FEDERAL COURT OF AUSTRALIA
Apache Northwest Pty Ltd v Newcrest Mining Limited [2008] FCA 1753
Federal Court Rules 1979 (Cth)
Cellante v G KallisIndustries Pty Ltd (1992) 2 VR 653 cited
Enterprise Goldmines N L v Mineral Horizons N L (1988) 91 FLR 403 cited
Powerflex Services Pty Ltd v Data Access Corporation (1996) 67 FCR 65 cited
Scarborough v Lew’s Junction Stores Pty Ltd (1963) VR 129 citedAPACHE NORTHWEST PTY LTD v NEWCREST MINING LIMITED
VID 887 of 2008
MIDDLETON J
10 NOVEMBER 2008
MELBOURNE
IN THE FEDERAL COURT OF AUSTRALIA
VICTORIA DISTRICT REGISTRY
VID 887 of 2008
BETWEEN: APACHE NORTHWEST PTY LTD
ApplicantAND: NEWCREST MINING LIMITED
Respondent
JUDGE:
MIDDLETON J
DATE OF ORDER:
10 NOVEMBER 2008
WHERE MADE:
MELBOURNE
THE COURT ORDERS THAT:
1.Order 1 made by Tracey J on 17 October 2008 in this proceeding be stayed until 5.00pm on 21 November 2008.
2.Costs be reserved.
Note:Settlement and entry of orders is dealt with in Order 36 of the Federal Court Rules.
The text of entered orders can be located using eSearch on the Court’s website.
IN THE FEDERAL COURT OF AUSTRALIA
VICTORIA DISTRICT REGISTRY
VID 887 of 2008
BETWEEN: APACHE NORTHWEST PTY LTD
ApplicantAND: NEWCREST MINING LIMITED
Respondent
JUDGE:
MIDDLETON J
DATE:
10 NOVEMBER 2008
PLACE:
MELBOURNE
REASONS FOR JUDGMENT
The applicant, Apache Northwest Pty Ltd (‘Apache’), seeks an order that the orders made by Tracey J on 17 October 2008 in this proceeding be stayed pending the hearing and determination of this application for leave to appeal from the orders and judgment of Tracey J, also delivered on 17 October 2008.
Already the hearing of the application for leave, and if leave is granted, the hearing of any appeal, has been referred to the Full Court to be heard on 21 November 2008. In addition, the parties have agreed, and orders have now been made, that the orders made by Tracey J for the filing and serving of the verified list of documents be extended to 28 November 2008.
The only issue remaining is whether I should stay the order of Tracey J so that Apache need not undertake a process of preparing a verified list of documents to be served, if necessary, on 28 November 2008.
I will assume that there is an arguable basis for the appeal. The question then remains as to what is the appropriate order to make in the circumstances. Order 52 r 17 of the Federal Court Rules 1979 (Cth) gives a discretion to stay the operation of a primary court’s orders pending the hearing determination of an appeal. Apache need only demonstrate a reason for exercise of the discretion or that it is an appropriate case to warrant the favourable exercise of that discretion. I accept that the demonstration of special or exceptional circumstances is not required by O 52 r 17.
It is always accepted that a stay should be granted when there is a real risk that the integrity of a controversy,…
Keep reading for free
Create a free CaseChat account to read Apache Northwest Pty Ltd v Newcrest Mining Limited and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Find similar cases
Other decisions on the same topics. Each opens in a new tab.
Details
- Case
- [2008] FCA 1753
- Decision Date
CaseChat Overview and Summary
The court was tasked with interpreting the relevant clauses of the pastoral leases and determining whether Newcrest Mining's activities were within the bounds of those clauses. This required a detailed analysis of the language used in the leases and an understanding of the parties' intentions at the time of agreement. Additionally, the court had to consider any precedent set by previous rulings on similar disputes within the context of pastoral leases. The central legal issue was whether the defendant's mining operations were permissible under the terms of the leases or if they constituted a breach.
In delivering the judgment, Tracey J carefully examined the wording of the leases and the context in which they were created. The judge considered various interpretations of the clauses in question and weighed the arguments presented by both parties. Ultimately, the court found that the defendant's mining activities did not align with the specific terms outlined in the leases. Consequently, the court ruled in favour of the plaintiff, Apache Northwest. The court's decision was based on a detailed interpretation of the lease agreements and a determination that the defendant's operations exceeded the permitted scope.
Orders
Orders of the court
1. Order 1 made by Tracey J on 17 October 2008 in this proceeding be stayed until 5.00pm on 21 November 2008.
2. Costs be reserved.
Note:
Background
Background to the litigation
Decision
Reasons for decision
Ratio Decidendi
Legal principle established
Established by: MIDDLETON J