CITATION: Area Square Pty Ltd v Hill-Douglas & Anor [2010] QCAT 8
PARTIES: Area Square Pty Ltd
v
Sholto Hill-Douglas and Louise Hill-Douglas
APPLICATION NUMBER: BD017-08
MATTER TYPE: Building Matter
HEARING DATE: 10 and 11 December 2009
HEARD AT: Brisbane
DECISION OF: Richard Oliver, Senior Member
DELIVERED ON: 20 January 2010
DELIVERED AT: Brisbane
ORDERS MADE: The Applicant pay to the Respondents the sum of $5,944.31 by 4 pm on 26 February 2010.
CATCHWORDS: Contractual building dispute, claim for money due pursuant to signed variations, where variations signed under duress; counterclaim for damages for rectification to leaking swimming pool.
APPEARANCES and REPRESENTATION (if any):
Mr Thomson of counsel for the applicant
Ms Hatten, solicitor, for the respondents.
Introduction
The applicant is a registered builder. Its directors are Matthew Campbell and Michelle Gunn. The respondents are the owners of land at 9 Herbert St Toowong.
In the early part of 2006 the Applicant, through Mr Campbell, and the respondents commenced negotiations with a view of entering into a contract for the construction of house on the land in accordance with plans prepared by Brenton Rasheed, Architect. An initial quote for the construction was provided in February 2006 with a further quote provided in May 2006. On 11 May 2009 the parties entered into a building contract[1] to construct the house generally in accordance with the plans provided. The contract price was $629,000.00 inclusive of GST. A deposit was paid of $31,450.00.
[1] Ex 3 “MC1”
All that remained for the project to proceed was a Development Approval (“DA”) from the Brisbane City Council (Council”). This was the responsibility of the respondents. Problems arose with the DA, essentially the Council maintained that the project was Character Code Assessable because of the area in Toowong in which the land was located. To accommodate the Council and obtain the DA the respondents had to change the plans.
Finally a DA was issued by the Council on 30 August 2006.the applicant was prevented from commencing work until the approval issued. This according to Mr Campbell put the applicant in a very difficult situation. Quite obviously given the size of the project, he could not take on other work whilst waiting for the approval but at the same time, had to keep his sub trades in work if possible.
As the approval had not issued within the time prescribed by the contract Mr Campbell informed the respondents that it was his intention to cancel the contract to enable the applicant to take on other work. He indicated to Mr Hill-Douglas that he would be happy to consider the job again when the approval came through, which impliedly necessitated preparing a further quote, and presumably if accepted, entering into new contract.
These matters are deposed to in the statement of Mr Campbell[2]. Mr Hill-Douglas does not challenge this evidence in any direct or meaningful way other than to say that he disagrees, and that no such conversations occurred.
[2] Exhibit 3 para 21-22
Mr Campbell goes further…
Keep reading for free
Create a free CaseChat account to read Area Square Pty Ltd v Hill-Douglas and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2010] QCAT 8
- Decision Date
CaseChat Overview and Summary
The primary issue before the Tribunal was whether the Applicant was entitled to be paid for the variations claimed and whether the Respondents were liable to pay for the rectification of the swimming pool. The Tribunal considered the evidence of the parties and the experts, and found that the Applicant was entitled to be paid for the driveway but not for the other variations claimed. The Tribunal also found that the Respondents were entitled to be paid for the rectification of the swimming pool. The Tribunal held that the evidence established that the parties had agreed to the variation for the driveway and that the Respondents had the benefit of the tile credit. The Tribunal also held that the Respondents were liable for the cost of the swimming pool rectification because the leak was caused by the Applicant's failure to apply a waterproofing membrane before tiling the pool. The Tribunal rejected the Respondents' claims for rectification of the cornices and the air conditioning system, and the Applicant's claim for the rendering.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.