Application by ETSA Utilities

Link copied
Case Copied 13 min read

AUSTRALIAN COMPETITION TRIBUNAL

Application by ETSA Utilities [2010] ACompT 5

Citation: Application by ETSA Utilities [2010] ACompT 5
Review from: Australian Energy Regulator
Parties: ETSA UTILITIES (ABN 13 332 330 749)
File number: 4 of 2010
Judges: MIDDLETON J (DEPUTY PRESIDENT),
MR R DAVEY AND MR R SHOGREN
Date of delivery of reasons: 13 October 2010
Date of hearing: 13, 14, 15, 16, 17, 20 and 21 September 2010
Place: Melbourne
Category: No Catchwords
Number of paragraphs: 33
Counsel for ETSA Utilities: Ms M Sloss SC with Mr CA Moore and Mr M Borsky
Solicitor for ETSA Utilities: Gilbert + Tobin Lawyers
Counsel for Australian Energy Regulator: Mr P Hanks QC with Mr Gray, Ms R Ellyard, Mr T Clarke and Mr L Merrick
Solicitor for Australian Energy Regulator: Corrs Chambers Westgarth

IN THE AUSTRALIAN COMPETITION TRIBUNAL

FILE NO. 4 of 2010

RE:

APPLICATION UNDER SECTION 71B OF THE NATIONAL ELECTRICITY LAW FOR REVIEW OF A DISTRIBUTION DETERMINATION MADE BY THE AUSTRALIAN ENERGY REGULATOR IN RELATION TO ETSA UTLITITES PURSUANT TO CLAUSE 6.11.1 OF CHAPTER 6 OF THE NATIONAL ELECTRICITY RULES

BY:

ETSA UTLITITES (ABN 13 332 330 749)
Applicant

MEMBERS:

MIDDLETON J (DEPUTY PRESIDENT),
MR R DAVEY AND MR R SHOGREN

DATE OF PUBLICATION OF REASONS FOR DECISION:

13 OCTOBER 2010

PLACE:

MELBOURNE

REASONS FOR DECISION

  1. On 14 September 2010, the Tribunal made the following announcement and directions:

    OTHER MATTERS: The Tribunal has formed the view that a ground of review has been established for the purposes of section 71R(3) of the National Electricity (South Australia) Law in relation to the AER’s rejection of the Applicant’s claim for an addition to be made to its opening RAB in respect of easements extant as at 1 July 1999.

    In these directions:

    “category 1 easements” means registered power line easements in relation to ETSA Corporation’s distribution network as at 1 July 1999;

    “category 2 easements” means registered padmount transformer easements in relation to ETSA Corporation’s distribution network as at 1 July 1999;

    “category 3 easements” means deemed statutory easements arising from unregistered grants of easements by landowners in relation to ETSA Corporation’s distribution network as at 1 July 1999;

    “category 4 easements” means deemed statutory easements arising from licences granted by landowners in relation to ETSA Corporation’s distribution network as at 1 July 1999;

    “category 5 easements” means registered easements in relation to ETSA Corporation’s distribution network as at 1 July 1999 arising as a result of land subdivisions; and

    all dollar figures are in dollars as at 1 July 1999.

    THE TRIBUNAL DIRECTS THAT:

    1.By 4pm on 5 November 2010, the AER file and serve any report addressing the following estimates relied upon by the Applicant:

    (a)       as to category 1 easements:

    (i)        the rate of $1949 per easement for acquisition costs;

    (ii)       the rate of $872/km for survey costs;

    (b)       as to category 2 easements:

    (i)the rates of $2564 and $2052 per easement for acquisition costs;

    (c)       as to category 3 easements:

    (i)        the rate of $1282 per easement…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Application by ETSA Utilities and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2010] ACompT 5
Decision Date

CaseChat Overview and Summary

ETSA Utilities, an electricity distribution network service provider in South Australia, applied for a review of a distribution determination made by the Australian Energy Regulator (AER) concerning the valuation of easements extant as at 1 July 1999. The dispute centred on the AER's rejection of ETSA's claim for an adjustment to its opening regulatory asset base (RAB) to reflect the value of these easements. The Australian Competition Tribunal (Tribunal) was tasked with determining whether the AER had correctly exercised its discretion in not adjusting the RAB to include the value of these easements.

The primary legal issue was whether the AER had the authority to adjust ETSA's opening RAB as stipulated in the Electricity Pricing Order (EPO). This hinged on the interpretation of clause 7.3 of the EPO and its compatibility with the National Electricity Rules (Rules). ETSA argued that the AER had incorrectly exercised its discretion by not considering their valuation of the easements in detail and that this was an unreasonable decision. The Tribunal needed to ascertain whether the AER's failure to detail consider the valuation was indeed an incorrect exercise of discretion.

The Tribunal found that the AER had the discretion to adjust the opening RAB under clause 7.3 of the EPO, as the context of the EPO did not require subordination to the Rules. This conclusion was based on the fact that while other references in the Electricity Act 1996 (SA) were amended to refer to the Rules, the provision under which the EPO was made was not similarly amended. The Tribunal further found that the AER's decision not to consider ETSA's valuation in detail was an incorrect exercise of discretion because the $6 million figure adopted was only a partial valuation and did not align with ETSA's updated methodology. Consequently, the Tribunal directed the AER to provide a report addressing ETSA's estimates and set a timeline for ETSA to respond, before adjourning the application.

In summary, the Tribunal found that the AER had the discretion to adjust ETSA's opening RAB and that the AER's failure to detail consider ETSA's valuation constituted an incorrect exercise of discretion. This decision established a ground for review under the National Electricity (South Australia) Law, leading to the Tribunal's direction for further submissions and reports.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.