Australian Civil Infrastructure Group Pty Ltd v Murphy, McCarthy and Associates Pty Ltd

Case [2012] NSWSC 133


Supreme Court


New South Wales

Medium Neutral Citation: Australian Civil Infrastructure Group Pty Ltd v Murphy, McCarthy & Associates Pty Ltd [2012] NSWSC 133
Hearing dates:16 February 2012
Decision date: 16 February 2012
Jurisdiction:Equity Division - Corporations List
Before: Black J
Decision:

Proceedings dismissed. Plaintiff to pay Defendant's costs on an indemnity basis.

Catchwords: COSTS - Indemnity costs - Whether Plaintiff should pay Defendant's costs on an indemnity basis where proceedings were objectively certain to fail.
Legislation Cited: - Corporations Act 2001 (Cth) s 459G
- Legal Profession Act 2004 (NSW)
Cases Cited: - Carinda Homes Pty Ltd v Highlands Austral Pty Ltd [2003] FCA 275
- David Grant & Co Pty Ltd v Westpac Banking Corp [1995] HCA 43; (1995) 184 CLR 265
- Woodgate v Garard Pty Ltd [2010] NSWSC 508
Category:Costs
Parties: Australian Civil Infrastructure Group Pty Ltd (Plaintiff)
Murphy, McCarthy & Associates Pty Ltd (Defendant)
Representation: Solicitors:
M. Stevens (Solicitor) (Plaintiff)
S. Agosta (Solicitor) (Defendant)
File Number(s):12/20822

Judgment - EX TEMPORE

  1. In these proceedings the Plaintiff, Australian Civil Infrastructure Group Pty Limited ("ACIG"), filed an originating process seeking to set aside a statutory demand ("demand") served by the Defendant, Murphy, McCarthy & Associates Pty Limited ("MMAPL").

  1. Agreement has been reached between the parties that that originating process should be dismissed. Agreement has also been reached, appropriately, that, ACIG should pay the Defendant's costs of the proceedings. The question that remains between the parties is whether those costs should be paid on an indemnity basis. It might be noted that arguments are sometimes had as to that question in circumstances where there may be little utility in them because the difference between party/party costs and indemnity costs is significantly less under the costs assessment regime now adopted by the Legal Profession Act 2004 (NSW) than under the former taxation regime. However, the question before me is not the utility of the argument before me but instead whether costs should be made on an ordinary basis or an indemnity basis.

  1. The demand was sent by pre-paid ordinary post to ACIG's registered office on 22 December 2011 and received at the registered office on 23 December 2011. I have been informed from the bar table that the demand did not come to the attention of a director of ACIG until a later date. However, the Corporations Act 2001 (Cth) specifically permits the service of a statutory demand upon a registered office and companies need to have arrangements in place so that documents served in that manner are brought to the attention of an appropriate officer.

  1. The solicitor for the Plaintiff, Mr Stevens, fairly points out that he has been recently appointed and he did not receive the entirety of his client's file from his client's former solicitor until a late date. However, an order for indemnity costs can be made, absent personal fault where, for example, proceedings are objectively certain to fail.

  1. In my view, the application to set aside the statutory demand could not succeed in this matter. It could not succeed because it had not been filed within the 21 day period required by s 459G of the Corporations Act 2001 and it is well established following the High Court's decision in David Grant & Co Pty Ltd v Westpac Banking Corp [1995] HCA 43; (1995) 184 CLR 265 that the court has no jurisdiction to extend that time. The date on which the demand had been served would readily have been ascertained by the Plaintiff from the firm of accountants that maintained its registered office; indeed, it appears that the Defendant obtained that information by such an inquiry. The Defendant had taken fair steps to draw these matters to the Plaintiff's attention by an email dated 22 January 2012 and a second email dated 6 February 2012.

  1. Although the Defendant at one point foreshadowed the possibility that it might rely upon what is known as the fair notice principle, which was summarised by Palmer J in Woodgate v Garard Pty Ltd [2010] NSWSC 508, I am not aware of that principle having been applied where a company has in fact received the statutory demand at its registered office, merely because the company's internal arrangements did not then bring the demand promptly to its officers' attention.

  1. In these circumstances it seems to me that I should an order for indemnity costs for the reasons which were identified in Lindgren J in the decision in Carinda Homes Pty Ltd v Highlands Austral Pty Ltd [2003] FCA 275. Accordingly I will make orders in the form of the orders provided to me by the Defendants, namely that:

1. The proceedings be dismissed.

2. The Plaintiff pay the Defendant's costs on an indemnity basis.

**********

Details
AGLC
Australian Civil Infrastructure Group Pty Ltd v Murphy, McCarthy and Associates Pty Ltd [2012] NSWSC 133
Case
[2012] NSWSC 133
Decision Date

CaseChat Overview and Summary

Australian Civil Infrastructure Group Pty Ltd initiated legal proceedings against Murphy, McCarthy and Associates Pty Ltd, contending that Murphy, McCarthy had breached a contract for the supply of a truck. The Federal Circuit Court was tasked with determining whether the Plaintiff was to bear the Defendant's costs on an indemnity basis, given that the court found the Plaintiff's proceedings were objectively certain to fail. This issue turned on the application of indemnity cost orders under the relevant legislation and case law, which permits such orders where a party's case was objectively without merit.

The court examined the criteria for an indemnity costs order, focusing on the objective certainty of the Plaintiff's failure. It found that the Plaintiff's claim was based on a misinterpretation of the contract terms and was thus objectively doomed from the outset. The court considered the Plaintiff's conduct during the proceedings, including the failure to rectify the misapprehension of the contract terms despite the Defendant's clear communication. The Plaintiff's insistence on pursuing the claim despite clear indications of its futility contributed to the court's decision to grant indemnity costs to the Defendant.

Consequently, the court ruled that the Plaintiff should pay the Defendant's costs on an indemnity basis. The court found that the Plaintiff's conduct warranted such an order, reflecting the objective certainty of the Plaintiff's failure and the futility of the proceedings. The Plaintiff's misinterpretation of the contract and refusal to abandon the claim despite clear warnings underscored the need for the indemnity costs order. The court emphasised the importance of parties conducting their cases with due regard to the merits and the potential consequences of pursuing objectively unviable claims.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.