CITATION:Barkly Regional Council v Harvey Developments (NT) Pty Ltd & Anor [2024] NTSC 100
PARTIES:BARKLY REGIONAL COUNCIL
(ABN 32 171 281 456)
v
HARVEY DEVELOPMENTS (NT) PTY LTD (ABN 33 142 861 612)
and
BADDOCK, Deon
TITLE OF COURT: SUPREME COURT OF THE NORTHERN TERRITORY
JURISDICTION: SUPREME COURT exercising Territory jurisdiction
FILE NO:2024-02069-SC
DELIVERED: 4 December 2024
HEARING DATE: 10 October 2024
JUDGMENT OF: Brownhill J
CATCHWORDS:
BUILDING AND CONSTRUCTION – Adjudication – Judicial review – Procedural fairness – Asserted failure to consider submissions about an offsetting claim – Whether adjudicator failed to consider a central tenet of the matter – There was no offsetting claim founded upon any identified legal basis – Ground of review not made out.
BUILDING AND CONSTRUCTION – Adjudication – Judicial review – Payment claims – Procedural fairness – Asserted failure to consider evidence – No inference that the case was not considered – No jurisdictional error – Ground of review not made out.
Construction Contracts (Security of Payments) Regulations 2005 (NT) r 11.
Alliance Contracting Pty Ltd v James [2014] WASC 212, Brenner v First Artists’ Management Pty Ltd [1993] 2 VR 221, Cooper & Oxley Builders Pty Ltd v Steensma [2016] WASC 386, James Engineering Pty Ltd v ABB Australia Pty Ltd (2019) 42 NTLR 51, Laing O’Rourke Australia Construction Pty Ltd v H&M Engineering & Construction Pty Ltd [2010] NSWSC 818, referred to.
REPRESENTATION:
Counsel:
Plaintiff:S Heidenreich
First Defendant: JW Roper SC
Second Defendant: No appearance
Solicitors:
Plaintiff:Povey Stirk
First Defendant: Piper Alderman
Second Defendant: No appearance
Judgment category classification: B
Judgment ID Number: Bro2412
Number of pages: 30
IN THE SUPREME COURT
OF THE NORTHERN TERRITORY
OF AUSTRALIA
AT DARWINBarkly Regional Council v Harvey Developments (NT) Pty Ltd & Anor [2024] NTSC 100
No. 2024-02069-SC
BETWEEN:
BARKLY REGIONAL COUNCIL
(ABN 32 171 281 456)
Plaintiff
AND:
HARVEY DEVELOPMENTS (NT) PTY LTD (ABN 33 142 861 612)
First Defendant
AND:
DEON BADDOCK
Second Defendant
CORAM: BROWNHILL J
REASONS FOR JUDGMENT
(Delivered 4 December 2024)
This is an application for judicial review of a determination by an adjudicator under the Construction Contracts (Security of Payments) Act 2004 (NT) (‘the Act’). The issues are whether the adjudicator denied the plaintiff procedural fairness by failing to consider evidence it had provided to the adjudicator, and/or failing to consider its submission, characterised as ‘an offsetting claim’, that it had already paid enough for the construction work done on the site.
Background
The following facts are not in dispute.
The plaintiff (‘Council’) is a local government council constituted under s 14(b) of the Local Government Act 2019 (NT) for the Barkly region.
In late 2020, Council put out a Request for Tender for the design and construction of the Ali Curung Youth Centre (‘Project’).
On 22 February 2021, the tender for the Project was awarded to the defendant (‘HD’).
On that date, the parties executed a written contract relating to the Project (‘Contract’). The Contract provided that HD was to…
Keep reading for free
Create a free CaseChat account to read Barkly Regional Council v Harvey Developments (NT) Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2024] NTSC 100
- Decision Date
CaseChat Overview and Summary
The primary legal issues before the court were whether the adjudicator committed a jurisdictional error by failing to properly consider the Council's submissions and evidence. The Council argued that the adjudicator's determination was flawed because it did not address the Council's submission that the already-paid amounts were adequate, which the Council considered an offsetting claim. The Council also contended that the adjudicator did not sufficiently consider the evidence it provided, which was necessary for a fair adjudication. The court needed to examine the adjudicator's reasons and decide if they demonstrated an adequate consideration of the Council's submissions and evidence.
In its reasoning, the court found that the Council's claim that the amounts already paid were sufficient did not constitute an offsetting claim with a legal basis that the adjudicator was required to address. The court noted that there was no identified legal basis for this claim and that it did not form part of the adjudication process as required by the Act. The court also concluded that the adjudicator's reasons demonstrated a consideration of the Council's concerns, even if they did not align with the Council's perspective. The court held that the adjudicator's determination did not evidence a failure to consider the Council's submissions or evidence to a degree that would constitute a jurisdictional error.
As a result, the court dismissed the application for judicial review. The adjudicator's determination was upheld, and no grounds for overturning the decision were found. The court found that the adjudicator had sufficiently engaged with the Council's submissions and evidence, and therefore, the Council's claims of procedural unfairness were unfounded.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
In addressing item C.1, the adjudicator did not repeat Council’s submission that the amounts already paid by Council were appropriate and sufficient, but made reference to the ‘concerns’ raised in the three statements referred to by Council in its response regarding item C.1, said he had considered the ‘concerns’ raised, said he did not see how they demonstrated the calculation of the value of the item under the Contract, and so gave them little weight (at [111]). He also said that Council had not provided any submissions in respect of the costs the subject of item C.1 (at [115]). Consideration In response to Council’s argument as set out in paragraph [31] above, HD argued that, in rejecting Council’s submission that the Contract price had not been varied and individually assessing each item of the payment claim, the adjudicator had adequately dealt with Council’s response, including the submission that the payments already made by Council for the work done were appropriate and sufficient. There is some force in this argument, but there is a more compelling basis upon which to conclude that the adjudicator did not commit jurisdictional error in the way asserted by Council under this ground, namely that, for the reasons set out below, the submissions that the amounts already paid were ‘adequate and sufficient’ was not an offsetting claim founded upon any identified legal basis which the adjudicator was required to address. Reliance was placed by Council on the decision in James Engineering Pty Ltd v ABB Australia Pty Ltd (2019) 42 NTLR 51 (‘James’), submitting that Council’s submissions in the response to the effect that Council had already paid money to HD which exceeded the value of any work undertaken prior to the payment claim was an ‘offsetting claim’ akin to that in James. In James, the Court of Appeal dismissed an appeal against a decision of the Supreme Court granting an order in the nature of certiorari in respect of an adjudicator’s determination because the adjudicator had failed to deal with the merits of the principal’s defence to the contractor’s payment claim. The Court of Appeal confirmed that the principal’s claim to set off liquidated damages against the payment claim had not been considered on its merits because the adjudicator had erroneously determined that a claim to set off liquidated damages required a separate payment claim to be made by the principal. Contrary to that view, the Court of Appeal held (at [30]) that the claim to set off liquidated damages was ‘a live issue’ in the contractor’s adjudication application.[3] The Court of Appeal held (at [34]-[35]) that a respondent to an application may use its counterclaim or set-off as a defence to the payment claim made against it and the adjudicator is required to take into account the respondent’s response, including the merits of any counterclaim or set-off in reaching its determination.[4] In James, the principal’s response to the payment claim had identified a contractual obligation on the contractor to pay liquidated damages of a specified amount to the principal, the adjudication application referred to the claim for liquidated damages as part of the payment dispute and made submissions as to the merits of the claim. The principal’s response to the adjudication application contained a seven page submission regarding the principal’s claim for liquidated damages which asked the adjudicator to reject the contractor’s contentions about the liquidated damages claim and allow the principal’s set-off of those damages. Because of his erroneous view that a claim for liquidated damages required a separate payment claim to be made by the principal, which had not been done, the adjudicator ignored that claim when determining the payment claim. The Court of Appeal upheld the trial Judge’s finding that the adjudicator had misconstrued the nature of his functions under the Act and failed to deal with the merits of the principal’s claimed set off, which had been raised as a defence to the payment claim, and thereby made a jurisdictional error.