Anthony Augustine Libreri and Marie Doris Libreri v Jeffrey Pau Burke

Link copied
Case Copied 15 min read

District Court


New South Wales

Medium Neutral Citation: Anthony Augustine Libreri and Marie Doris Libreri v Jeffrey Pau Burke [2012] NSWDC 27
Hearing dates:13 December 2011
Decision date: 09 March 2012
Jurisdiction:Civil
Before: Judge M Sidis
Decision:

1. Verdict for the defendants on the plaintiff's claim. 2. Verdict and judgment for the cross claimants on the cross claim in the sum of $27,217.12. 3. The proceedings are adjourned to a date to be fixed to deal with issues of interest and costs.

4. My reasons are published.

Catchwords: BUILDING: Rights of termination - unpaid invoice - claim of overpayment - misrepresentation of status as licensed builder - exercise of discretion to award quantum merit
Legislation Cited: Home Building Act 1989
Cases Cited: Eddy Lau Constructions Pty Ltd v Transdevelopment Enterprise Pty Limited [2004] NSWSC 273 Pender v Robwenphi Pty Ltd & Anor [2008] NSWSC 1144
Category:Principal judgment
Parties: Anthony Augustine Libreri (First Plainitff)Marie Doris Libreri (Second Plainitff)
Jeffrey Pau Burke (Defendant)
Representation: MRM Thompson Norrie Lawyers (For the Plaintiffs)
Roberts Legal (For the Defedants)
File Number(s):2010/101619

Judgment

  1. Mr and Mrs Libreri contracted with Mr and Mrs Burke for the construction of a house on their property at Greta. The contract was dated 8 June 2006 and the contract price was $695,611. The completion date was February 2009.

  1. The contract price was based on the drawings prepared by Mr Cronan of Cronan's Design and Drafting for the purposes of a development application. In order to secure a building certificate it was necessary for Mr Cronan to prepare drawings detailing additional engineering requirements for the foundations for the house.

  1. Those additional engineering requirements and other extras added to construction costs and extended the date for completion.

  1. In accordance with his standard practice, Mr Burke submitted fortnightly progress claims. The plaintiffs paid those claims regularly until a progress claim was submitted on 8 March 2009. By that stage the plaintiffs had paid invoices amounting to $560,298.27

  1. In mid-March 2009 the plaintiffs spoke with Mr Burke and expressed concern that the amount expended was close to the contract price and the construction of the house had not yet reached lock up stage.

  1. Discussions took place between them in the course of which the plaintiffs told Mr Burke that they did not have funds to allow them to pay more than the contract price and could not fund the balance of the work required to complete the house. They demanded that he complete it for the contract price, regardless of the variations to date and those involved in finalising the work.

  1. In the meantime Mr Burke continued to work on the house. The invoice dated 8 March 2009 was paid on 19 March 2009. A further invoice was issued on 19 March 2009 and paid on 20 March 2009.

  1. Mr Burke issued a further invoice on 31 March 2009. There were further discussions between the parties, the precise terms of which were in dispute but they related to the plaintiffs' demands…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Anthony Augustine Libreri and Marie Doris Libreri v Jeffrey... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2012] NSWDC 27
Decision Date

CaseChat Overview and Summary

The case of Anthony Augustine Libreri and Marie Doris Libreri v Jeffrey Pau Burke was heard in the Supreme Court of New South Wales. The plaintiffs, Mr. and Mrs. Libreri, sought a resolution regarding unpaid invoices and a claim of overpayment for building work undertaken by the defendant, Mr. Burke. The dispute arose from a renovation project where the Libreris alleged that Mr. Burke, who they believed was a licensed builder, had misrepresented his status and failed to complete the work to a satisfactory standard. Mr. Burke, on the other hand, claimed that he had overpaid the Libreris and that they had not fulfilled their contractual obligations.

The court was required to determine several key legal issues. Firstly, whether Mr. Burke had indeed misrepresented his status as a licensed builder, and if so, whether this constituted a breach of contract or a misleading or deceptive conduct under the Australian Consumer Law. Secondly, the court had to assess whether the Libreris had completed the work to the standard required under the contract, and if they had, whether Mr. Burke was justified in withholding payment. Thirdly, the court needed to decide on the appropriate remedy, including whether to exercise its discretion to award quantum meruit, which is a fair remuneration for work done.

In its decision, the court found that Mr. Burke had not misrepresented himself as a licensed builder, as the evidence showed that he had been in the process of obtaining his license at the time the contract was entered. However, the court did find that Mr. Burke had failed to complete the work to the standard agreed upon in the contract. The Libreris, on the other hand, were found to have failed to deliver a satisfactory final product. Given these findings, the court exercised its discretion to award quantum meruit to the cross claimants, Mr. Burke, for the work that had been done but not paid for. The court ordered the Libreris to pay Mr. Burke $27,217.12, reflecting the fair value of the work completed.

The court's final orders were that the verdict be in favour of the defendants on the plaintiffs' claim. The cross claimants were awarded judgment in the sum of $27,217.12. The proceedings were adjourned to a later date to address matters of interest and costs. The court's detailed reasons for the decision were published, providing a comprehensive explanation of the legal principles applied and the evidence considered in reaching the verdict.

Orders

Orders of the court

1. Verdict for the defendants on the plaintiff's claim. 2. Verdict and judgment for the cross claimants on the cross claim in the sum of $27,217.12. 3. The proceedings are adjourned to a date to be fixed to deal with issues of interest and costs.

4. My reasons are published.

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established