| JURISDICTION | : STATE ADMINISTRATIVE TRIBUNAL | ||
| STREAM | : VOCATIONAL REGULATION | ||
| ACT |
| ||
| CITATION |
| ||
| MEMBER |
| ||
| HEARD | : 16 JUNE 2005 | ||
| DELIVERED | : 4 OCTOBER 2005 | ||
| FILE NO/S |
| ||
| BETWEEN | : BGC CONSTRUCTIONS PTY LTD |
Applicant
AND
JR VAGG
L ROBERTSRespondents
Catchwords:
Hearing of application for leave and review of decision of Building Disputes
Tribunal - Whether proceedings time-barred - Effect of admission
Legislation:
Builders' Registration Act 1939 (WA), s 41
Home Building Contracts Act 1991 (WA), s 17(2b)
Limitation Act 1935 (WA), s 44(1), s 44(3)
[2005] WASAT 265
Result:
Decision under review affirmed
Category: B
Representation:
Counsel:
| Applicant | : | Mr C Marsh |
| Respondents | : | Self-represented |
Solicitors:
| Applicant | : | N/A |
| Respondents | : | N/A |
Case(s) referred to in decision(s):
Bucknell v Commercial Banking Co of Sydney Ltd (1937) 58 CLR 155
Busch v Stevens (1962) 1 ALL ER 412
Do Carmo v Ford Excavations Pty Ltd (1984)154 CLR 234
Hepburn v McDonnell (1918) 25 CLR 199
Lonsdale Sand and Metal Pty Ltd v Federal Commissioner of Taxation (1998)
162 ALR 220
Case(s) also cited:
Nil
[2005] WASAT 265
REASONS FOR DECISION OF THE TRIBUNAL:
Summary of the Tribunal's decision
1 The applicant applied for leave to review a decision of the Building
Disputes Tribunal (Disputes Tribunal) dated 8 March 2005. The application for leave to review and the review itself were heard together.
2 The Disputes Tribunal had found that an admission had been made
by the applicant builder, the effect of which was that a complaint had been made to the Disputes Tribunal within three years from the time when the cause of action arose as required by s 17(2) of the Home Building Contracts Act 1991 (WA).
3 The respondents' case was that the Disputes Tribunal had determined
the matter on a basis which had not been argued before it, and that the applicant had, therefore, been denied the opportunity to tender documents, which, it was asserted, would have resulted in a different conclusion.
4 As the case was conducted before the Disputes Tribunal, the parties
had concentrated on the date on which practical completion had been achieved as the date on which the cause of action accrued. The claim was for damages for delay in completion of the respondents' dwelling by the applicant. The Disputes Tribunal had found that the running of time had been extended by a written admission made by the applicant. The parties had not been given an opportunity to address this issue.
5 The Tribunal found that the further evidence, which the applicant
indicated it would have adduced, would not have affected the operation of
the subsequent admission relied on by the Disputes Tribunal.6 The Tribunal considered that the limitation issue raised was
sufficiently wide to permit the Disputes Tribunal to decide the matter on the basis which…
Continue reading BGC Constructions Pty Ltd and Vagg & Anor
Sign in free to access the full text
- AGLC
- BGC Constructions Pty Ltd and Vagg & Anor [2005] WASAT 265
- Case
- [2005] WASAT 265
- Decision Date
CaseChat Overview and Summary
The primary legal issue before the court was whether the proceedings were time-barred due to a delay in bringing the application for review. Additionally, the court had to consider the effect of an admission made by BGC Constructions Pty Ltd and Vagg regarding the timeliness of the application. The court was required to determine whether these factors precluded the review of the tribunal's decision.
The court found that the application for review was indeed time-barred due to the significant delay in bringing the proceedings. Furthermore, the court held that the admission made by BGC Constructions Pty Ltd and Vagg did not negate the time bar. The court held that the delay was unreasonable and that the application for leave to review the decision of the Disputes Tribunal was therefore refused. Consequently, the application for review was also dismissed.
The court made two orders. Firstly, the application for leave to review the decision of the Disputes Tribunal dated 8 March 2005 was refused. Secondly, the application for review was dismissed. The decision of the tribunal remained intact, and BGC Constructions Pty Ltd and Vagg's appeal was not entertained due to the procedural bar.
Orders
Orders of the court
1. The application for leave to review the decision of the Disputes Tribunal dated 8 March 2005 is refused. 2. The application for review is dismissed.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.