CITATION: Barclay Mowlem Construction v Tesrol Walsh Bay [2004] NSWSC 716 revised - 10/12/2004 HEARING DATE(S): 30 July 2004 JUDGMENT DATE:
13 August 2004JURISDICTION:
EquityJUDGMENT OF: McDougall J DECISION: See paras [26] and [27] of judgment CATCHWORDS: BUILDING AND CONSTRUCTION - Building and Construction Industry Security of Payment Act 1999 (NSW) - where plaintiff moves for summary judgment - whether defendant has arguable defence to preclude plaintiff from obtaining summary judgment - where document alleged to be payment schedule did not indicate the payment defendant intended to make - whether defendant provided payment schedule for purposes of s 14 - requirements of payment schedules - whether question to be determined on final hearing and not by way of summary judgment - estoppel by representation - where alleged representation that parties take no further step in response to claim until negotiations take place - whether defendant relied upon representation to its detriment by taking no further steps under Act in respect of payment claim - whether estoppel defence prohibited by s 34 - whether question to be resolved on application for summary judgment LEGISLATION CITED: Building and Construction Industry Security of Payment Act 1999 (NSW)
Trades Practices Act 1974CASES CITED: Multiplex Constructions Pty Ltd v Luikens and Anor [2003] NSWSC 1140 PARTIES :
Barclay Mowlem Construction Ltd (Plaintiff)
Tesrol Walsh Bay Pty Ltd (Defendant)FILE NUMBER(S): SC 55043/04 COUNSEL: M Rudge SC / D Sibtain (Plaintiff)
G Inatey SC / D Miller (Defendant)SOLICITORS: Corrs Chambers Westgarth (Plaintiff)
Malcolm Johns & Company (Defendant)
BARCLAY MOWLEM CONSTRUCTION LTD v TESROL WALSH BAY PTY LTD
55043/04
INDEX to JUDGMENT
First issue: was there a payment schedule? 3 Second issue: estoppel 16 Third issue: section 52 23 Conclusion and Order 26
IN THE SUPREME COURT
OF NEW SOUTH WALES
EQUITY DIVISION
TECHNLOGY AND CONSTRUCTION LIST
McDougall J
13 August 2004
55043/04 Barclay Mowlem Construction Ltd v Tesrol Walsh Bay Pty Ltd
JUDGMENT
1 HIS HONOUR: The plaintiff (“Barclay Mowlem”) undertook building work for the defendant (“Tesrol”). On 7 May 2004, Barclay Mowlem served a payment claim on Tesrol. The claim was said to be made under s 13 of the Building and Construction Industry Security of Payment Act 1999 (NSW) (“the Act”). The amount claimed was $1,111,923. Barclay Mowlem says that Tesrol did not provide it with a payment schedule in accordance with s 14 of the Act. Accordingly, Barclay Mowlem says, Tesrol is liable to pay the amount claimed. Barclay Mowlem has sued to recover that amount as a debt. It moves for summary judgment.
2 Tesrol says that there are three arguable defences:
(1) It did, within the time permitted by s14 of the Act, provide Barclay Mowlem with a payment schedule for the purposes of s 14.
(2) Alternatively, Barclay Mowlem is estopped from asserting that Tesrol did not do so.
(3) Alternatively, Barclay Mowlem has engaged in misleading and deceptive conduct, in breach of s 52 of the Trades Practices Act 1974 (Cth) (“the TP…
Keep reading for free
Create a free CaseChat account to read Barclay Mowlem Construction Ltd v Tesrol Walsh Bay Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2004] NSWSC 716
- Decision Date
CaseChat Overview and Summary
The court examined the requirements of a payment schedule under the Act, concluding that the document in question did not clearly indicate the payment the defendant intended to make. The court held that whether the document constituted a payment schedule should be determined at a final hearing, not through a summary judgment application. The court also considered the defence of estoppel by representation, finding that there was an alleged representation that the parties would not take any further steps in response to the claim until negotiations took place. The court noted that the defendant had relied on this representation to its detriment by not taking further steps under the Act regarding the payment claim. However, the court determined that section 34 of the Act prohibited the use of estoppel as a defence, and thus, this matter should also be resolved at a final hearing rather than through an application for summary judgment.
The court denied the plaintiff's application for summary judgment, ruling that the issues regarding the validity of the payment schedule and the applicability of estoppel by representation were not suitable for resolution on an application for summary judgment. These matters required a more comprehensive examination at a final hearing. The court's decision ensured that the substantive issues would be thoroughly explored, providing both parties with an opportunity to present their arguments and evidence in detail.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.