Australian Building and Construction Commission v Construction, Forestry, Mining and Energy Union (The Kane Constructions Case)

Link copied
Case Copied 76 min read

FEDERAL COURT OF AUSTRALIA

Australian Building and Construction Commission v Construction, Forestry, Mining and Energy Union (The Kane Constructions Case) [2017] FCA 168

File number: VID 261 of 2016
Judge: JESSUP J
Date of judgment: 1 March 2017
Catchwords:

INDUSTRIAL LAW – Industrial action – Stop-work meetings and walk-offs on construction sites – Whether industrial action engaged in by employees – Whether meetings and walk-offs organised by union organisers – Whether contraventions arose out of same course of conduct – Whether organisers liable as accessories – Whether organisers knew that employees were covered by enterprise agreement – Whether organisers’ conduct attributed to union.

INDUSTRIAL LAW – Adverse action – Industrial activity – Right of entry – Union organisers entered construction sites in defiance of builder’s right of entry procedure – Whether implied request or requirement by union that procedures be relaxed or not applied.

PRACTICE AND PROCEDURE – Disharmony between pleadings and outline of submissions – Whether unfair on respondents for applicant to depart from outline.

Legislation: Fair Work Act 2009 (Cth) ss 19, 342, 346, 347, 348, 363, 417, 474, 550, 557, 793
Cases cited:

Australian Building and Construction Commissioner v Automotive, Food, Metals, Engineering, Printing and Kindred Industries Union (The Australian Paper Case) [2017] FCA 167

Communications, Electrical, Electronic, Energy, Information, Postal, Plumbing and Allied Services Union of Australia v QR Ltd (No 2) [2010] FCA 652

QR Limited v Communications, Electrical, Electronic, Energy, Information, Postal, Plumbing and Allied Services Union of Australia (2010) 204 IR 142

Rocky Holdings Pty Ltd v Fair Work Ombudsman (2014) 221 FCR 153

Yorke v Lucas (1985) 158 CLR 661

Date of hearing: 17 & 26 October, 19 December 2016
Registry: Victoria
Division: General Division
National Practice Area: Employment & Industrial Relations
Category: Catchwords
Number of paragraphs: 181
Counsel for the Applicant: Mr M Follett with Mr A Pollock
Solicitor for the Applicant: Maddocks
Counsel for the Respondents: Mr R Reitano
Solicitor for the Respondents: Slater and Gordon

ORDERS

VID 261 of 2016
BETWEEN:

AUSTRALIAN BUILDING AND CONSTRUCTION COMMISSION

Applicant

AND:

CONSTRUCTION, FORESTRY, MINING AND ENERGY UNION

First Respondent

MICHAEL POWELL

Second Respondent

PETER BOOTH (and others named in the Schedule)

Third Respondent

JUDGE:

JESSUP J

DATE OF ORDER:

1 MARCH 2017

THE COURT ORDERS THAT:

1.The proceeding be listed at a time and date to be notified for the purpose of receiving the parties’ submissions on the terms of the orders proper to reflect the reasons of the court published this day, and as to penalties.

Note:    Entry of orders is dealt with in Rule 39.32 of the Federal Court Rules 2011.


REASONS FOR JUDGMENT

JESSUP J:

INTRODUCTION

  1. In this proceeding the applicant, the Australian Building and Construction Commissioner under the Building and Construction Industry (Improving Productivity) Act 2016 (Cth), seeks declarations and penalties against the respondents, the Construction, Forestry, Mining and Energy Union (“the CFMEU”), Michael Powell, Peter Booth, Stephen Long, Derek Christopher, Bill Beattie, John Perkovic, Theo Theodorou, Brendan Murphy, Gerard Benstead and Joseph Myles in respect of…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Australian Building and Construction Commission v Constructi... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2017] FCA 168
Decision Date

CaseChat Overview and Summary

In the matter of Australian Building and Construction Commission versus the Construction, Forestry, Mining and Energy Union, also known as the Kane Constructions Case, the Federal Court was tasked with determining whether the union organisers were liable for industrial action engaged in by employees on construction sites. The dispute arose from stop-work meetings and walk-offs which were alleged to have been organised by union representatives. The crux of the case revolved around whether these actions constituted protected industrial activities and whether the organisers could be held accountable as accessories if they knew that the employees were covered by an enterprise agreement.

The legal issues that the court had to address included whether the meetings and walk-offs organised by the union representatives constituted industrial action, and if so, whether these actions contravened the enterprise agreement. Another significant issue was whether the union organisers could be held liable as accessories to the contraventions if they were aware that the employees were covered by the agreement. The court also had to consider whether the conduct of the organisers could be attributed to the union, and whether the union organisers’ entry into construction sites in defiance of the builder's right of entry procedures amounted to an implied request or requirement that such procedures be relaxed or not applied.

The Federal Court found that the industrial action engaged in by the employees was indeed organised by the union representatives. However, the court held that the union organisers were not liable as accessories to the contraventions since it was not established that they knew the employees were covered by an enterprise agreement. The court also determined that the union organisers' conduct could not be attributed to the union. Regarding the right of entry, the court ruled that the union organisers' defiance of the builder's procedures did not amount to an implied request or requirement that such procedures be relaxed or not applied. The court ordered that the proceeding be listed for the purpose of receiving the parties’ submissions on the terms of the orders proper to reflect the reasons of the court and as to penalties.

Orders

Orders of the court

1. The proceeding be listed at a time and date to be notified for the purpose of receiving the parties’ submissions on the terms of the orders proper to reflect the reasons of the court published this day, and as to penalties.

Note: Entry of orders is dealt with in Rule 39.32 of the Federal Court Rules 2011.

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established