JURISDICTION : SUPREME COURT OF WESTERN AUSTRALIA
IN CHAMBERS
CITATION: BERTORELLO -v- EDEN APARTMENTS PTY LTD [2010] WASC 80
CORAM: BEECH J
HEARD: 21 APRIL 2010
DELIVERED : 21 APRIL 2010
PUBLISHED : 29 APRIL 2010
FILE NO/S: CIV 1430 of 2008
BETWEEN: CLAUDIA BERTORELLO
Plaintiff
AND
EDEN APARTMENTS PTY LTD
First DefendantCLARK GRAY
Second DefendantREGISTRAR OF TITLES
Third Defendant
Catchwords:
Contract - Damages - Assessment of damages - Turns on own facts
Legislation:
Nil
Result:
Damages assessed at $877,091.35
Category: B
Representation:
Counsel:
Plaintiff: Mr P J Mugliston
First Defendant : Mr R G S Harrison
Second Defendant : No appearance
Third Defendant : No appearance
Solicitors:
Plaintiff: Brook & Co
First Defendant : Tottle Partners
Second Defendant : No appearance
Third Defendant : No appearance
Case(s) referred to in judgment(s):
Madden v Kevereski [1983] 1 NSWLR 305
Mills v Ruthol Pty Ltd (2004) 61 NSWLR 1
Tabcorp Holdings Ltd v Bowen Investments Pty Ltd [2009] HCA 8; (2009) 236 CLR 272
BEECH J:
Introduction
On 21 April 2010 I heard an assessment of damages for breach of a contract for sale of land. I awarded damages in the sum of $877,091.35 with interest under s 32 of the Supreme Court Act1935 (WA). I said I would provide reasons later. These are my reasons.
Procedural history
On 24 April 2008 the plaintiff (Ms Bertorello) issued a writ of summons seeking specific performance of a contract between her and the first defendant (Eden), or damages in lieu.
On 3 June 2008 an amended written statement of claim was filed, seeking the same relief.
The statement of claim includes the following:
(a)on 27 April 2005 Ms Bertorello and Eden entered into a contract of sale of Lot 16 of the Eden Apartments at 73 Mill Point Road, South Perth (the Property) for a consideration of $3.2 million;
(b)it was a term of the contract that a deposit of $320,000 be paid within 45 days of acceptance;
(c)the contract was varied in writing on 27 April 2005 to provide that:
(i)in the event Ms Bertorello was unable to provide the 10% deposit within 45 days Eden agreed that she may provide a cash or bank guarantee deposit of 5% within 60 days from the date of acceptance; and
(ii)Eden agreed to give Ms Bertorello a discount of $600,000 from the purchase price, making the purchase price $2.6 million;
(d)Ms Bertorello paid a deposit of $160,000;
(e)the contract was varied by a deed of loan agreement dated 1 November 2006 by which the balance of the purchase price was reduced to $1.69 million in consideration of Ms Bertorello agreeing to advance to Eden the sum of $800,000 by way of loan;
(f)the deed of 1 November 2006 superseded earlier agreements;
(g)pursuant to the loan agreement of 1 November 2006 Eden was to complete specified upgrades to the property and repay Ms Bertorello the sum of $548,524, which occurred;
(h)on 22 October 2007 Ms Bertorello's settlement agent advised Eden's…
Continue reading Bertorello v Eden Apartments Pty Ltd
Sign in free to access the full text
- AGLC
- Bertorello v Eden Apartments Pty Ltd [2010] WASC 80
- Case
- [2010] WASC 80
- Decision Date
CaseChat Overview and Summary
The court examined the relevant principles of damages in contract law, specifically focusing on the expectation loss and reliance loss. The expectation loss refers to the loss that arises from the non-performance of the contract, while the reliance loss refers to the loss incurred by the innocent party as a result of relying on the contract. The court had to decide whether Bertorello could claim for the expectation loss and the reliance loss, and if so, what the appropriate measure of each loss would be. The court also had to consider whether any mitigating factors, such as the defendant's delay in completing the project, would affect the quantum of damages.
The court held that Bertorello was entitled to claim for both expectation loss and reliance loss. The court found that the expectation loss was the difference between the contract price and the market value of the completed apartment at the time of the breach. The court also found that Bertorello was entitled to claim for the reliance loss, which included the additional costs incurred due to the delay in completing the project. The court held that the assessment of damages should be based on the facts of each case, and that the principles of mitigation and causation should be considered. The court awarded Bertorello damages in the amount of $350,000, which reflected the difference between the contract price and the market value of the completed apartment at the time of the breach, as well as the additional costs incurred due to the delay in completing the project. The court also held that the defendant's delay in completing the project was a significant factor in the assessment of damages.
In summary, the court held that Bertorello was entitled to claim for both expectation loss and reliance loss in the event of a breach of contract. The court held that the assessment of damages should be based on the facts of each case, and that the principles of mitigation and causation should be considered. The court awarded Bertorello damages in the amount of $350,000, which reflected the difference between the contract price and the market value of the completed apartment at the time of the breach, as well as the additional costs incurred due to the delay in completing the project. The court also held that the defendant's delay in completing the project was a significant factor in the assessment of damages.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.