Application by Ergon Energy Corporation Limited (Service Target Performance Incentive Scheme) (No 10)

Link copied
Case Copied 6 min read

AUSTRALIAN COMPETITION TRIBUNAL

Application by Ergon Energy Corporation Limited
(Service Target Performance Incentive Scheme) (No 10) [2011] ACompT 7

Citation: Application by Ergon Energy Corporation Limited (Service Target Performance Incentive Scheme) (No 10) [2011] ACompT 7
Review from: Australian Energy Regulator
Parties: ERGON ENERGY CORPORATION LIMITED
(ACN 087 646 062)
File number: 3 of 2010
Members: MIDDLETON J (DEPUTY PRESIDENT),
MR R DAVEY AND MR R SHOGREN
Date of determination: 29 March 2011
Date of hearing: On the papers (Written Submissions dated 17 March 2011)
Place: Melbourne
Number of paragraphs: 22
Solicitor for Ergon Energy Corporation Limited: Minter Ellison Lawyers
Solicitor for Australian Energy Regulator: Corrs Chambers Westgarth

IN THE AUSTRALIAN COMPETITION TRIBUNAL

FILE NO 3 of 2010

RE:

APPLICATION UNDER SECTION 71B OF THE NATIONAL ELECTRICITY LAW FOR A REVIEW OF A DISTRIBUTION DETERMINATION MADE BY THE AUSTRALIAN ENERGY REGULATOR IN RELATION TO ERGON ENERGY CORPORATION LIMITED PURSUANT TO RULE 6.11.1 OF THE NATIONAL ELECTRICITY RULES

BY:

ERGON ENERGY CORPORATION LIMITED
(ACN 087 646 062)

MEMBERS:

MIDDLETON J (DEPUTY PRESIDENT),
MR R DAVEY AND MR R SHOGREN

DATE:

29 MARCH 2011

PLACE:

MELBOURNE

REASONS FOR DETERMINATION:
(SERVICE TARGET PERFORMANCE INCENTIVE SCHEME)

  1. On 24 December 2010, the Tribunal delivered its reasons for judgment in respect of the part of Ergon Energy Corporation Limited’s (‘Ergon Energy’) application for review of the Australian Energy Regulator’s (‘AER’) distribution determination made on 6 May 2010 (‘the Determination’) relating to its Service Target Performance Incentive Scheme (‘STPIS’): see Application by Ergon Energy Corporation Limited (Service Target Performance Incentive Scheme) (No 5) [2010] ACompT 13.

  2. The Tribunal found that no ground of review under s 71C(1) of the National Electricity Law (‘NEL’) had been established by Ergon Energy.  It directed the parties to confer and provide minutes of the appropriate determination to be made in light of the above reasons by no later than 4pm on Monday, 31 January 2011.

  3. The Tribunal noted that the AER had referred to an error in the course of identifying incentive rates and that this error may need to be reflected in the minutes of the Tribunal’s determination.   

  4. On 21 January 2011, the AER provided Ergon Energy a draft minute which proposed to vary the incentive rates in the Determination.

  5. On 31 January 2011, Ergon Energy wrote to the AER stating:

    (a)the proposed amended incentive rates could not be assessed on their face;

    (b)the AER had not provided a live model to enable Ergon Energy to review the calculation; and

    (c)its view that, as Ergon Energy had failed to establish a ground of review with respect to the STPIS, the only appropriate order for the Tribunal to make was one affirming the Determination.

  6. On 24 February 2011, the AER provided Ergon Energy with a note outlining the alleged error and an extract from the AER’s internal STPIS model.

  7. On 28 February 2011, Ergon Energy responded to the AER confirming that Ergon Energy’s view remained as set out in its letter of 31 January 2011.

  8. On 8 March 2011 the…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Application by Ergon Energy Corporation Limited (Service Tar... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2011] ACompT 7
Decision Date

CaseChat Overview and Summary

In this case, Ergon Energy Corporation Limited applied to the Australian Competition Tribunal for a review of a distribution determination made by the Australian Energy Regulator regarding its Service Target Performance Incentive Scheme (STPIS). The Tribunal, comprising Middleton J (Deputy President), Mr R Davey, and Mr R Shogren, was tasked with determining whether the AER’s calculation of incentive rates in the STPIS was erroneous and whether such an error could be rectified within the Tribunal's review process. The primary legal issue before the Tribunal was whether the AER could rely on a spreadsheet and an internal model to correct an alleged miscalculation in the incentive rates. The Tribunal concluded that the material provided by the AER did not constitute "review related matter" as defined under section 71R(6) of the National Electricity Law. Therefore, the Tribunal was precluded from considering the spreadsheet and the internal model. Consequently, the Tribunal could not correct the alleged miscalculation and affirmed the original determination made by the AER.

The reasoning of the Tribunal was grounded in the statutory framework provided by the National Electricity Law, which restricts the Tribunal's review to "review related matter" and prohibits consideration of any other information. The Tribunal found that the spreadsheet and internal model provided by the AER did not fall within the scope of "review related matter." Additionally, the Tribunal noted that even if the AER had the power to raise the alleged error, there was no basis for the Tribunal to make the correction due to the lack of necessary material. The Tribunal also observed that the Australian Energy Regulator could potentially address the alleged error outside the Tribunal’s review process by revoking the determination under clause 6.13 of the National Electricity Rules. Ultimately, the Tribunal affirmed the original determination and declined to order any costs.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established