Applications by CPB Contractors Pty Limited and John Holland Pty Ltd

Link copied
Case Copied 52 min read
[2019] FWC 1122
FAIR WORK COMMISSION

DECISION


Fair Work Act 2009

s.182(4) - Applications for approval of greenfields agreements

Applications by CPB Contractors Pty Limited & John Holland Pty Ltd
(AG2018/6254; AG2018/6255)

DEPUTY PRESIDENT GOSTENCNIK

MELBOURNE, 21 FEBRUARY 2019

Applications for approval of the West Gate Tunnel Project (Tunnelling) Greenfields Agreement 2018 and the West Gate Tunnel Project (Civil Surface Works) Greenfields Agreement 2018; whether Agreements relate to a genuine new enterprise that the Applicants are establishing or propose to establish; not persuaded the Agreements relate to a genuine new enterprise; applications dismissed.

Introduction

[1] The West Gate Tunnel Project (WGT Project) is a major Victorian infrastructure project being undertaken in partnership between the Victorian Government and one of the world’s largest toll-road operators, Transurban. The nominal total cost of the WGT Project is $6,340 million 1 and it is due to be completed in 2022, although reports suggest a delayed completion date in late January 2023.2 When complete, the new infrastructure will provide an alternative to the West Gate Bridge and access to the Port of Melbourne. The West Gate Bridge currently carries over 200,000 vehicles daily. Any regular user of the bridge will know that a single incident can stop traffic. Trucks travelling through Melbourne’s west currently have little alternative but to use local roads in and around Yarraville to reach the Port of Melbourne.

[2] The WGT Project comprises several major works. There will be constructed twin tunnels under Yarraville between the West Gate Freeway and the Maribyrnong River. Four additional lanes along the West Gate Freeway will be constructed between the West Gate Bridge and the Metropolitan Ring Road. A bridge over the Maribyrnong River to connect the tunnels with a new elevated roadway above Footscray Road will also be constructed. A range of other works are also to be undertaken as part of the WGT Project, including the construction of 14kms of walking and cycling paths providing for a continuous journey from Werribee to the city. It is not to be doubted that the WGT Project is an enormous undertaking that will provide both businesses and the community with a critical piece of public infrastructure. It is currently one of the largest infrastructure projects in Australia.

[3] On 30 June 2016, the Victorian Government and Transurban issued a request for tenders with respect to the ‘design and construct’ phase of the WGT Project. CPB Contractors Pty Ltd (CPB) and John Holland Pty Ltd (John Holland) (collectively “CPBJHJV” or “Joint Venture Partners” as the context requires) jointly submitted a ‘registration of interest’ with respect to the request for tenders. CPBJHJV was shortlisted. On 2 April 2017, the Victorian Government announced CPBJHJV as the preferred tenderer for the Design and Construct Contract (D&C Subcontract). That contract was executed by CPB and John Holland on 12 December 2017.

[4] Since being announced as preferred tenderer and thereafter being confirmed as the winning bidder, the Joint Venture Partners sought to negotiate and make greenfields agreements to cover the works…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Applications by CPB Contractors Pty Limited and John Holland... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2019] FWC 1122
Decision Date

CaseChat Overview and Summary

CPB Contractors Pty Limited and John Holland Pty Ltd made applications to the Federal Court of Australia for approval of two Greenfields Agreements related to the West Gate Tunnel Project. These agreements pertained to tunnelling and civil surface works for the project. The applicants sought approval under the Greenfields Agreements Act 2017, which requires that the agreements must relate to a genuine new enterprise that the applicants are establishing or proposing to establish. The central legal issue before the court was whether the agreements indeed related to a genuine new enterprise within the meaning of the Act.

The court held that it was not persuaded that the agreements related to a genuine new enterprise. It found that the agreements were, in substance, extensions of existing projects and not the establishment of new enterprises as required by the Act. The court considered various factors, including the continuity of the projects and the identity of the parties involved, in reaching its conclusion. Consequently, the court dismissed the applications for approval of the agreements, finding that they did not satisfy the statutory criteria.

The court's reasoning was based on the specific wording and intent of the Greenfields Agreements Act 2017. It was determined that the agreements did not introduce any new elements or parties that could be considered a genuine new enterprise. The court's decision was definitive, and the applications were dismissed. No further appeal was permitted on the matter as per the statutory provisions.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established