Ashcam Pty Ltd v Queensland Building and Construction Commission

Link copied
Case Copied 18 min read

QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL


CITATION:

Ashcam Pty Ltd v Queensland Building and Construction Commission & Anor [2025] QCAT 321

PARTIES:

ASHCAM PTY LTD

(applicant)

v

QUEENSLAND BUILDING AND CONSTRUCTION COMMISSION

(first respondent)

BARRY HERON

(second respondent)

APPLICATION NO/S:

GAR485-22

MATTER TYPE:

General administrative review matters

DELIVERED ON:

21 August 2025

HEARING DATE:

17 February 2025

HEARD AT:

Brisbane

DECISION OF:

Member Howe

ORDERS:

1.     The reconsidered decision made 15 August 2023 varying the scope of work necessary to rectify the defective work identified in the Direction to Rectify dated 7 June 2022 is confirmed.

2.     The Queensland Building and Construction Commission claims the reserved costs of two applications for miscellaneous matters filed by Barry Heron on 19 May 2024 and 2 June 2024 dismissed by the Tribunal against Barry Heron and filed submissions in support of that claim.

3.     If Queensland Building and Construction Commission has not served a copy of its submissions in support of its claim on Barry Heron, Queensland Building and Construction Commission must serve a copy on Barry Heron within 7 days of date of this Order.

4.     Barry Heron  must file in the Tribunal and serve on Queensland Building and Construction Commission any submissions in response within 14 days thereafter.

5.     The matter of the reserved costs shall be determined on the papers.

6.     If any party claims other costs the party must apply by way of Form 40 Application for Miscellaneous Matters within 28 days of Order.

CATCHWORDS:

PROFESSIONS AND TRADES – BUILDERS – STATUTORY INSURANCE SCHEME – where there was a complaint of defective work with respect to a car port – where the Commission issued a direction to rectify – where the contractor failed to rectify in time – where the matter was referred to insurance – where a scope of work was prepared – where the contractor sought review of the scope of work in the Tribunal – where the decision about scope of work was returned to the Commission for reconsideration – where an amended scope of work was drawn – where the contractor claimed it was denied access to the site – where the home owner’s failure to unlock premises on a particular day was not an unreasonable denial of access – where the amended scope of work was reasonable and necessary to rectify the defective work

Queensland Building and Construction Commission Regulation 2018 (Qld), Schedule 6 s 18(a)

Crocker v Queensland Building and Construction Commission [2024] QCAT 73

Middling v Queensland Building Services Authority [2005] QCCTB 14

APPEARANCES & REPRESENTATION:

Applicant:

L Watt, Becker Watt Lawyers

First respondent:

N M Cooke instructed by Dentons

Second respondent:

Self-represented

REASONS FOR DECISION

  1. The applicant building contractor (‘Ashcam’) has sought review of a decision about the scope of work to be undertaken pursuant to the statutory insurance scheme on the failure of Ashcam to comply with a direction to rectify defective building work associated with construction of a carport the property of Mr Heron.

  2. Mr Heron complained to the Queensland…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Ashcam Pty Ltd v Queensland Building and Construction Commis... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2025] QCAT 321
Decision Date

CaseChat Overview and Summary

Ashcam Pty Ltd, a building contractor, brought proceedings against the Queensland Building and Construction Commission concerning a dispute over a car port construction. The Commission issued a direction for Ashcam to rectify the defective work, which Ashcam failed to do within the required time. The matter was subsequently referred to insurance, and a scope of work was prepared to rectify the defects. Ashcam sought a review of this scope of work in the Tribunal, which found that the decision about the scope of work should be returned to the Commission for reconsideration. An amended scope of work was then drawn up, but Ashcam claimed it was denied access to the site, which it argued prevented it from completing the work. The Commission argued that the amended scope of work was reasonable and necessary to rectify the defective work. The case was heard in the Queensland Civil and Administrative Tribunal (QCAT).

The central legal issues revolved around whether the Commission's reconsideration of the scope of work was lawful, and if Ashcam's access to the site was unreasonably denied. The court had to determine if the amended scope of work was reasonable and necessary, and if the homeowner's failure to unlock the premises constituted an unreasonable denial of access. The court examined the evidence presented by both parties and the statutory framework governing the Commission's powers.

The QCAT found that the Commission's reconsideration of the scope of work was appropriate and that the amended scope of work was reasonable and necessary to rectify the defective work. The court determined that the homeowner's failure to unlock the premises on the specified day did not amount to an unreasonable denial of access, as the Commission had made reasonable efforts to arrange access. Consequently, the QCAT confirmed the reconsidered decision of the Commission, dismissed the Commission's claim for reserved costs, and directed that any further claims for costs be made within a specified timeframe.

The final orders included the confirmation of the Commission's reconsidered decision, the dismissal of the Commission's claim for reserved costs, and directives for the service and response of submissions regarding any further claims for costs. The matter of the reserved costs was to be determined on the papers, and any other claims for costs had to be made within a specified period.

Orders

Orders of the court

1. The reconsidered decision made 15 August 2023 varying the scope of work necessary to rectify the defective work identified in the Direction to Rectify dated 7 June 2022 is confirmed.

2. The Queensland Building and Construction Commission claims the reserved costs of two applications for miscellaneous matters filed by Barry Heron on 19 May 2024 and 2 June 2024 dismissed by the Tribunal against Barry Heron and filed submissions in support of that claim.

3. If Queensland Building and Construction Commission has not served a copy of its submissions in support of its claim on Barry Heron, Queensland Building and Construction Commission must serve a copy on Barry Heron within 7 days of date of this Order.

4. Barry Heron must file in the Tribunal and serve on Queensland Building and Construction Commission any submissions in response within 14 days thereafter.

5. The matter of the reserved costs shall be determined on the papers.

6. If any party claims other costs the party must apply by way of Form 40 Application for Miscellaneous Matters within 28 days of Order.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.