Reported Decision:
(2004) 13 ANZ Insurance Cases 61-611
Court of Appeal
CITATION: AXA GLOBAL RISKS (UK) LTD v HASKINS CONTRACTORS PTY LTD [2004] NSWCA 138 HEARING DATE(S): 24 March 2004 JUDGMENT DATE:
6 May 2004JUDGMENT OF: Mason P at 1; Bryson JA at 87; Windeyer J at 88 DECISION: Appeal upheld in part (see par 86) CATCHWORDS: INSURANCE CONTRACT - whether damages occurred during the period of insurance - distinction between damaged property and property liable to become damaged - whether "condition when new" confined recovery to reconstruction with original faults - whether supervisory costs were necessarily incurred - whether losses were a 'single event' or 'series'. PARTIES :
AXA GLOBAL RISKS (UK) LTD
HASKINS CONTRACTORS PTY LTDFILE NUMBER(S): CA 40591/03 COUNSEL: Appellant: J E Marshall SC/ D S Weinberger
Respondent: J Kelly SC/ M OrlovSOLICITORS: Appellant: Moray & Agnew
Respondent: Abadee, Dresdner & Freeman
LOWER COURTJURISDICTION: District Court LOWER COURT FILE NUMBER(S): DC 10568/01 LOWER COURT
JUDICIAL OFFICER :Puckeridge DCJ
CA 40591/2003
DC 10568/2001MASON P
BRYSON JA
WINDEYER JThursday 6 May 2004
BACKGROUND:
The respondent (the insured) entered into a building contract to construct a subdivision project at Bayview. The construction of two timber crib retaining walls was sub-contracted to Terra Services Pty Ltd. The eastern wall was completed in October 1999 and the western wall completed in March 2000. During March 2000 various defects and non-conformities were identified with the construction of the walls. Terra Services was advised that rectification work was required, however, it failed to carry it out and later went into liquidation. As time progressed, further damage was observed in the walls, including the splitting and crushing of headers.
The walls were demolished and reconstructed by the insured. Under a Contract Works and Liability Insurance Policy (the Policy), the appellant (the insurer) had provided the insured with insurance for the period 31 December 1999 to 31 December 2000.The insurer accepted liability for the western wall but submitted that the Policy did not respond in relation to the eastern wall because the relevant physical loss or damage occurred before the period of insurance.
At trial, Puckeridge DCJ held that the insured property fell within the scope of the insuring clause and that the insured was entitled to be indemnified for the total cost of rebuilding both the eastern and western walls.
HELD: per Mason P (Bryson JA and Windeyer J agreeing) upholding the appeal in part and upholding the cross-appeal:
1. The policy responded to the eastern wall
There was no proof of splitting or cracking before March 2000. There is a critical distinction between property that is liable to become damaged and property that is damaged. Although the eastern wall was defective when built, until the defects manifested themselves in injury to the structure there was no “physical damage to the property insured” within the meaning of the policy.
2. The appellant’s submission on the quantum issue…
Keep reading for free
Create a free CaseChat account to read AXA Global Risks (UK) Ltd v Haskins Contractors Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2004] NSWCA 138
- Decision Date
CaseChat Overview and Summary
The central legal issues before the Court of Appeal were whether the damage to the concrete structure occurred during the currency of the insurance policy, the proper interpretation of the policy's "condition when new" exclusion, and whether the costs of supervision incurred by Haskins were necessarily incurred within the meaning of the policy. The court also considered whether the losses constituted a "single event" or a "series of events" for the purposes of the policy's excess provisions.
The Court of Appeal analysed the distinction between property that was damaged during the policy period and property that was merely liable to become damaged due to inherent defects. It found that the primary judge had erred in concluding that the damage occurred during the policy period, holding that the defects were present from the time of construction and did not constitute damage that arose during the currency of the policy. The court further interpreted the "condition when new" exclusion to mean that recovery was confined to reconstruction with the original faults, and that the policy did not cover the cost of rectifying inherent defects. Regarding supervisory costs, the court determined that these were not necessarily incurred within the meaning of the policy. The court also addressed the "single event" versus "series of events" issue, finding that the defects arose from a single cause.
The appeal was upheld in part, with the Court of Appeal overturning the primary judge's decision on the key issues of when the damage occurred and the scope of the policy's coverage for pre-existing defects.
Orders
Orders of the court
Appeal upheld in part (see par 86)
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.