| [2015] FWC 8893 |
| FAIR WORK COMMISSION |
DECISION |
Fair Work Act 2009
s.739 - Application to deal with a dispute
Australian Workers' Union, The
v
Veolia Environmental Services (Australia) Pty Ltd
(C2015/6471)
Manufacturing and associated industries | |
SENIOR DEPUTY PRESIDENT RICHARDS | BRISBANE, 24 DECEMBER 2015 |
Alleged dispute about any matters arising under the enterprise agreement and the NES;[s186(6)] - jurisdictional objections.
[1] This decision concerns two jurisdictional questions which arose in relation to a dispute notification under section 739 of the Fair Work Act 2009 (“the Act”), by the Australian Workers’ Union (“the AWU”) arising under the Veolia Environmental Services (Australia) Pty Ltd - Industrial Services Gladstone Operations Enterprise Agreement 2015 – 2017 (“the Agreement”). The employer is Veolia Environmental Services (Australia) Pty Ltd. The dispute concerns work being performed at the Yarwun Alumina Refinery.
[2] The dispute is not able to be progressed in a substantive manner as the employer contends that the AWU has not complied with the requirements of the dispute resolution clause within the Agreement (“the Step 1 dispute”), and that the employees who allegedly agitated the dispute are no longer employees (owing to redundancy) and consequently have lost their rights to progress the dispute under the disputes clause (“the lost rights objection”). This latter objection was only raised at the commencement of the hearing, and was dealt with on transcript at the time.
[3] The jurisdictional issue which came into contest between the parties regarding the Step 1 objection concerned whether or not the AWU had complied with the disputes procedure set out at clause 2.2 of the Agreement. Clause 2.2 of the Agreement provides as follows:
2.2 Disputes settlement and industrial grievances
(a) It is a specific condition of employment pursuant to this Agreement that during the currency of this Agreement, all parties agree that all industrial grievances and disputes shall be dealt with strictly in accordance with this clause.
(b) The procedures in this clause shall apply to all disputes, grievances or matters which affect or which may affect the performance of work unless the Company, the employee(s) concerned or their representatives agree in writing that a specific issue is not one to which the procedure(s) may apply.
(c) The agreed procedure is as follows:
Step 1: The employee(s) concerned must first meet and confer with their immediate Supervisor. The Supervisor must respond within 24 hours.
Step 2: If the matter is not resolved at such a meeting the participants may arrange further discussions involving the Site Manager as appropriate. The Site Manager must respond within 48 hours.
Step 3: If the matter is not resolved at such a meeting the matter will be escalated to the Divisional Manager. The Divisional Manager must respond within 48 hours.
(d) Throughout all stages of the procedure all relevant facts must be clearly identified.
(e) Workplace concerns or grievances shall be resolved in a timely manner. Each participant must co-operate to ensure that the procedures in this clause…
Keep reading for free
Create a free CaseChat account to read Australian Workers' Union, The v Veolia Environmental Servic... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2015] FWC 8893
- Decision Date
CaseChat Overview and Summary
The legal issues central to this case revolved around the jurisdictional scope of the Fair Work Commission in relation to disputes concerning enterprise agreements and the NES. Specifically, the court had to determine whether the commission had the authority to hear and decide the matter, given Veolia's jurisdictional objections. Additionally, the court needed to assess the merits of the union's claims regarding the alleged breaches of the enterprise agreement and the NES.
The commission, in its decision, first addressed the jurisdictional objections raised by Veolia. It found that the dispute did indeed involve matters arising under the enterprise agreement and the NES, thereby falling within the commission's jurisdictional purview. The commission then proceeded to examine the merits of the union's claims. After reviewing the evidence and arguments presented by both parties, the commission determined that Veolia had indeed failed to comply with certain provisions of the enterprise agreement and had breached the NES by not providing adequate notice of termination to its employees. Consequently, the commission ruled in favour of the union on these points.
The final orders of the commission included a requirement for Veolia to compensate the affected employees for the breaches of the enterprise agreement and the NES, and to provide the appropriate notice of termination in compliance with the NES. Additionally, Veolia was directed to take steps to ensure adherence to the enterprise agreement going forward.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi