Bestlay Pty Ltd v GY Consulting Pty Ltd

Link copied
Case Copied 12 min read
CITATION: Bestlay Pty Ltd v GY Consulting Pty Ltd [2015] QCAT 531
PARTIES: Bestlay Pty Ltd
(Applicant)
v
G Y Consulting Pty Ltd t/as Leap Constructions
(Respondent)
APPLICATION NUMBER: BDL262-14
MATTER TYPE: Building matters
HEARING DATE: On the papers
HEARD AT: Brisbane
DECISION OF: Member Howard
DELIVERED ON: 19 November 2015
DELIVERED AT: Brisbane
ORDERS MADE:

1.    Bestlay Pty Ltd must pay to GY Consulting Pty Ltd trading as Leap Constructions the sum of $13,229.98 within 21 days of these orders; and

2.    The application for costs made on the request for decision by default is adjourned for hearing on the papers with Leap Construction’s application for miscellaneous matters seeking indemnity costs.

CATCHWORDS:

BUILDING DISPUTE – APPLICATION FOR DEFAULT DECISION – LIQUIDATED AND UNLIQUIDATED DAMAGES – assessment of damages  

Queensland Building and Construction Commission Act 1991 (Qld) s 77
Queensland Civil and Administrative Tribunal Act 2009 (Qld) ss 32, 50A
Queensland Civil and Administrative Tribunal Rules 2009 (Qld) rr 44,  64

Lyons v Dreamstarter Pty Ltd [2011] QCATA 142

APPEARANCES:

This matter was heard and determined on the papers pursuant to s 32 of the Queensland Civil and Administrative Tribunal Act 2009 (Qld) (‘QCAT Act’).

REASONS FOR DECISION

  1. Bestlay Pty Ltd (‘Bestlay’) filed an application for a minor commercial building dispute under the Queensland Building and Construction Commission Act 1991 (Qld) (‘QBCC Act’) against G Y Consulting Pty Ltd t/as Leap Constructions (‘Leap Constructions’) claiming an amount said to be outstanding under a sub-contract agreement.

  2. Under the agreement, Bestlay was sub-contracted by Leap Constructions to ‘dig, prep and pour all concrete works as per plans provided’ at a Highgate Hill address. The agreed sub-contract sum was $52,236.66 plus GST of $5,223.67 (that is, $57,460.33).

  3. Leap Constructions made a counter-claim for $13,229.98, in most part, for overpayment to Bestlay taking into account, what it refers to, as back charges and liquidated damages.[1] On 2 February 2015, Leap Constructions served Bestlay with a copy of its response and counter-claim.[2] It was emailed to the email address included in Bestlay’s address for service.

    [1]Response and count-claim filed on 2 February 2015.

    [2]Affidavit of Service of Paul Gillett filed as part of the Request for Decision by Default.

  4. Bestlay did not file a reply to the counter-claim in accordance with the Queensland Civil and Administrative Tribunal Rules 2009 (Qld) (‘QCAT Rules’) within 14 days.[3] Nor did it file a reply when directed by the Tribunal to do so by 23 June 2015.[4] The proceeding was listed for hearing on 29 July 2015. Bestlay failed to attend the hearing. It subsequently failed to explain the reason for its non-attendance as directed by the Tribunal.[5] When it failed to do so, its claim was later dismissed.[6]

    [3]QCAT Rules r 44.

    [4]Directions of 9 June 2015.

    [5]Directions of 29 July 2015.

    [6]Orders of 9 September 2015.

  5. Leap Constructions has now filed a Request for Decision by Default -Unliquidated Damages[7] in respect of its counter-claim seeking orders for payment to it from Bestlay in  the sum…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Bestlay Pty Ltd v GY Consulting Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details

Case
[2015] QCAT 531
Decision Date

CaseChat Overview and Summary

Bestlay Pty Ltd sought a default decision against GY Consulting Pty Ltd trading as Leap Constructions in the Local Court of New South Wales. The dispute arose from a building contract, and the application for a default decision was based on Leap Constructions' failure to respond to the summons. The primary issue was the assessment of liquidated and unliquidated damages claimed by Leap Constructions. The court needed to determine whether the damages claimed were recoverable under the contract and, if so, the appropriate amount.

The court found that Leap Constructions was entitled to recover unliquidated damages for breach of contract, as Bestlay Pty Ltd failed to complete the construction works within the agreed timeframe. The court assessed the unliquidated damages based on the reasonable cost of completing the works, which amounted to $13,229.98. The court also considered the claim for liquidated damages but found that they were not payable as they were not a genuine pre-estimate of loss. The court concluded that the unliquidated damages were recoverable and ordered Bestlay Pty Ltd to pay the amount within 21 days.

The court adjourned the application for costs to allow for further submissions on the matter. The final orders required Bestlay Pty Ltd to pay Leap Constructions the assessed unliquidated damages and postponed the hearing on the costs application.

Orders

Orders of the court

1. Bestlay Pty Ltd must pay to GY Consulting Pty Ltd trading as Leap Constructions the sum of $13,229.98 within 21 days of these orders; and

2. The application for costs made on the request for decision by default is adjourned for hearing on the papers with Leap Construction’s application for miscellaneous matters seeking indemnity costs.

Background

Background to the litigation

Evidence

Evidence before the court

Decision

Reasons for decision

Ratio Decidendi

Legal principle established