Babhoota v AMT Grand Homes Pty Ltd

Link copied
Case Copied 28 min read

Civil and Administrative Tribunal


New South Wales

  • Amendment notes
Medium Neutral Citation: Babhoota v AMT Grand Homes Pty Ltd [2022] NSWCATCD 217
Hearing dates: 13 October 2022
Date of orders: 18 October 2022
Decision date: 18 October 2022
Jurisdiction:Consumer and Commercial Division
Before: D Ziegler, Senior Member
Decision:

1. Within 14 weeks of the date of these orders the respondent is to carry out the works specified in the Schedule attached to these orders, in a proper and workmanlike manner.

2. The application is otherwise dismissed.

3.  If there is a costs application, the costs applicant is to file and serve submissions and documents on the costs application by 14 days from the date of these orders.

4. The costs respondent is to file and serve submissions and documents on the costs application by 28 days from the date of these orders.

5. The costs applicant is to file and serve costs submissions in reply by 35 days from the date of these orders.

6. The costs submissions of the parties are to state whether the parties seek an oral hearing on the issue of costs, or consent to the costs application being determined on the papers in accordance with s 50 (2) of the Civil and Administrative Tribunal Act 2013 (NSW).

7. The Tribunal may determine it appropriate to deal with any costs application on the papers and without a further oral hearing.

Catchwords:

BUILDING AND CONSTRUCTION – Home Building Act 1989 (NSW) – Defective building work – Variation of contract – whether exchange of emails satisfied requirement for variation to be in writing and signed – expert evidence.

Legislation Cited:

Electronic Transactions Act 2000 (NSW)

Home Building Act 1989 (NSW)

Cases Cited:

Makita (Aust) Pty Ltd v Sprowles (2001) 52 NSWLR 705; [2001] NSWCA 305

Paraiso v CBS Build Pty Ltd [2020] NSWSC 190

Texts Cited:

Nil

Category:Principal judgment
Parties: Rajeev Babhoota (Applicant)
AMT Grand Homes Pty Ltd (First Respondent)
Representation: Self-represented (Applicant)
Birch Partners (Respondent)
File Number(s): HB 22/11283
Publication restriction: Nil

REASONS FOR DECISION

  1. This is a residential building dispute involving construction of a new dwelling in Dural, New South Wales.

  2. In this decision any reference to “the homeowner” is a reference to the applicant, Mr Bahboota, and any reference to “the builder” is a reference to the respondent, AMT Grand Homes Pty Ltd.

  3. Mr Taki is a director of the builder.

  4. Numbering used in this decision to identify alleged building defects mirrors the numbering used in the joint conclave report prepared by the parties’ respective experts.

  5. On 15 December 2018 the parties entered a contract to perform residential building works (the Contract). The Contract is in the form of the Master Builders Association BC 4 standard form contract. Mr Bahboota’s wife Savita Bahboota is also a party to the Contract but she was not named as a party to these proceedings.

  6. The works involved demolition of an existing structure and construction of a new dwelling. The Contract price was $870,500.

  7. Attached to the…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Babhoota v AMT Grand Homes Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2022] NSWCATCD 217
Decision Date

CaseChat Overview and Summary

Babhoota v AMT Grand Homes Pty Ltd involved a dispute between the applicant and the respondent regarding the completion of a home construction project. The applicant alleged that the respondent failed to complete the works in accordance with the contract and that the respondent had breached the Home Building Act 1989 (NSW) by engaging in defective building work. The matter was heard in the Civil and Administrative Tribunal of New South Wales.

The primary legal issue the court had to address was whether an exchange of emails satisfied the requirement for variations to be in writing and signed, as stipulated by the Home Building Act 1989 (NSW). Additionally, the court had to determine whether the respondent had failed to complete the works in accordance with the contract. The applicant also sought an order for the respondent to complete the works to the required standard.

In its decision, the court found that the exchange of emails did not meet the statutory requirement for variations to be in writing and signed. The court emphasised the importance of strict compliance with the statutory requirements to protect consumers from defective building work. However, the court held that the respondent had completed the works in accordance with the contract and dismissed the applicant's claim for defective building work. The court ordered the respondent to complete the works specified in the Schedule attached to the orders, within a specified timeframe. The court also made orders regarding the costs of the application.

The court ordered the respondent to carry out the specified works within 14 weeks of the date of the orders. The respondent was also ordered to file and serve submissions and documents on any costs application within a specified timeframe. The court noted that it may determine any costs application on the papers and without a further oral hearing. The court dismissed the applicant's application for an order for defective building work and any other relief sought by the applicant.

Orders

Orders of the court

1. Within 14 weeks of the date of these orders the respondent is to carry out the works specified in the Schedule attached to these orders, in a proper and workmanlike manner.

2. The application is otherwise dismissed.

3. If there is a costs application, the costs applicant is to file and serve submissions and documents on the costs application by 14 days from the date of these orders.

4. The costs respondent is to file and serve submissions and documents on the costs application by 28 days from the date of these orders.

5. The costs applicant is to file and serve costs submissions in reply by 35 days from the date of these orders.

6. The costs submissions of the parties are to state whether the parties seek an oral hearing on the issue of costs, or consent to the costs application being determined on the papers in accordance with s 50 (2) of the Civil and Administrative Tribunal Act 2013 (NSW).

7. The Tribunal may determine it appropriate to deal with any costs application on the papers and without a further oral hearing.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.