Land and Environment Court
New South Wales
Medium Neutral Citation: Architecture Design Studio (NSW) Pty Ltd v Canterbury-Bankstown Council [2020] NSWLEC 1398 Hearing dates: 12 June 2020 and 17 June 2020 Date of orders: 31 August 2020 Decision date: 31 August 2020 Jurisdiction: Class 1 Before: Horton C Decision: The Court orders that:
(1) The Applicant is granted leave to amend the application and rely upon the amended plans marked Exhibit A and other documents listed at [3] subject to the Applicant paying the Respondent’s costs thrown away pursuant to s 8.15(3) of the Environmental Planning and Assessment Act 1979 as agreed or assessed.
(2) The appeal is dismissed.
(3) Development consent for Development Application No. 376/2018 seeking consent for the demolition of existing structures and the construction of a three storey boarding house over basement car park on land at 1 Ernest Street North, Lakemba is refused.
(4) All Exhibits are returned except for Exhibits A, Q and 6.
Catchwords: DEVELOPMENT APPLICATION – State Environmental Planning Policy (Affordable Rental Housing) – boarding house development in R4 High Density Residential zone – weight given to draft Local Environmental Plan – clause 30A character of the local area
Legislation Cited: Canterbury Local Environmental Plan 2012
Environmental Planning and Assessment Act 1979
Land and Environment Court 1979
State Environmental Planning Policy (Affordable Rental Housing) 2009
Cases Cited: Alamdo Holdings Pty Limited v The Hills Shire Council [2012] NSWLEC 1302
Maygood Australia Pty Ltd v Willoughby City Council [2013] NSWLEC 142
Omid Mohebati-Arani v Kuringai Council [2017] NSWLEC 143
Terrace Tower Holdings Pty Limited v Sutherland Shire Council (2003) 129 LGERA 195; [2003] NSWCA 289
Texts Cited: Canterbury Development Control Plan 2012
Canterbury Development Control Plan 2012, Amendment No. 5
Land and Environment Court of New South Wales, COVID-19 Pandemic Arrangements Policy, (March 2020)
Category: Principal judgment Parties: Architecture Design Studio (NSW) Pty Ltd (Applicant)
Canterbury-Bankstown Council (Respondent)Representation: Counsel:
Solicitors:
M Seymour with T Poisel (Applicant)
M Bonnano (Solicitor) (Respondent)
Birchgrove Legal (Applicant)
Canterbury-Bankstown Council (Respondent)
File Number(s): 2019/101322 Publication restriction: No
Judgment
-
COMMISSIONER: This Class 1 appeal concerns a development application brought before the Court under s 97 of the Environmental Planning and Assessment Act 1979 (EPA Act), according to the class 1 application filed with the Court, which I understand to be s 8.7 of the EPA Act against the deemed refusal of Development Application No. 376/2018 (the application) seeking consent for:
Demolition of existing structures on land at 1 Ernest Street North, Lakemba;
Construction of:
A three-storey boarding house containing a total of 15 x single boarding house rooms (including 1 adaptable room and a manager’s room) and 4 x double rooms (including 1 x accessible room) with private open space to the rear of the site;
a basement with 10 car spaces (including 1 accessible space) and 4 motorcycle spaces with lift access;
at ground level 2 x single boarding rooms…
Keep reading for free
Create a free CaseChat account to read Architecture Design Studio (NSW) Pty Ltd v Canterbury-Bankst... and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2020] NSWLEC 1398
- Decision Date
CaseChat Overview and Summary
The primary legal issue before the court was whether the applicant should be granted leave to amend their application and rely on the amended plans. A secondary issue was whether the amended application complied with the relevant planning provisions and local environmental plans. The court had to balance the applicant’s right to amend their application against the potential prejudice to the respondent if leave was granted.
The court found that the applicant was entitled to amend their application, as the proposed changes were not materially different from the original application and would not cause significant prejudice to the respondent. The court noted that the amended application complied with the relevant planning provisions and local environmental plans. However, the court ultimately found that the amended application did not comply with the local environment plan and refused development consent for the proposed development.
The court ordered that the applicant be granted leave to amend their application and rely on the amended plans, subject to the payment of the respondent’s costs. The court dismissed the appeal and refused development consent for the proposed development. The court ordered that all exhibits be returned, except for the amended plans and certain other documents.
Orders
Orders of the court
The Court orders that:
(1) The Applicant is granted leave to amend the application and rely upon the amended plans marked Exhibit A and other documents listed at [3] subject to the Applicant paying the Respondent’s costs thrown away pursuant to s 8.15(3) of the Environmental Planning and Assessment Act 1979 as agreed or assessed.
(2) The appeal is dismissed.
(3) Development consent for Development Application No. 376/2018 seeking consent for the demolition of existing structures and the construction of a three storey boarding house over basement car park on land at 1 Ernest Street North, Lakemba is refused.
(4) All Exhibits are returned except for Exhibits A, Q and 6.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi