JURISDICTION : SUPREME COURT OF WESTERN AUSTRALIA
IN CIVIL
CITATION: ARMADA BALNAVES PTE LTD -v- WOODSIDE ENERGY JULIMAR PTY LTD [No 2] [2020] WASC 14
CORAM: KENNETH MARTIN J
HEARD: 18-21, 25-28 FEBRUARY & 26-27 MARCH 2019
DELIVERED : 24 JANUARY 2020
FILE NO/S: CIV 1408 of 2016
BETWEEN: ARMADA BALNAVES PTE LTD
Plaintiff
AND
WOODSIDE ENERGY JULIMAR PTY LTD
Defendant
Catchwords:
Contract - Breach of contract claim - Service Agreement between parties - Express term Termination of Services Agreement for cause - Contractor asserted Company's right to terminate lost by election by conduct to affirm Services Agreement - Alleged abandonment of right to terminate for cause - Contractor asserts attempted termination for cause was a repudiation of Services Agreement amounting to wrongful renunciation or repudiation by Company - Consideration of election and affirmation legal principles - Distinction between present case and more typical election and affirmation cases - Issues of confrontation, delay and communication - Analysis of alleged acts of election and affirmation - Whether election to affirm Services Agreement proven by communicated inconsistent acts
Damages - Measure of damages - Claim for loss of bargain damages for repudiation - Alternative hypothetical rival scenario assuming Services Agreement had not been terminated and had continued to be performed - Preferred damages claim based on loss of opportunity to receive a fixed sum express 'break fee' - Alternative hypothetical damages based on the assumed performance of the first term of the Services Agreement performed to completion with assumed revenue payments made to Contractor
Damages - Assessment of damages - Consideration as to whether Contractor ready, willing and able to perform - Whether right to terminate at specific time - Assessment of alternate counter factual damages scenarios as more likely
Legislation:
Nil
Result:
Plaintiff's action dismissed
Category: A
Representation:
Counsel:
| Plaintiff | : | Mr B Walker SC & Mr N Kirby |
| Defendant | : | Mr D Ryan SC & Mr K de Kerloy |
Solicitors:
| Plaintiff | : | Clayton Utz |
| Defendant | : | Herbert Smith Freehills |
Case(s) referred to in decision(s):
Agricultural and Rural Finance Pty Ltd v Gardiner [2008] HCA 57; (2008) 238 CLR 570
Almond Investors v Kualitree Nursery Pty Ltd [2011] NSWCA 198
Carr v JA Berriman Pty Ltd [1953] HCA 31; (1953) 89 CLR 327
Donau Pty Ltd v ASC AWD Shipbuilder Pty Ltd [2018] NSWSC 1273
DTC No 1 Pty Ltd v Matthew [2009] NSWSC 1485
Galafassi v Kelly [2014] NSWCA 190; (2014) NSWLR 119
Highmist Pty Ltd v Tricave Ltd [2005] QCA 357
Hongkong Fir Shipping Co Ltd v Kawasaki Kishen Kiasha Ltd [1962] 2 QB 26
Immer No. 145 Pty Ltd v Uniting Church in Australia Property Trust (NSW) [1933] HCA 27; (1993) 182 CLR 26
Inlon Pty Ltd v Celli SpA [2017] NSWSC 569
Khoury v Government Insurance Office (NSW) [1984] HCA 55; (1984) 164 CLR 622
Koompahtoo Local Aboriginal Land Council v Sanine Pty Ltd [2007] HCA 61; (2007) 233 CLR 115
Lindsay Petroleum Co v Hurd (1874) LR 5 PC 221
Keep reading for free
Create a free CaseChat account to read Armada Balnaves Pte Ltd v Woodside Energy Julimar Pty Ltd [N... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2020] WASC 14
- Decision Date
CaseChat Overview and Summary
The court had to determine whether WEJ had the right to terminate the Services Agreement for cause and whether AB had effectively affirmed the agreement by its conduct, thereby waiving the right to terminate. The court also needed to decide the appropriate measure of damages, specifically whether AB was entitled to loss of bargain damages or a fixed sum break fee. The analysis involved examining the principles of election and affirmation, as well as the specific terms and circumstances of the Services Agreement.
In its reasoning, the court found that WEJ's right to terminate the Services Agreement for cause was not lost by AB's conduct, as AB had not unequivocally affirmed the agreement. The court concluded that AB had not abandoned its right to terminate for cause. However, the court also found that WEJ's attempted termination for cause was not a repudiation of the Services Agreement. As for damages, the court preferred the break fee claim over loss of bargain damages, considering it more certain and appropriate given the specific contractual terms. The court assessed the damages based on the likelihood of AB being ready, willing, and able to perform, and determined that AB was entitled to a payment for satisfying milestone K4, plus interest from the date it first attempted the 72-hour operational efficiency test. The court also addressed minor fiscal claims and cross claims between the parties.
The final orders of the court included a liability for WEJ to pay AB $US50 plus GST for Milestone B11 and $US2 million plus GST for Milestone K4. Additionally, AB was awarded $AUD341,165.29, being the difference between the invoiced amount and the credit note issued by AB. The court provided detailed calculations and reasoning for these awards, ensuring clarity and precision in the final determination of the case.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi
Legal Principle Established
I would emphasise that this specified threshold did not require the satisfaction of cl 10.6, but merely the completion of preparation activities for the tests in cl 10.6. The key constructional issue is whether it can be said that AB had completed 'preparation activities for Acceptance tests'. The requirements of 'preparation activities' seem to chronologically precede any subsequent satisfaction of the Acceptance Test. To interpret the SA otherwise, effectively, is to seek to rewrite 'preparation activities for Acceptance' as 'completion of Acceptance Tests'. Hence, I am of the end view that WEJ's advocated construction of the milestone K4 requirements demands too much of preparatory works. It fails to sufficiently engage with the required textual distinction as between the preparation and the completion. The WEJ advocated interpretation which requires AB bring the FPSO Facility to the point where it could, with certainty, complete the 72 hour OET, is not realistic. Preparation for an attempt at the OET and a satisfactory completion of that test are entirely different things - as the underlying facts at the present trial now illustrate only too graphically. Here, AB had ultimately performed three of the four nominated Acceptance Tests. But it could never pass the remaining OET, despite making multiple attempts as from September 2015. It is clear then that AB did not ever reach a completion of the Acceptance Tests. However, AB's preparatory work for the OETs, I would alternately assess, was sufficient to support a conclusion that AB satisfied what was a lesser and anterior requirement of it reaching the culmination of 'preparation activities' for the Acceptance Tests. Therefore, I conclude, in the end, that AB did become entitled as at 13 September 2015 to receive from WEJ a payment tied its satisfaction of milestone K4 and with interest accruing from that date - which was the first occasion that the FPSO Facility was able to run for a full required 72 hour OET test period, upon that (ultimately unsuccessful) sustained attempt to satisfactorily complete the OET. The fact AB did not satisfactorily perform the OET then or ever does not detract from the achievement by it of its preparedness to attempt the last of the Acceptance Tests, at 13 September 2015. Accordingly, I conclude at the end that WEJ is liable to pay AB, first in relation to Milestone B11, the sum of $US50 plus GST and, second, for Milestone K4, the sum of $US2 million plus GST. AB and WEJ also advance as against each other a variety of miscellaneous fiscally minor (relatively speaking) claims and cross claims, which must also be addressed. Again, as was the case in relation to the Milestone Claims, all these issues were addressed only by written submissions, without being canvassed verbally by counsel at trial. These further claims include asserted claimed repayments, or for refunds of various amounts including redundancy costs, logistics payments and insurance policy refunds. AB pleads out its claims in relation to its allegedly unpaid invoices by WEJ under pars 54A - 54E of the 4FASOC. Those paragraphs relate:Unpaid FPSO Facilities Services Fee Invoices54A.From the date of issuing the Certificate of Production Test the defendant was obliged to pay the plaintiff the Performance Adjusted FPSO Facilities Services Fee within 30 days from the receipt of a valid invoice.54B.On 9 June 2016 the plaintiff issued an invoice in the amount of $US721,878.97 (including GST) (being an equivalent of $AUD967,977.59 (including GST)) for work related to in relation to D1. Facilities Services for April 2016.54C.The Company has not paid the $US721,878.97, by the due date or at all.54D.On 15 June 2016 the plaintiff issued a Credit Note in favour of the defendant in the amount of $AUD626,812.30 (including GST) in relation to services provided in April 2016 and purchase of fuel.54E.As a result of the matters pleaded in paragraphs 54A to 54D above, the defendant is liable to pay the plaintiff $AUD341,165.29, being the $AUD967,977.59 invoiced less the $AUD626,812.00 credited. (particulars excluded)