FEDERAL COURT OF AUSTRALIA
Australian Building and Construction Commission v Construction, Forestry, Mining and Energy Union (The Kane Constructions Case) [2017] FCA 168
File number: VID 261 of 2016 Judge: JESSUP J Date of judgment: 1 March 2017 Catchwords: INDUSTRIAL LAW – Industrial action – Stop-work meetings and walk-offs on construction sites – Whether industrial action engaged in by employees – Whether meetings and walk-offs organised by union organisers – Whether contraventions arose out of same course of conduct – Whether organisers liable as accessories – Whether organisers knew that employees were covered by enterprise agreement – Whether organisers’ conduct attributed to union.
INDUSTRIAL LAW – Adverse action – Industrial activity – Right of entry – Union organisers entered construction sites in defiance of builder’s right of entry procedure – Whether implied request or requirement by union that procedures be relaxed or not applied.
PRACTICE AND PROCEDURE – Disharmony between pleadings and outline of submissions – Whether unfair on respondents for applicant to depart from outline.
Legislation: Fair Work Act 2009 (Cth) ss 19, 342, 346, 347, 348, 363, 417, 474, 550, 557, 793 Cases cited: QR Limited v Communications, Electrical, Electronic, Energy, Information, Postal, Plumbing and Allied Services Union of Australia (2010) 204 IR 142
Rocky Holdings Pty Ltd v Fair Work Ombudsman (2014) 221 FCR 153
Date of hearing: 17 & 26 October, 19 December 2016 Registry: Victoria Division: General Division National Practice Area: Employment & Industrial Relations Category: Catchwords Number of paragraphs: 181 Counsel for the Applicant: Mr M Follett with Mr A Pollock Solicitor for the Applicant: Maddocks Counsel for the Respondents: Mr R Reitano Solicitor for the Respondents: Slater and Gordon ORDERS
VID 261 of 2016 BETWEEN: AUSTRALIAN BUILDING AND CONSTRUCTION COMMISSION
Applicant
AND: CONSTRUCTION, FORESTRY, MINING AND ENERGY UNION
First Respondent
MICHAEL POWELL
Second Respondent
PETER BOOTH (and others named in the Schedule)
Third Respondent
JUDGE:
JESSUP J
DATE OF ORDER:
1 MARCH 2017
THE COURT ORDERS THAT:
1.The proceeding be listed at a time and date to be notified for the purpose of receiving the parties’ submissions on the terms of the orders proper to reflect the reasons of the court published this day, and as to penalties.
Note: Entry of orders is dealt with in Rule 39.32 of the Federal Court Rules 2011.
REASONS FOR JUDGMENT
JESSUP J:
INTRODUCTION
In this proceeding the applicant, the Australian Building and Construction Commissioner under the Building and Construction Industry (Improving Productivity) Act 2016 (Cth), seeks declarations and penalties against the respondents, the Construction, Forestry, Mining and Energy Union (“the CFMEU”), Michael Powell, Peter Booth, Stephen Long, Derek Christopher, Bill Beattie, John Perkovic, Theo Theodorou, Brendan Murphy, Gerard Benstead and Joseph Myles in respect of…
Keep reading for free
Create a free CaseChat account to read Australian Building and Construction Commission v Constructi... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2017] FCA 168
- Decision Date
CaseChat Overview and Summary
The legal issues that the court had to address included whether the meetings and walk-offs organised by the union representatives constituted industrial action, and if so, whether these actions contravened the enterprise agreement. Another significant issue was whether the union organisers could be held liable as accessories to the contraventions if they were aware that the employees were covered by the agreement. The court also had to consider whether the conduct of the organisers could be attributed to the union, and whether the union organisers’ entry into construction sites in defiance of the builder's right of entry procedures amounted to an implied request or requirement that such procedures be relaxed or not applied.
The Federal Court found that the industrial action engaged in by the employees was indeed organised by the union representatives. However, the court held that the union organisers were not liable as accessories to the contraventions since it was not established that they knew the employees were covered by an enterprise agreement. The court also determined that the union organisers' conduct could not be attributed to the union. Regarding the right of entry, the court ruled that the union organisers' defiance of the builder's procedures did not amount to an implied request or requirement that such procedures be relaxed or not applied. The court ordered that the proceeding be listed for the purpose of receiving the parties’ submissions on the terms of the orders proper to reflect the reasons of the court and as to penalties.
Orders
Orders of the court
1. The proceeding be listed at a time and date to be notified for the purpose of receiving the parties’ submissions on the terms of the orders proper to reflect the reasons of the court published this day, and as to penalties.
Note: Entry of orders is dealt with in Rule 39.32 of the Federal Court Rules 2011.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi