
J Dillon for the Respondent
SOLICITORS:
DSS Law for the Appellant
King & Co for the Respondent
Introduction
This is an Applicant appeal[1] against the Respondent’s decision to refuse an impact assessable application for a Transport terminal and ancillary accommodation (8 units) on land situated at 38493 Leichardt Highway, Miles (“the land”).
[1]Pursuant to s 461(1)(a) of SPA.
The Respondent’s reasons for refusal allege that a decision to approve the development application would conflict with two planning schemes, namely the Murilla Shire 2006 planning scheme (“the 2006 planning scheme”) and the Western Downs Planning Scheme (“the 2017 planning scheme”)[2]. The conflict is said to arise for three reasons. First, the application seeks approval for an industrial activity that should be located in an industrial area rather than the rural area in which it is proposed. Second, the proposed development, being industrial in nature, will have unacceptable impacts on the amenity and character of the locality, which is rural in nature. Third, there is no overriding community need for the development.
[2]Exhibit 21, paragraphs 1, 2, 3 and 5.
It is common ground that the Sustainable Planning Act 2009 (“SPA”)[3] continues to apply to this appeal notwithstanding the enactment of the Planning Act 2016. Section 326(1)(b) of SPA mandates that the application must be refused if a decision to approve would conflict with the 2006 planning scheme, unless…
Keep reading for free
Create a free CaseChat account to read Bilinga Beach Holdings Pty Ltd v Western Downs Regional Coun... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2018] QPEC 34
- Decision Date
CaseChat Overview and Summary
The primary legal issues for the court to address were whether the proposed use of the property should be characterised as a transport terminal and whether approving such a use would conflict with the planning scheme. Additionally, the court had to consider the weight to be given to a new planning scheme that was in the process of being enacted. The court examined the evidence presented and the arguments of the parties to determine these issues.
The court found that the proposed use of the property could be characterised as a transport terminal. However, it concluded that approving this use would conflict with the planning scheme. The court also determined that the new planning scheme, although not yet in effect, should be given significant consideration. Based on these findings, the court decided that the appeal was not well founded and dismissed it.
The orders included a directive for the respondent to deliver a draft suite of conditions to the appellant by a specified date and the scheduling of the appeal for review at a later date.
Orders
Orders of the court
I order that:
(a) by 4 pm on 3 August 2018 the Respondent is to deliver a draft suite of conditions to the Appellant; and
(b) the appeal is to be listed for review at 9:15 am on 24 August 2018.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi