SUPREME COURT OF VICTORIA
COURT OF APPEAL
S APCI 2015 0099
| AUSTRALIAN DREAM HOMES PTY LTD (ACN 089 782 990) | Applicant |
| V | |
| ILIJA STOJANOVSKI and ZAGORKA STOJANOVSKI | Respondents |
---
| JUDGES: | ASHLEY, OSBORN and KAYE JJA |
| WHERE HELD: | MELBOURNE |
| DATE OF HEARING: | 31 May 2016 |
| DATE OF JUDGMENT: | 10 June 2016 |
| MEDIUM NEUTRAL CITATION: | [2016] VSCA 133 |
| JUDGMENT APPEALED FROM: | Stojanovski v Australian Dream Homes [2015] VSC 404 (John Dixon J) |
---
ADMINISTRATIVE LAW – Appeal from Victorian Civil and Administrative Tribunal – Domestic building dispute – Termination of contract by owners on failure of builder to rectify defects specified in default notice – Clause 20 of Victorian Master Builders Association New Homes Contract (HC-6 addition 1 - 2009) – Meaning of ‘substantial breach’ in clause 20.1 – Whether owners acted unreasonably in terminating contract based on default notice allowing 14 days to rectify defects – Remediation works estimated to take 6 weeks
---
| APPEARANCES: | Counsel | Solicitors |
| For the Applicant | R De Meyrick | Lovegrove Smith & Cotton Solicitors |
| For the Respondents | R Andrew and N Phillpott | Noble Lawyers |
ASHLEY JA:
I agree in the reasons of Kaye JA, and with the orders which his Honour proposes.
OSBORN JA:
I agree with Kaye JA. The trial judge was correct to conclude that the Tribunal erred in law in reaching conclusions that were not open to it.
KAYE JA:
The applicant seeks leave to appeal a decision of a justice of the Trial Division,[1] which allowed an appeal from a decision of the Victorian Civil and Administrative Tribunal (‘the Tribunal’) that the respondents pay the applicant the sum of $21,914.85.[2]
[2]Australian Dream Homes Pty Ltd v Stojanovski [2014] VCAT 975 (‘Tribunal decision’).
The proceedings before the Tribunal concerned a domestic building contract dated 21 August 2011 by which the applicant agreed to construct a new single storey brick veneer dwelling for the respondents in Reservoir for the sum of $320,000. The building works commenced in late October or early November 2011 with a prescribed construction period of 296 days. The building permit for the works was issued on 16 October 2011, so that the earliest due date for completion of the works was 7 August 2012.
Clause 8.4 of the building contract required the applicant to bring the works to completion on the completion date. By cl 10.1 of the contract, the applicant gave to the respondents the warranties, contained in s 8 of the Domestic Building Contracts Act, 1995, including that:
The Builder will carry out the Works in a proper and workmanlike manner and in accordance with the Plans and Specifications set out in the contract.
By cl 11.8 of the building contract, the respondents agreed to make progress payments to the applicant as follows:
Deposit $16,000 Base stage $32,000 Frame stage $48,000 Lock up stage $112,000 Fixing stage $80,000 Completion stage $32,000
Clause 20.1 provided for the respondents to serve a default notice, the relevant parts of which…
Keep reading for free
Create a free CaseChat account to read Australian Dream Homes Pty Ltd v Stojanovski and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2016] VSCA 133
- Decision Date
CaseChat Overview and Summary
The court was tasked with interpreting the meaning of ‘substantial breach’ in the context of the contract, specifically whether the builder's failure to rectify defects within the 14-day period specified in the default notice constituted such a breach. Furthermore, the court had to consider whether Mr Stojanovski's decision to terminate the contract was reasonable, given that the remediation works were estimated to take six weeks to complete. The court examined the language of the contract, the conduct of the parties, and the reasonable expectations of both the builder and the homeowner.
The court found that the term ‘substantial breach’ was not limited to immediate rectification but encompassed a reasonable timeframe for the builder to address the defects. Given the significant time difference between the 14-day notice and the estimated six weeks required for remediation, the court concluded that the builder's failure to rectify the defects within the notice period did not amount to a substantial breach. Additionally, the court held that Mr Stojanovski's decision to terminate the contract based on the default notice was unreasonable, as it did not allow for a reasonable period to address the defects. Consequently, the court dismissed the builder's appeal, upholding the VCAT's decision to affirm the termination of the contract.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.