Assaf v Sky Group Pty Ltd

Link copied
Case Copied 36 min read

Civil and Administrative Tribunal


New South Wales

Medium Neutral Citation: Assaf v Sky Group Pty Ltd [2019] NSWCATCD 67
Hearing dates: 10/9/18;11/9/18;27/11/18;29/3/19
Date of orders: 30 July 2019
Decision date: 30 July 2019
Jurisdiction:Consumer and Commercial Division
Before: C Paull, Senior Member
Decision:

1. In matter HB17/18441 I find that the respondent, Sky Group Pty Ltd is liable to pay the applicant, George Assaf $128,348.79 for defective work and $7000 for an overpayment of work not done by the respondent.

2. In matter HB17/35616 I find that the respondent, George Assaf is liable to pay the applicant, Sky Group Pty Ltd $1540 for variations

3. In offsetting Order 1 against Order 2 I order Sky Group Pty Ltd to pay $133,808.79 on or before 29 August 2019.

4. The parties have until 29/8/19 to make any costs application or any application as to whether the name of Sky Group Pty Ltd needs to be amended

Legislation Cited:

Home Building Act 1989

Category:Principal judgment
Parties: George Assaf (Applicant in HB 17/18441; Respondent in HB 17/35616)
Sky Group Pty Ltd (Respondent in HB 17/18441; Applicant in HB 17/35616)
Representation:

Counsel:
Michael Klooster (for George Assaf)
Maurice Baroni (for Sky Group Pty Ltd)

Solicitors:
Kerin Benson Lawyers (for George Assaf)

Construction Legal (for Sky Group Pty Ltd)
File Number(s): HB17/18441; HB17/35616
Publication restriction: Nil

REASONS FOR DECISION

  1. On or about 19 April 2017, the builder and homeowner entered into a written contract ( the contract) for the builder to carry out “residential building work” as that term is defined under the Home Building Act 1989 (the HBA).

  2. Prior to this, on or about 13 April 2016, the builder had issued a tender in relation to the subject building work, which the parties agree forms part of the contract (the tender).

  3. The builder commenced work sometime in July 2016, the work continued and Progress claims 1-7; Claim 9; and the first half of Claim 8 (PC8 Invoice 1) were issued and paid .

  4. There is some dispute as to when the builder issued and the homeowner received the invoice for the remaining 50% balance of money owing for progress claim 8.

  5. There are two claim 8 Invoices in evidence. One is dated 10/4/17 (PC8 Invoice 2) . The other is dated 26/4/17. PC 8 Invoice 3).

  6. On 28/4/17 the builder issued a suspension notice (the Suspension Notice) and then on 20/6/17, a termination notice (the Termination Notice).The homeowner disputes receiving these notices at the time the builder states they were issued.

  7. On 1/7/17, the homeowner took possession of the site. On 8/7/17 the builder removed the fencing from the site.

  8. It is convenient to note here that the hearing of the evidence concluded on 29/3/19. On that day the builder represented himself and appeared to suggest that his legal advisors no longer acted for him. This is supported in some correspondence that is on the Tribunal file and I note that the builder has failed to file and serve submissions as directed.

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Assaf v Sky Group Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details

Case
[2019] NSWCATCD 67
Decision Date

CaseChat Overview and Summary

The matter of Assaf v Sky Group Pty Ltd involved a dispute between the plaintiff, George Assaf, and the defendant, Sky Group Pty Ltd. The plaintiff sought damages for defective work and an overpayment made to the defendant, while the defendant claimed for variations to the work. The case was heard in the Federal Circuit Court. The plaintiff argued that the defendant had failed to complete the work to the agreed standard and had overcharged for work that was not completed. The defendant, on the other hand, claimed that the plaintiff had not paid for variations to the original scope of work.

The court was required to determine whether the defendant had breached the contract by failing to complete the work to the agreed standard and by overcharging for work that was not completed. The court also needed to determine whether the plaintiff had breached the contract by failing to pay for variations to the original scope of work. The court had to assess the evidence presented by both parties and determine the amount of damages, if any, that were owed by each party.

The court found that the defendant had breached the contract by failing to complete the work to the agreed standard and by overcharging for work that was not completed. The court awarded the plaintiff damages in the amount of $128,348.79 for defective work and $7000 for an overpayment of work not done by the defendant. The court also found that the plaintiff had breached the contract by failing to pay for variations to the original scope of work, and awarded the defendant damages in the amount of $1540. The court ordered that the defendant pay the plaintiff $133,808.79, after offsetting the amounts owed by each party. The parties were given until a specified date to make any costs application or any application as to whether the name of the defendant needs to be amended.

Orders

Orders of the court

1. In matter HB17/18441 I find that the respondent, Sky Group Pty Ltd is liable to pay the applicant, George Assaf $128,348.79 for defective work and $7000 for an overpayment of work not done by the respondent.

2. In matter HB17/35616 I find that the respondent, George Assaf is liable to pay the applicant, Sky Group Pty Ltd $1540 for variations

3. In offsetting Order 1 against Order 2 I order Sky Group Pty Ltd to pay $133,808.79 on or before 29 August 2019.

4. The parties have until 29/8/19 to make any costs application or any application as to whether the name of Sky Group Pty Ltd needs to be amended

Background

Background to the litigation

Evidence

Evidence before the court

Decision

Reasons for decision

Ratio Decidendi

Legal principle established