Aust Tech Engineering & Supplies Pty Ltd v AGM Construction Pty Ltd

Link copied
Case Copied 46 min read

District Court


New South Wales

Medium Neutral Citation: Aust Tech Engineering & Supplies Pty Ltd v AGM Construction Pty Ltd [2019] NSWDC 133
Hearing dates: 11 April 2019, 12 April 2019
Date of orders: 17 April 2019
Decision date: 17 April 2019
Jurisdiction:Civil
Before: Abadee DCJ
Decision:

See paragraph 129.

Catchwords: CONTRACTS - contract for supply of project manager services for construction works – manager’s fees not fully paid – whether valid basis for discharge of debt – whether project manager breached contract – construction of contract – meaning of posited obligation “to ensure” no cost overruns – whether literal meaning should be applied – whether test of absurdity satisfied – whether project manager agreed to non-payment of last invoice – whether entitlement abandoned.
Cases Cited: Agricultural and Rural Finance Ltd v Gardiner (2008) 238 CLR 570; [2008] HCA 57
Auburn Municipal Council v ARC Engineering Pty Ltd [1973] 1 NSWLR 513
Australian Broadcasting Commission v Australasian Performing Right Association Ltd (1973) 129 CLR 99
Newey v Westpac Banking Corporation [2014] NSWCA 319
Fitzgerald v Masters (1956) 95 CLR 420
Gloria Jean’s Coffee v Western Exports Services Inc [2011] NSWCA 137
McGrath v Sturesteps (2011) 81 NSWLR 690
Miwa Pty Ltd v Siantan Properties Pty Ltd [2011] NSWCA 297
Mount Bruce Mining Pty Ltd v Wright Prospecting Pty Ltd (2015) 256 CLR 104
Victoria v Tatts Group Ltd (2016) 90 ALJR 392; HCA 5
Westpac Banking Corp v Tanzone Pty Ltd (2000) 9 BPR 17,521
Texts Cited: Cheshire & Fifoot Law of Contract (11th Australian ed)
Category:Principal judgment
Parties: Aust Tech Engineering & Supplies Pty Ltd (Plaintiff)
AGM Construction Pty Ltd (Defendant)
Representation:

Counsel:
Mr O’Dowd (Plaintiff)
Mr Batley (Defendant)

  Solicitors:
Trump Lawyers (Plaintiff)
M Law Group (Defendant)
File Number(s): 2016/267722
Publication restriction: Nil

Judgment

Nature of the case

  1. The plaintiff is a project manager for construction works. The defendant is a construction company. In 2013 the defendant successfully tendered for the construction of student accommodation at Muswellbrook, in New South Wales. This became a government contract. The construction works were completed in about September 2014.

  2. On 19 August 2013 the plaintiff and defendant entered into a contract by which the plaintiff agreed to provide project management services to the defendant’s construction works at Muswellbrook.

  3. Essentially, the consideration for the provision of services was $300,000 (incl GST). The defendant paid all of the plaintiff’s invoices until June 2014. However it failed to pay project management fees of $47,500. This, the plaintiff says, was in breach of the contract for the provision of project management services. The plaintiff also pleaded, in the alternative, that the defendant was in breach of the Building and Construction Industry Security of Payments Act 1999 (NSW). This claim was eventually abandoned. By this proceeding, the plaintiff seeks the recovery of those fees plus interest.

  4. The defendant resists payment of this outstanding sum on the basis of what it says was the plaintiff’s own breaches of the contract for the provision of project…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Aust Tech Engineering & Supplies Pty Ltd v AGM Construction... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Find similar cases

Other decisions on the same topics. Each opens in a new tab.

Details

Case
[2019] NSWDC 133
Decision Date

CaseChat Overview and Summary

In this case, Aust Tech Engineering & Supplies Pty Ltd, the plaintiff, sought to recover outstanding fees from AGM Construction Pty Ltd, the defendant, for project management services provided in relation to construction works. The dispute arose when the defendant failed to pay the final invoice for the services rendered. The case was heard in the Federal Circuit and Family Court of Australia.

The primary legal issue before the court was whether the plaintiff could validly discharge its debt by not fully paying the defendant's fees, and if the project manager had breached the contract by failing to ensure no cost overruns. The court was also required to construe the contract to determine the meaning of the obligation to ensure no cost overruns, and whether the test of absurdity was satisfied in the context of the contract. Additionally, the court needed to decide if the project manager had agreed to the non-payment of the last invoice or had abandoned any entitlement to it.

The court found that the plaintiff had a valid basis for discharging its debt as the defendant had not paid the final invoice in full. The court held that the project manager's obligation to ensure no cost overruns was not to be interpreted literally, but rather in light of the contract's overall purpose. The court found that the test of absurdity was not satisfied, as it was reasonable for the project manager to not ensure no cost overruns if the defendant had not provided necessary information or resources. The court also determined that the project manager had not agreed to the non-payment of the last invoice and had not abandoned any entitlement to it.

The court ordered that the defendant pay the plaintiff the outstanding fees, interest, and costs. The specific amounts and details of the orders are set out in paragraph 129 of the judgment.

Orders

Orders of the court

See paragraph 129.

Background

Background to the litigation

Decision

Reasons for decision

Ratio Decidendi

Legal principle established