Amolo v CJ Homes Pty Ltd ATF CJ Homes Trust

Link copied
Case Copied 21 min read

QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL


CITATION:

Amolo v CJ Homes Pty Ltd ATF CJ Homes Trust [2024] QCAT 497

PARTIES:

LUCY AMOLO

(first applicant)

MAXWELL OCHIEN’G AMOLO

(second applicant)

v

CJ HOMES PTY LTD ATF CJ HOMES TRUST

(respondent)

APPLICATION NO/S:

BDL264-23

MATTER TYPE:

Building matters

DELIVERED ON:

8 November 2024

HEARING DATE:

23 July 2024

HEARD AT:

Brisbane

DECISION OF:

Member Howe

ORDERS:

The preliminary issue is determined as follows: The contract was not lawfully terminated by CJ Homes Pty Ltd ATF CJ Homes Trust.  

CATCHWORDS:

CONTRACTS – BUILDING, ENGINEERING AND RELATED CONTRACTS – THE CONTRACT – CONSTRUCTION OF PARTICULAR CONTRACTS AND IMPLIED CONDITIONS – OTHER MATTERS – where a preliminary issue whether the builder had terminated the contract was to be determined – where the building contract included a special condition which said the contract was valid for 120 days and then a price increase might occur – whether the provision rendered the contract void at 120 days – where the provision granted the builder an election to increase the price after 120 days or terminate if no price agreement was struck – where the builder elected not to terminate the contract by claiming a price increase after the 120 days had passed – where termination in reliance on the special condition was not available to the builder after the election – where the provision allowed a price increase but it was not noted on the first page of the contract schedule as required by s 108D of the Queensland Building and Construction Commission Act 1991 (Qld)– where the provision was therefore an attempt to contract out of the Act and therefore void – where the builder had not validly terminated the contract

Queensland Building and Construction Commission Act1991 (Qld), s 108D, Schedule 1B s 14

Allianz Australia Insurance Limited v Delor Vue Apartments CTS 39788 [2022] HCA 38

Perera v Bold Properties (Qld) Pty Ltd [2023] QDC 99
Saaroq Pty Ltd t/as Stroud Homes Wide Bay v Queensland Building and Construction Commission & Ors [2024] QCAT 436

Sargent v ASL Developments Ltd (1974) 131 CLR 634

APPEARANCES & REPRESENTATION:

Applicants:

Self-represented

Respondent:

K T Grimshaw of Counsel, instructed by Creevey Horrell Lawyers

REASONS FOR DECISION

  1. The applicant owners and the respondent builder entered into a HIA Peace of Mind New Home Construction Contract on 3 November 2021.

  2. The contract price was $405,595 including GST. The owners paid $3,800 to cover the preliminary costs of the builder including soil tests, drawings, building approval and costs of contract. By item 10 of the Schedule to the contract the builder was responsible for obtaining building and plumbing approval.

  3. Practical completion was to be obtained within 330 days after commencement and by item 14 of the Schedule the anticipated start date was, given nothing was stated, 60 days from the date of the contract.

  4. The builder had plans prepared and lodged an application for building approval with a private certifier on 10 February 2022.

  5. The following day, 11 February 2022,…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Amolo v CJ Homes Pty Ltd ATF CJ Homes Trust and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2024] QCAT 497
Decision Date

CaseChat Overview and Summary

Amolo v CJ Homes Pty Ltd ATF CJ Homes Trust involved a dispute concerning the validity of the termination of a building contract. The respondent, CJ Homes Pty Ltd ATF CJ Homes Trust, a builder, had entered into a contract with the appellant, Mr Amolo, for the construction of a residential building. The contract contained a special condition that allowed for a price increase or termination after 120 days if no price agreement was reached. Mr Amolo sought a declaration that the contract was not lawfully terminated by CJ Homes.

The primary legal issue for the court was whether the contract was lawfully terminated by the builder under the special condition, which provided that the contract was valid for 120 days and then allowed for a price increase or termination. The court needed to determine if the special condition rendered the contract void after 120 days and whether the builder could validly terminate the contract by claiming a price increase after that period had elapsed. Additionally, the court considered whether the special condition, which allowed for a price increase but was not noted on the first page of the contract schedule as required by section 108D of the Queensland Building and Construction Commission Act 1991 (Qld), was an attempt to contract out of the Act and therefore void.

The court held that the special condition was an attempt to contract out of the statutory requirements of section 108D and was therefore void. As the special condition was void, the builder was not entitled to terminate the contract by claiming a price increase after 120 days. The builder had elected not to terminate the contract, and termination in reliance on the special condition was not available to the builder after the election. Therefore, the contract was not lawfully terminated by CJ Homes.

The court determined the preliminary issue in favour of the appellant, declaring that the contract was not lawfully terminated by CJ Homes. This decision set the stage for further proceedings to resolve the remaining issues in the dispute.

Orders

Orders of the court

The preliminary issue is determined as follows: The contract was not lawfully terminated by CJ Homes Pty Ltd ATF CJ Homes Trust.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

ATF CJ

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Established by: ATF CJ

Full text does not contain this section.