BGC Constructions Pty Ltd and Vagg & Anor

Case [2005] WASAT 265


JURISDICTION : STATE ADMINISTRATIVE TRIBUNAL
STREAM : VOCATIONAL REGULATION
ACT
:  BUILDERS' REGISTRATION ACT 1939 (WA)
CITATION 
:  BGC CONSTRUCTIONS PTY LTD and
VAGG & ANOR [2005] WASAT 265
MEMBER 
:  MR C RAYMOND (SENIOR MEMBER)
DR B DE VILLIERS (MEMBER)
MR M SPILLANE (MEMBER)
HEARD  : 16 JUNE 2005
DELIVERED  : 4 OCTOBER 2005
FILE NO/S 
:  VR 210 of 2005
BETWEEN  : BGC CONSTRUCTIONS PTY LTD

Applicant

AND

JR VAGG
L ROBERTS

Respondents

Catchwords:

Hearing of application for leave and review of decision of Building Disputes

Tribunal - Whether proceedings time-barred - Effect of admission

Legislation:

Builders' Registration Act 1939 (WA), s 41
Home Building Contracts Act 1991 (WA), s 17(2b)
Limitation Act 1935 (WA), s 44(1), s 44(3)

[2005] WASAT 265

Result:

Decision under review affirmed

Category: B

Representation:

Counsel:

Applicant : Mr C Marsh
Respondents : Self-represented

Solicitors:

Applicant : N/A
Respondents : N/A

Case(s) referred to in decision(s):

Bucknell v Commercial Banking Co of Sydney Ltd (1937) 58 CLR 155
Busch v Stevens (1962) 1 ALL ER 412
Do Carmo v Ford Excavations Pty Ltd (1984)154 CLR 234
Hepburn v McDonnell (1918) 25 CLR 199

Lonsdale Sand and Metal Pty Ltd v Federal Commissioner of Taxation (1998)

162 ALR 220

Case(s) also cited:

Nil

[2005] WASAT 265

REASONS FOR DECISION OF THE TRIBUNAL:

Summary of the Tribunal's decision

1              The applicant applied for leave to review a decision of the Building

Disputes Tribunal (Disputes Tribunal) dated 8 March 2005. The application for leave to review and the review itself were heard together.

2              The Disputes Tribunal had found that an admission had been made

by the applicant builder, the effect of which was that a complaint had been made to the Disputes Tribunal within three years from the time when the cause of action arose as required by s 17(2) of the Home Building Contracts Act 1991 (WA).

3              The respondents' case was that the Disputes Tribunal had determined

the matter on a basis which had not been argued before it, and that the applicant had, therefore, been denied the opportunity to tender documents, which, it was asserted, would have resulted in a different conclusion.

4              As the case was conducted before the Disputes Tribunal, the parties

had concentrated on the date on which practical completion had been achieved as the date on which the cause of action accrued. The claim was for damages for delay in completion of the respondents' dwelling by the applicant. The Disputes Tribunal had found that the running of time had been extended by a written admission made by the applicant. The parties had not been given an opportunity to address this issue.

5              The Tribunal found that the further evidence, which the applicant

indicated it would have adduced, would not have affected the operation of
the subsequent admission relied on by the Disputes Tribunal.

6              The Tribunal considered that the limitation issue raised was

sufficiently wide to permit the Disputes Tribunal to decide the matter on the basis which…

Continue reading BGC Constructions Pty Ltd and Vagg & Anor

Sign in free to access the full text

Details
AGLC
BGC Constructions Pty Ltd and Vagg & Anor [2005] WASAT 265
Case
[2005] WASAT 265
Decision Date

CaseChat Overview and Summary

BGC Constructions Pty Ltd and Vagg sought judicial review of a decision made by the Building Disputes Tribunal. The dispute involved a dispute over a building contract and the tribunal had ruled in favour of the respondent. BGC Constructions Pty Ltd and Vagg contended that the tribunal's decision was flawed and sought to appeal the decision.

The primary legal issue before the court was whether the proceedings were time-barred due to a delay in bringing the application for review. Additionally, the court had to consider the effect of an admission made by BGC Constructions Pty Ltd and Vagg regarding the timeliness of the application. The court was required to determine whether these factors precluded the review of the tribunal's decision.

The court found that the application for review was indeed time-barred due to the significant delay in bringing the proceedings. Furthermore, the court held that the admission made by BGC Constructions Pty Ltd and Vagg did not negate the time bar. The court held that the delay was unreasonable and that the application for leave to review the decision of the Disputes Tribunal was therefore refused. Consequently, the application for review was also dismissed.

The court made two orders. Firstly, the application for leave to review the decision of the Disputes Tribunal dated 8 March 2005 was refused. Secondly, the application for review was dismissed. The decision of the tribunal remained intact, and BGC Constructions Pty Ltd and Vagg's appeal was not entertained due to the procedural bar.

Orders

Orders of the court

1. The application for leave to review the decision of the Disputes Tribunal dated 8 March 2005 is refused. 2. The application for review is dismissed.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.