JURISDICTION : SUPREME COURT OF WESTERN AUSTRALIA
IN CHAMBERS
CITATION: BAYSIDE CIVIL & DRAINAGE PTY LTD -v- MARINESTAR HOLDINGS PTY LTD [2000] WASC 78
CORAM: MASTER BREDMEYER
HEARD: 2 FEBRUARY 2000
DELIVERED : 4 FEBRUARY 2000
PUBLISHED : 28 MARCH 2000
FILE NO/S: CIV 2252 of 1999
BETWEEN: BAYSIDE CIVIL & DRAINAGE PTY LTD (ACN 065 070 733)
Plaintiff
AND
MARINESTAR HOLDINGS PTY LTD (ACN 057 584 577)
Defendant
Catchwords:
Summary judgment - Moneys due under a building contract AS 2124-92, cl 42.1, cl 42.2, cl 42.10, cl 44.6, cl 47.1 - Moneys due under a progress certificate - Effect of correction of payment certificate - Set offs by principal - Adjustment on completion of work taken out of hands of the contractor - Arbitration clause
Legislation:
Trade Practices Act, s 52
Result:
Appeal allowed
Representation:
Counsel:
Plaintiff: Mr M C Goldblatt
Defendant: Ms P E Cahill
Solicitors:
Plaintiff: Freehill Hollingdale & Page
Defendant: Pullinger Stewart
Case(s) referred to in judgment(s):
Blue Chip Pty Ltd v Concrete Constructions (1996) 13 BCL 31
Devaugh v Lamac Developments Pty Ltd [1999] WASCA 280
Fancourt v Mercantile Credits Ltd (1983) 154 CLR 87
IBM Australia Ltd v National Distribution Services (1991) ATPR 41-094
Lamac Developments Pty Ltd v Devaugh Pty Ltd [1999] WASC 76
Re Concrete Constructions [1997] 1 Qd R 6
Case(s) also cited:
Algons Engineering Pty Ltd v Abi Group Contractors Pty Ltd (1997) 14 BCL 215
Commonwealth v Verwayen (1990) 170 CLR 394
Lewkowski v Bergalin Pty Ltd, unreported; SCt of WA; Library No 7675; 26 May 1989
Moscow Narodny Bank v Mosbert Finance (Aust) Pty Ltd [1976] WAR 109
Whitehall Holdings Pty Ltd v Custom Credit Corp Ltd, unreported; SCt of WA; Library No 9189; 13 December 1991
MASTER BREDMEYER: This is an application by the plaintiff for summary judgment. The plaintiff was a contractor engaged in doing earthworks etcetera for the defendant at Busselton under a written contract AS 2124‑1992. A similar contract was considered by the Full Court in Devaugh v Lamac Developments Pty Ltd [1999] WASCA 280. The plaintiff's claim was for moneys due under two progress certificates as follows:
| "Progress Claim 2 | small lots | 14.7.99 | 29,702.39 |
| Progress Claim 2 | large lots | 14.7.99 | 232,193.11 |
| Progress Claim 3 | large lots | 14.9.99 | 102,615.32 |
| Progress Claim 3 | small lots | 14.9.99 | 103.01 |
| Total | $364,407.81" |
These are progress certificates issued by the superintendent's representative under cl 42.1 and prima facie they should be paid without deduction. The Devaugh case is Full Court authority for that.
What are the defences raised? The first defence relates to amendment certificates. There are two certificates, both called 3A and dated 6 December 1999, which is after the action commenced and after the application for summary judgment was filed. The one for the large lots is for $53,415.31. It reduces the large lots certificate 3 of 14 September 1999 from $102,615.32 to $53,415.31. The difference is liquidated damages, 82 days at $600 per day equals $49,200. Some explanation is given in an…
Keep reading for free
Create a free CaseChat account to read Bayside Civil & Drainage Pty Ltd v Marinestar Holdings Pty L... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2000] WASC 78
- Decision Date
CaseChat Overview and Summary
The legal issues before the court involved the interpretation of clauses 42.1, 42.2, 42.10, 44.6, and 47.1 of AS 2124-92, particularly in relation to the correction of a payment certificate and the effect of set-offs by the principal. Additionally, the court needed to consider the adjustment of monies due upon the completion of work and its removal from the contractor's possession. The existence of an arbitration clause in the contract also raised questions regarding the court's jurisdiction to hear the matter.
The court held that the defendant's arguments regarding the set-offs and adjustments were misplaced, as they did not align with the clear terms of the contract. The court found that the correction of the payment certificate did not alter the sums due to the plaintiff, and that the defendant's attempts to make set-offs were not supported by the contract provisions. Furthermore, the court determined that the adjustment of monies due upon completion of work should be made in accordance with the contract terms, without regard to the removal of work from the contractor's hands. The arbitration clause did not prevent the court from granting summary judgment in this instance, as the issues raised were not within the scope of the arbitration agreement.
The court granted summary judgment in favour of the plaintiff, Bayside Civil & Drainage Pty Ltd, and ordered the defendant, Marinestar Holdings Pty Ltd, to pay the full amount claimed, together with interest and costs.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi