| [2022] FWC 2448 |
| FAIR WORK COMMISSION |
| DECISION |
Fair Work Act 2009
s.604 - Appeal of decisions
Australian Manufacturing Workers' Union
v
Opal Packaging Australia Pty Ltd
(C2022/5814)
| VICE PRESIDENT HATCHER | SYDNEY, 14 SEPTEMBER 2022 |
Appeal against decision [2022] FWC 1840 of Commissioner McKinnon at Sydney on 20 July 2022 in matter number C2022/1228
The Australian Manufacturing Workers’ Union (AMWU) has lodged an appeal, for which permission is required, against a decision made by Commissioner McKinnon on 20 July 2022.[1] The decision concerned an application by the AMWU under s 739 of the Fair Work Act 2009 (FW Act) for the Commission to deal with a dispute with Opal Packaging Australia Pty Ltd (Opal) concerning whether Opal could, under the Orora Fibre Packaging National Enterprise Agreement 2019 (Agreement), proceed with a proposal to change the pattern of working hours for maintenance employees at Opal’s site at its Revesby plant.
The current arrangement at Revesby is that employees, who under the Agreement have a 35-hour week, are rostered to work 37 hours per week, with 2 hours being banked and taken as time off at a later time. Opal proposed that, from 1 January 2022, this be altered so that employees would be rostered for only 35 ordinary hours per week plus 10 minutes rostered overtime per day for the purpose of a handover from one shift to the next. The purpose of the proposed change was to align the working hours of Revesby employees with those of production and despatch employees.
The AMWU disputed the introduction of this change. It contended that the change would be unsafe, and could not be made under clause 5(b) of the Agreement (which preserves “historical site differentials”) and clause 9.1(m) (which prohibits further claims). Once the AMWU disputed the matter, clause 15.3 operated to preserve the status quo until the dispute was resolved pursuant to the dispute resolution procedure prescribed by clause 15. The dispute was ultimately arbitrated by the Commissioner pursuant to that procedure.
In her decision, the Commissioner rejected the AMWU’s contentions that the proposed change would be unsafe or that it was prohibited by clause 9.1(m).[2] The Commissioner accepted the AMWU’s contention that the current working hours arrangement for maintenance employees at the Revesby plant was an historical site difference to which clause 5 of the Agreement applies. Relevantly, clause 5(b) of the Agreement provides:
(b) The parties agree that interstate site differentials will be maintained for the period of the Agreement and recognise that Wage Parity across Orora Fibre packaging sites is an issue between the parties. The parties agree to consult with each other at a national level to review their respective positions on Wage Parity prior to the next EBA. Initial consultation will commence 3 months after approval of the agreement by FWC, except that where within a state a site is identified as having a significant wages anomaly, then the parties shall meet within one month of the Agreement being accepted by the members to ensure…
Keep reading for free
Create a free CaseChat account to read Australian Manufacturing Workers' Union v Opal Packaging Aus... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Find similar cases
Other decisions on the same topics. Each opens in a new tab.
Details
- Case
- [2022] FWC 2448
- Decision Date
CaseChat Overview and Summary
The court considered whether the AMWU had demonstrated that it had a reasonable prospect of success on the merits of the appeal, and whether the balance of convenience favoured a stay. The court found that there was some ambiguity in the Agreement and that the AMWU had a reasonable prospect of success in arguing that the term "period of the Agreement" should be interpreted as the period during which the Agreement remains in operation, rather than the period until the nominal expiry date. The court also found that the balance of convenience favoured a stay because the appeal was expected to be determined quickly, and denying a stay would result in unnecessary disruption for the employees if the appeal was ultimately successful. The court granted the AMWU’s application for a stay of the Commissioner’s decision pending the outcome of the appeal.
Background
Background to the litigation
Decision
Reasons for decision
Ratio Decidendi