| [2019] FWC 6767 |
| FAIR WORK COMMISSION |
DECISION |
Fair Work Act 2009
s.739 - Application to deal with a dispute in accordance with a Dispute Settlement Procedure
Australian Rail, Tram and Bus Industry Union
v
Transit Systems West Services Pty Ltd T/A Transit Systems West Services
(C2019/3235)
COMMISSIONER CAMBRIDGE | SYDNEY, 11 OCTOBER 2019 |
Dispute settlement procedure - dispute about interpretation of clause providing for additional payment when rostered off on a public holiday - no agreement as to any determination of alleged contractual obligation arising from extraneous materials - interpretation made in support of application.
[1] This Decision is made in respect of an application that was taken under section 739 of the Fair Work Act 2009 (the Act) for the Fair Work Commission (the Commission) to deal with a dispute in accordance with a Dispute Settlement Procedure (DSP). The application was lodged at Sydney on 23 May 2019, and it was made by the Australian Rail, Tram and Bus Industry Union (the RTBU or the Union) and taken against Transit Systems West Services Pty Ltd T/A Transit Systems West Services (the employer or Transit Systems).
[2] The application was advanced pursuant to a DSP which can be found at clause 85 of the State Transit Authority Bus Operations Enterprise (State) Award 2018 (the Copied State Award). The Parties agreed that the relevant procedural requirements of the DSP contained in the Copied State Award had been followed to the extent necessary to permit the application to proceed to a Determination before the Commission. Further, there was no contest that the Commission was duly empowered by the DSP to resolve the identified dispute by providing a Determination of the interpretation to be given to particular terms contained in the Copied State Award. However, Transit Systems asserted, inter alia, that the Commission did not have jurisdiction to Determine an issue of contest identified in the application and which involved asserted obligations arising from documents that were extraneous to the Copied State Award.
[3] The application was the subject of unsuccessful conciliation proceedings held on 31 May and 27 June 2019. The matter has subsequently advanced to arbitration proceedings which involved a Hearing conducted in Sydney on 10 September 2019.
[4] At the Hearing, the Commission granted permission pursuant to s. 596 of the Act, over the objections of the RTBU, for Transit Systems to be represented by lawyers or paid agents. Mr M Diamond, National Lawyer, appeared for the RTBU, and the employer was represented by Mr M Moir, barrister, instructed by Mr M Ushakoff, solicitor from Meridian Lawyers. The Parties introduced evidence by way of witness statements with each Party calling one respective witness.
[5] Mr Diamond and Mr Moir both made oral submissions in elaboration of documentary material that each had filed on behalf of the respective Parties.
Background
[6] There was little factual contest between the Parties about the circumstances which gave rise to the dispute in this matter. The dispute arose from a decision taken by Transit Systems…
Keep reading for free
Create a free CaseChat account to read Australian Rail, Tram and Bus Industry Union v Transit Syste... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Details
- Case
- [2019] FWC 6767
- Decision Date
CaseChat Overview and Summary
The central legal issue before the Commission was the proper interpretation of the clause in question. The union maintained that the clause explicitly provided for additional payments when employees were scheduled off on public holidays. Conversely, the employer asserted that the clause did not obligate them to make such payments and that any such obligations arose from extraneous materials not part of the employment agreement. The Commission had to determine the true meaning of the clause and whether the employer was indeed bound to make additional payments under the terms of the agreement.
The Commission examined the text of the clause and the surrounding context, including the language used and the overall purpose of the agreement. The Commission found that the clause was clear and unambiguous in its requirement for additional payments when employees were rostered off on public holidays. Given the lack of agreement between the parties on any determination of the alleged contractual obligation arising from extraneous materials, the Commission proceeded to interpret the clause in support of the union's application. The Commission held that the employer was obligated to make the additional payments as stipulated in the clause.
The Fair Work Commission ordered that Transit Systems West Services Pty Ltd was required to make the additional payments to the employees as outlined in the interpreted clause of the employment agreement. This decision provided clarity on the contractual obligations of the employer in relation to public holiday rostering.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence before the court
Decision
Reasons for decision
Ratio Decidendi