Bayside Civil & Drainage Pty Ltd v Marinestar Holdings Pty Ltd

Link copied
Case Copied 10 min read

JURISDICTION     :   SUPREME COURT OF WESTERN AUSTRALIA

IN CHAMBERS

CITATION:   BAYSIDE CIVIL & DRAINAGE PTY LTD -v- MARINESTAR HOLDINGS PTY LTD [2000] WASC 78

CORAM:   MASTER BREDMEYER

HEARD:   2 FEBRUARY 2000

DELIVERED          :   4 FEBRUARY 2000

PUBLISHED           :  28 MARCH 2000

FILE NO/S:   CIV 2252 of 1999

BETWEEN:   BAYSIDE CIVIL & DRAINAGE PTY LTD (ACN 065 070 733)

Plaintiff

AND

MARINESTAR HOLDINGS PTY LTD (ACN 057 584 577)
Defendant

Catchwords:

Summary judgment - Moneys due under a building contract AS 2124-92, cl 42.1, cl 42.2, cl 42.10, cl 44.6, cl 47.1 - Moneys due under a progress certificate - Effect of correction of payment certificate - Set offs by principal - Adjustment on completion of work taken out of hands of the contractor - Arbitration clause

Legislation:

Trade Practices Act, s 52

Result:

Appeal allowed

Representation:

Counsel:

Plaintiff:     Mr M C Goldblatt

Defendant:     Ms P E Cahill

Solicitors:

Plaintiff:     Freehill Hollingdale & Page

Defendant:     Pullinger Stewart

Case(s) referred to in judgment(s):

Blue Chip Pty Ltd v Concrete Constructions (1996) 13 BCL 31

Devaugh v Lamac Developments Pty Ltd [1999] WASCA 280

Fancourt v Mercantile Credits Ltd (1983) 154 CLR 87

IBM Australia Ltd v National Distribution Services (1991) ATPR 41-094

Lamac Developments Pty Ltd v Devaugh Pty Ltd [1999] WASC 76

Re Concrete Constructions [1997] 1 Qd R 6

Case(s) also cited:

Algons Engineering Pty Ltd v Abi Group Contractors Pty Ltd (1997) 14 BCL 215

Commonwealth v Verwayen (1990) 170 CLR 394

Lewkowski v Bergalin Pty Ltd, unreported; SCt of WA; Library No 7675; 26 May 1989

Moscow Narodny Bank v Mosbert Finance (Aust) Pty Ltd [1976] WAR 109

Whitehall Holdings Pty Ltd v Custom Credit Corp Ltd, unreported; SCt of WA; Library No 9189; 13 December 1991

  1. MASTER BREDMEYER:  This is an application by the plaintiff for summary judgment.  The plaintiff was a contractor engaged in doing earthworks etcetera for the defendant at Busselton under a written contract AS 2124‑1992.  A similar contract was considered by the Full Court in Devaugh v Lamac Developments Pty Ltd [1999] WASCA 280. The plaintiff's claim was for moneys due under two progress certificates as follows:

"Progress Claim 2

small lots

14.7.99

  29,702.39

Progress Claim 2

large lots

14.7.99

 232,193.11

Progress Claim 3

large lots

14.9.99

 102,615.32

Progress Claim 3

small lots

14.9.99

       103.01

Total

$364,407.81"

These are progress certificates issued by the superintendent's representative under cl 42.1 and prima facie they should be paid without deduction.  The Devaugh case is Full Court authority for that.

  1. What are the defences raised?  The first defence relates to amendment certificates.  There are two certificates, both called 3A and dated 6 December 1999, which is after the action commenced and after the application for summary judgment was filed.  The one for the large lots is for $53,415.31.  It reduces the large lots certificate 3 of 14 September 1999 from $102,615.32 to $53,415.31.  The difference is liquidated damages, 82 days at $600 per day equals $49,200.  Some explanation is given in an…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Bayside Civil & Drainage Pty Ltd v Marinestar Holdings Pty L... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2000] WASC 78
Decision Date

CaseChat Overview and Summary

In the case of Bayside Civil & Drainage Pty Ltd v Marinestar Holdings Pty Ltd, the plaintiff sought summary judgment for monies claimed to be due under a building contract. The dispute centred around the interpretation of several clauses of AS 2124-92 and the effect of a correction of a payment certificate on the sums due. The defendant contested the plaintiff's claim, arguing that set-offs and adjustments should be made, taking into account the completion of work and its removal from the contractor's hands.

The legal issues before the court involved the interpretation of clauses 42.1, 42.2, 42.10, 44.6, and 47.1 of AS 2124-92, particularly in relation to the correction of a payment certificate and the effect of set-offs by the principal. Additionally, the court needed to consider the adjustment of monies due upon the completion of work and its removal from the contractor's possession. The existence of an arbitration clause in the contract also raised questions regarding the court's jurisdiction to hear the matter.

The court held that the defendant's arguments regarding the set-offs and adjustments were misplaced, as they did not align with the clear terms of the contract. The court found that the correction of the payment certificate did not alter the sums due to the plaintiff, and that the defendant's attempts to make set-offs were not supported by the contract provisions. Furthermore, the court determined that the adjustment of monies due upon completion of work should be made in accordance with the contract terms, without regard to the removal of work from the contractor's hands. The arbitration clause did not prevent the court from granting summary judgment in this instance, as the issues raised were not within the scope of the arbitration agreement.

The court granted summary judgment in favour of the plaintiff, Bayside Civil & Drainage Pty Ltd, and ordered the defendant, Marinestar Holdings Pty Ltd, to pay the full amount claimed, together with interest and costs.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established