BHP Steel (AIS) Pty Ltd v Construction, Forestry, Mining and Energy Union

Link copied
Case Copied 48 min read

FEDERAL COURT OF AUSTRALIA

BHP Steel (AIS) Pty Ltd v Construction, Forestry, Mining & Energy Union [2000] FCA 1614

WORKPLACE RELATIONS – order by Australian Industrial Relations Commission that industrial action stop or not occur – whether order, which applied for a period of two months, was only in respect of current dispute or could also apply to a later national dispute.

WORKPLACE RELATIONS – collateral challenge as to the validity of the order open to the respondent – order not invalid by failure to identify time and date by which conduct ordered was to be done – use of the adverb “immediately” sufficiently certain – positive expression to perform work is tantamount to negative stipulation to cease industrial action –order that respondent supply a copy of order to employees within power to give incidental directions.

WORKPLACE RELATIONS – respondent failed to supply a copy of the order to employees – respondent failed to take steps to ensure the employees complied with the order.

Workplace Relations Act 1996 (Cth) s 127, s 178, s 143(1)

O’Toole v Charles David Pty Ltd (1991) 171 CLR 232
Ousley v The Queen (1997) 192 CLR 69
The Attorney-General (Cth) v Breckler (1999) 197 CLR 83
Dorsman v Nichol (1978) 20 ALR 231
Measures v McFadyen (1910) 11 CLR 723
Communications, Electrical, Electronic, Energy, Information, Postal, Plumbing and Allied Services Union of Australia v A G Coombs Fire Protection (1998) 87 IR 110
Phillip Morris Incorporated v Adam P Brown Male Fashions Pty Ltd (1981) 148 CLR 457
Re Refugee Review Tribunal;  Ex parte Aala [2000] HCA 57
Australasian Meat Industry Employees’ Union v Meneling Station Pty Ltd (1986) 16 IR 245
Microsoft Corporation v Marks (1996) 139 ALR 99
Australian Industry Group v Automotive, Food, Metals, Engineering, Printing & Kindred Industries Union [2000] FCA 629
Hillingdon London Borough Council v Cutler [1968] 1 QB 124
The Queen v Kelly; Ex part Berman (1953) 89 CLR 608
Attorney-General v Walthamstow Urban District Council (1895) 11 TLR 533

The Macquarie Dictionary, 2nd ed., 1991

Halsbury’s Laws of England, 4th ed. (Reissue)

BHP STEEL (AIS) PTY LIMITED V CONSTRUCTION, FORESTRY, MINING AND ENERGY UNION

N 150 OF 2000

JUDGE:         BEAUMONT J
DATE:           21 NOVEMBER 2000          
PLACE:         SYDNEY


IN THE FEDERAL COURT OF AUSTRALIA

NEW SOUTH WALES DISTRICT REGISTRY

N 150 OF 2000

BETWEEN:

BHP STEEL (AIS) PTY LIMITED
APPLICANT

AND:

CONSTRUCTION, FORESTRY, MINING AND ENERGY UNION
RESPONDENT

JUDGE:

BEAUMONT J

DATE OF ORDER:

21 NOVEMBER 2000

WHERE MADE:

SYDNEY

THE COURT ORDERS THAT:

1.The breaches alleged in pars 1 and 2 of the amended application have been established.

2.The claim made in par 3 of the amended application be dismissed.

3.The proceedings be stood over to Wednesday, 22 November 2000 at 9.45 a.m. for directions on the hearing of the question of penalty in respect of the breaches found.

Note:    Settlement and entry of orders is dealt with in Order 36 of the Federal Court Rules.


IN THE FEDERAL COURT OF AUSTRALIA

NEW…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read BHP Steel (AIS) Pty Ltd v Construction, Forestry, Mining and... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details

Case
[2000] FCA 1614
Decision Date

CaseChat Overview and Summary

The case of BHP Steel (AIS) Pty Ltd v Construction, Forestry, Mining and Energy Union involved a dispute between the employer, BHP Steel, and the Construction, Forestry, Mining and Energy Union, over industrial action taken by the union members. The dispute was brought before the court to determine the validity of an order made by the Commission under section 127 of an Act, which directed that industrial action stop. The Commission had issued an order requiring the union and its members to cease industrial action and comply with certain terms, in light of a 48-hour strike that had commenced due to a breakdown in negotiations.

The primary legal issue before the court was the interpretation and validity of the Commission's order, which was argued to be overly broad in its scope and application. The court was tasked with determining whether the order was properly made under the relevant statutory authority and whether it was validly directed at the union and its members. Additionally, the court had to consider whether the order was correctly interpreted to bind the union and its members to cease industrial action immediately and comply with the employer's reasonable work requirements.

The court, in its reasoning, focused on the statutory context and the language of the order itself. It found that the order was properly made under the authority of section 127 of the Act, which allows the Commission to direct that industrial action stop if it appears to the Commission that such action is occurring in relation to an industrial dispute. The court held that the order was binding on the union and its members, who were required to comply with its terms. The court rejected the employer's argument that the order should have an ambulatory operation, applying to industrial action occurring in relation to different disputes, and found that the order was limited in its scope and effect to the particular industrial dispute as it stood on 2 December 1999.

The court concluded that the breaches of the order alleged in parts 1 and 2 of the employer's amended application had been established, but dismissed the claim made in part 3 of the amended application, which sought a penalty for an alleged breach of the order on 20 January 2000. The proceedings were stood over for directions on the hearing of the question of penalty in respect of the breaches found.

The final orders of the court were that the breaches alleged in parts 1 and 2 of the amended application were established, the claim in part 3 of the amended application was dismissed, and the proceedings were to be stood over for further directions.

Orders

Orders of the court

1. The breaches alleged in pars 1 and 2 of the amended application have been established.

2. The claim made in par 3 of the amended application be dismissed.

3. The proceedings be stood over to Wednesday, 22 November 2000 at 9.45 a.m. for directions on the hearing of the question of penalty in respect of the breaches found.

Background

Background to the litigation

Decision

Reasons for decision

The Commission adjourned at 10.54 a.m., resuming at 11.58 a.m. to give its decision. At 12.03 p.m., after giving its decision, the Commission adjourned indefinitely.THE COMMISSION’S DECISION Relevantly, the Commission’s decision was as follows:“[2]The Commission has been informed that a 48 hour strike by the above members commenced at 11.00pm on 30 November 1999 following what can best be described as a breakdown in negotiations around a revised ‘survival agreement’ for the Colliery.[3]Mr Davies, on behalf of the Company submitted that the action of the members is in breach of the Disputes Settling Procedures contained in the relevant award and agreement. He described the action as a ‘wildcat strike’ occurring at a time when the colliery is ‘haemorrhaging’ financially. With the prospect of further ongoing industrial action, the orders sought were necessary to protect and ensure the viability of the business.[4]Mr Fisher who appeared for the union did not generally dispute the tenuous economic position of the colliery but complained of a heavy handed approach by management in introducing changes to the bonus scheme applicable on site.[5]He submitted that a proposed revised bonus scheme, which was recommended for acceptance by the unions district official, was rejected by a meeting of the rank and file members.[6]Exhibit BHP1 is a copy of a grievance form lodged by the union’s lodge at Tower Colliery and a copy of the response of management. It reads:‘We (the Lodge) do not believe the Company has the right to change our bonus arrangements without reaching an agreed position with the workforce. The AIRC ordered BHP and the Union to trial on 2-2-99 the BHP Group Bonus Scheme on a 6 months trial. This has continued. The Company has made a change without agreement.’[7] The Company’s response in part reads:‘During November 1999 Management and Unions have been required, due to poor business results in the financial year to date, to review all areas of the operations to develop a survival plan which helps deliver improved business forecasts for the remainder of the financial year and allows the mine to remain operational. Part of the review and negotiations was a request by Management for the development of a new bonus agreement based on the ability of the business to pay and which would therefore assist with the survival of the Colliery.‘The Colliery has been forced by market conditions to act immediately to effect survival changes. To maintain a bonus scheme the business cannot afford, will jeopardise the viability of the mine.’[8]Section 127 directs the Commissions attention to whether it appears that industrial action is happening, threatened, impending or probable.[9]Having considered the submissions of the parties in todays proceedings, I am clearly satisfied that industrial action is occurring and is probable into the future.[10]It is against the background of the submissions that I am satisfied that I should exercise the discretion contained in section 127 and make an order in this matter.[11]I do so because I consider the action complained of to be unauthorised and extremely counter productive to the viability of the Colliery.”THE COMMISSION’S ORDER

Ratio Decidendi

Legal principle established

Before describing the evidence, both affidavit and oral, bearing upon the factual issues that arise, it will be necessary to turn first to consider a preliminary issue, that is, the meaning and operation of the Order, and then, in the light of those matters, to consider the Union’s challenge to its validity.THE FIRST ISSUE: THE MEANING AND OPERATION OF THE ORDER The meaning and operation of the Order should first be considered. The material provisions of the Order were, it will be recalled, as follows:·With respect to its scope, the Order is expressed to be “binding upon”:(a)The Union and its officers;(b)The Employees.(c)BHP.·In ordering “[i]ndustrial action to stop”, the Order directs (par 3.1) that the Employees “must immediately cease and refrain from engaging in industrial action in the form of any strike, or any restriction, ban or other limitation on the performance of work”.·In this connection, the Order then directs (par 3.2) that the Employees “must make themselves available for work and perform work as [BHP] may reasonably require”.·Further in this connection, the Order directs (par 3.3) that the Union “must take any and all steps necessary and available under the rules of the [Union] to ensure that the [Employees] comply with the Order”.·In directing service of the Order, the Order directs (par 5.1) that a copy (1) “must be served by [BHP] on the [Union]” and (2) “must be supplied by the [Union] to each of the [Employees]”. It is further directed that “[s]ervice by [BHP] of this Order on the [Union] shall be sufficient service of the Order on the [Union] and its official and members”.·The Order was to take effect from 2 December 1999 and to remain in force for two months (par 6.1). In construing the Order, it is necessary to have regard to its statutory context, which, as noted, is s 127 of the Act. It will be recalled that the following are, relevantly, its principal features:·The grant to the Commission of the power, by order, to direct that “industrial action” (as defined) stop if it appears to the Commission that such is happening in relation to an “industrial dispute” (as defined) (s 127(1)).·An organisation to whom such an order is expressed to apply must comply with the Order (s 127(5)). When the Order is read in this statutory context, the Order should, in my view, receive the following interpretation of its meaning and operation:·Since the Order is expressed (par 2(a)) to bind, inter alios, the Union, the Union is bound by virtue of s 127(5)) to comply with it. The Employees, likewise, are bound to comply.·The Employees must, during the period of two months from 2 December 1999, immediately cease and refrain from engaging in “industrial action” in any of the forms specified and must make themselves available for work and perform work as BHP may reasonably require (pars 3.1, 3.2, 6.1). Although, as has been said, “industrial action” has the particular meaning provided by its statutory definition (s 4(1)), the other language of par 3.1 and par 3.2 was, in my view, intended to have its ordinary meaning. However, on behalf of BHP a claim is made, as noted, which would give these provisions an ambulatory operation, so as to pick up (albeit within the two month period) industrial action happening in relation to a different dispute. As has been seen, the amended statement of claim addressed not only the Tower Colliery dispute which was unresolved as at 2 December 1999, but also the national stoppage which later happened on 20 January 2000. This (latter) particular claim is reflected in par 3 of the amended application, whereby BHP seeks the imposition of a penalty for an alleged breach of Order 3 on 20 January 2000.