DISTRICT COURT OF QUEENSLAND
CITATION:
B J and S Paterson Pty Ltd (t/a Cooloola Civil Constructions) v Eleventh Trail Pty Ltd [2009] QDC 380
PARTIES:
B J and S Paterson Pty Ltd ACN 058587318 (t/a “Cooloola Civil Constructions”)
(Plaintiff/ Respondent)
and
Eleventh Trail Pty Ltd ACN 007 280 355
(Defendant/ Applicant)
FILE NO/S:
D 312 of 2009
DIVISION:
District Court of Queensland, Maroochydore
PROCEEDING:
Civil Proceeding
ORIGINATING COURT:
District Court at Maroochydore
DELIVERED ON:
4 December 2009
DELIVERED AT:
District Court at Maroochydore
HEARING DATE:
24 November 2009
JUDGE:
J.M. Robertson DCJ
ORDER:
The application is dismissed with costs.
CATCHWORDS:
BUILDING AND CONSTRUCTION – Payment Claim - Building and Construction Industry Payments Act 2004 - Adjudicator's determination - Adjudication certificate and judgement; whether claim upon which the adjudicator’s decision is based was void; whether judgment and enforcement warrant should be permanently stayed.
Legislation:
Building and Construction Industry Payments Act 2004 (Qld)
Cases Considered:
Brodyn Pty Ltd and Davenport (2003) NSWSC 1019
Roadtek, Department of Main Road and Davenport (2006) QSC 47
R. J. Neller Building Pty Ltd and Ainsworth [2008] QCA 397
Brodyn Pty Ltd and Davenport & Anor (2004) NSWCA 394
Baxbex Pty Ltd and Bickle [2009] QSC 194
Neumann Contractors Pty Ltd v Peet Beachton Syndicate Ltd [2009] QSC 376
Surfabear Pty Ltd and G J Drainage and Concrete Construction Pty Ltd [2009] QSC 308
COUNSEL:
Mr P. Telford for the Plaintiff/ Respondent
Mr M. Evans for the Defendant/ Applicant
SOLICITORS:
Garland Waddington for the Plaintiff/ Respondent
Sykes Pearson Miller for the Defendant/ Applicant
The defendant (Eleventh Trail) filed an application on 16 November 2009 which sought (inter alia) the following orders:
(1) That the judgment filed 5 November 2009 and execution thereof be permanently stayed;
(2) Such further or other orders as the court may deem meet; …
It is common ground that the plaintiff (Paterson) and the defendant (Eleventh Trail) entered into a construction contract on 10 December 2008 whereby Paterson agreed to carry out certain building and construction works at Eleventh Trail’s residential development at Lillis Road, Gympie. It is common ground that the contract is a “construction contract” for the purposes of the Building and Construction Industry Payments Act (2004) (The Act).
In September 2009, Paterson issued to Eleventh Trail a payment claim no. 8 said to be made under the Act for the sum of $134,655.22. Eleventh Trail disputed the validity of the payment claim and served on Paterson a payment schedule pursuant to s 18 of the Act in which it proposed to pay none of the amount claimed. Paterson then elected, pursuant to s 20(2)(a)(ii) of the Act to make an adjudication application under s 21(1)(a)(ii).
An adjudicator (Mr Welsh) was appointed and received and considered an adjudication application with submissions from Paterson, and an adjudication response and submissions from Eleventh Trail. On 23 October 2009 Mr Welsh…
Keep reading for free
Create a free CaseChat account to read B J and S Paterson Pty Ltd (t/a Cooloola Civil Constructions... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2009] QDC 380
- Decision Date
CaseChat Overview and Summary
The primary legal issues before the court were whether the payment claim upon which the adjudicator's decision was based was void and, if not, whether the judgment and enforcement warrant should be permanently stayed. The court considered the statutory framework of the Building and Construction Industry Payments Act 2004, which mandates prompt and fair adjudication processes to ensure timely payments in the construction industry. The court also examined the principles of administrative law, particularly the grounds on which a party may challenge an adjudicator's determination. The court's task was to balance the urgency of payment in the construction industry with the respondent's right to challenge the validity of the claim.
The court found that the respondent had not established that the payment claim was void, nor had they demonstrated any basis for the judgment and enforcement warrant to be permanently stayed. The court emphasised the importance of adhering to the statutory processes established under the Building and Construction Industry Payments Act 2004, highlighting the legislature's intent to facilitate timely payments. Given the respondent's failure to substantiate their objections, the court dismissed the application with costs. This decision underscores the importance of parties adhering to the legislative framework designed to support efficient payment processes in the construction industry.
Orders
Orders of the court
The application is dismissed with costs.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi