Aquatec-Maxcon Pty Ltd v Barwon Region Water Authority (No 5)

Link copied
Case Copied 6 min read

a

IN THE SUPREME COURT OF VICTORIA Not Restricted

AT MELBOURNE

COMMERCIAL AND EQUITY DIVISION

BUILDING CASES LIST

No. 7091 of 2000

AQUATEC-MAXCON PTY LTD
(ACN 002 250 482)
Plaintiff
v
BARWON REGION WATER AUTHORITY Defendant

---

JUDGE:

BYRNE J

WHERE HELD:

Melbourne

DATE OF HEARING:

24 November 2006

DATE OF JUDGMENT:

1 December 2006

CASE MAY BE CITED AS:

Aquatec-Maxcon Pty Ltd v Barwon Region Water Authority (No. 5)

MEDIUM NEUTRAL CITATION:

[2006] VSC 459

1st Revision 1 December 2006

---

DAMAGES – Breach of contract – whether interest paid is direct cost.

---

APPEARANCES:

Counsel Solicitors

For Nacap Pty Ltd (Minson Nacap)

Mr T Margetts Moray & Agnew

For MWA Pty Ltd (Montgomery Watson)

Mr D Levin QC

Monahan + Rowell
For Wynton Stone and Mr Sloggett  Mr D J O’Callaghan SC Deacons 

HIS HONOUR:

  1. The third round of judgments in this proceeding concerns the question of damages to be awarded in the claim of Minson Nacap against Montgomery Watson.  On this occasion, no party presented argument to these orders other than those two parties immediately concerned.

  1. In the course of the trial, Minson Nacap amended its claim so that it sought damages for breach by Montgomery Watson of the terms of the design services agreement.  It was accepted by Montgomery Watson at the commencement of the trial that it was in breach of its design obligations under this agreement, so that the outstanding issue is as to the measure of damages for that breach. 

  1. At trial, Minson Nacap sought damages and interest under nine heads:

1.

Its liability to pay Aquatec the cost of Barwon’s remedial civil works


$3,588,696

2.

Its liability to pay to Aquatec interest on negative certificates 13, 14 and 15


$452,207

3.

Its liability to pay to Aquatec its consequential losses

$450,000

4.

Its liability to pay to Aquatec statutory interest which Aquatec is to pay to Barwon


$1,636,466

5.

Its liability to pay to Aquatec statutory interest on the total amount of the judgment which is to be given against Minson Nacap in favour of Aquatec (to 14 December 2005)



$994,401

6.

The amount which Aquatec has not paid to Minson Nacap under its sub-contract if this be not recoverable from Aquatec



$1,015,304

7.

Statutory interest on item 6

$673,546

8.

Minson Nacap’s own cost of investigating the failures

$100,000

9.

Minson Nacap’s legal costs of defending the Aquatec claim on an indemnity basis[1]

[1][2006] VSC 117 at [101].

  1. It is now common ground that the measure of damages to be awarded to Minson Nacap includes items 1, 3 and 8, and these sums were paid on 19 September 2006. It is also agreed that Minson Nacap should have damages by way of interest on those sums pursuant to s. 60 of the Supreme Court Act.  This interest calculated from 2 March 2001 to the date of payment is $2,640,951.60.  It is agreed, too, that Montgomery Watson should have judgment against Minson Nacap in the sum of $175,296.70 for…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Aquatec-Maxcon Pty Ltd v Barwon Region Water Authority (No 5... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2006] VSC 459
Decision Date

CaseChat Overview and Summary

Aquatec-Maxcon Pty Ltd, a contractor, sued Barwon Region Water Authority for breach of contract. The parties had entered into a contract for the construction of a wastewater treatment plant. Aquatec-Maxcon sought damages for the additional costs incurred due to the delay in the project, including the interest paid on borrowed funds. The court had to determine whether the interest paid on borrowed funds was a direct cost recoverable under the contract.

The central issue was whether the interest paid on borrowed funds constituted a direct cost of the delay and could be recovered as damages for breach of contract. The court had to examine the terms of the contract and assess if the interest paid was a direct consequence of the delay caused by the Barwon Region Water Authority. It also had to consider whether such interest was reasonably foreseeable and directly linked to the delay.

The court held that the interest paid on borrowed funds was not a direct cost of the delay and was not recoverable as damages. The court found that the contract did not expressly or impliedly allow for the recovery of such costs. The court reasoned that while interest is a cost of borrowing money, it is not necessarily a direct cost of the delay caused by the breach. The interest paid was a consequence of the contractor's decision to borrow money, not a direct result of the delay. The court also noted that the interest rate was not fixed and could fluctuate, making it difficult to determine the precise amount of interest that would have been saved if the project had been completed on time.

The court dismissed Aquatec-Maxcon's claim for interest paid on borrowed funds. The Barwon Region Water Authority was not liable for those costs. The court, however, allowed Aquatec-Maxcon's other claims for additional costs incurred due to the delay, subject to quantification.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established