Amann Aviation Pty Ltd v Commonwealth of Australia

Case

[1988] FCA 740

21 Feb 1988

No judgment structure available for this case.

WDGMENT No. 7~bw.."

CATCHWORDS

Contract - Whether statements were promissory - construction - bre'ach - estoppel or "unconscionable" conduct - duty to co-operate in the performance of the contract - "show cause" provision - whether Secretary of Department acting in arbltral or qua,ii-judicial capacity under show cause provision - measure of damages - whether chance of exercise of power to cancel under show.cause provision should be taken into account in assessing damages - proper measure of damages - whether "reliance" damages available - whether permissible to "pierce the corporate veil" in assessing damages.

Evidence - Inference that may be drawn from failure to call evidence - whether available in the case of expert testimony.

Evidence - Judicial notice - whether judicial notice may be taken

of time of commencement of "wet" season in Northern Australia.

AMANN AVIATION PTY. LIMITED v. COMMONWEALTH OF AUSTRALIA

21 December 1988

No. G667 of 1987

Beaumont. J.

Sydney

IN THE FEDERAL COURT OF AUSTRALIA

)

NEW SOUTH WALES DISTRICT REGISTRY ) NO. G667 Of 1987
1
DIVISION GENERAL )
BETWEEN:  AMANN AVIATION PTY. LIMITED

Applicant

- AND : COMMONWEALTH OF AUSTRALIA
Respondent

MINUTES OF ORDER

Judge making order: Beaumont, J.

Date order made:  21 December 1988
Where made:  Sydney
THE COURT ORDERS  THAT:
1. The respondent pay the applicant he sum of

$410,000.00.

2. The

costs of and incidental to the proceedings, to be
taxed.

respondent pay one-half of the applicant’s
Note:  Settlement and entry of orders is dealt with in
Order 36 of the Federal Court Rules.
- INDEX
Sublect Page
Introduction 1
Surveillance of the northern coastline 2
The tender 3
Elaboration of the tender 5
Acceptance of the tender 6
Proposals for the commencement of operations 7
The commencement of operations 22
Termination of the contract 23
The issues arising on the pleadings 25
The grounds for termination stated in the
notice dated 12 September 29
The documentation of the contract 29
The "Conditions of Tender" (Section 1) 30
The "Conditions of Contract" (Section 2 ) 34
The "Specificat ,ion for Charter Aircraft Task"
(Section 3) 36
The Schedules (Section 4) 40
The "Form of Tender" 43
The correspondence referred to in the letter of
acceptance 43

Steps taken by the applicant to prepare for

performance 50
The flying schedule for 12 September 54
The flights undertaken by the applicant on
12 September 55

Construction of the material provlsions of

the contract 56
1. The period of the contract (cl. 2.4) 56
2. Liquidated damages, default and
termination (cl. 2.22; 2.23; 2.24). 50
3. Aircraft requirements (cl. 3.3) 6 5
4. Aircraft availability (cl. 3.11) 6 5
5. Suitability of equipment (cl. 3.15) 66

6.   Technical data provided by the applicant

in the Contract Schedules and in the
correspondence 66
(a) Commencement of the service 6 1

(b) Aircraft availability The first issue:

68

Did the Commonwealth give a

notice to show cause as required by cl. 2.241 1 5
The second issue:  What general principles
determine the measure of damages? 84

The third issue: In assessing damages, should

it be assumed that the Commonwealth would have

exercised its power under cl. 2.24 to determine

contract the event? in any 0 5

Could the Commonwealth have issued a

100 notice? cause" "show

Did the applicant make the flights programmed

100 September? 12 for

Did the applicant provide "sufficient"

September? 102 12 on aircraft
Were the aircraft suitable and fully equipped

103on 12 September?

Is the Commonwealth now estopped from

bceaches? 104 these on relying

Would it have been "unconscionable" for the

Commonwealth to give a "show cause" notice? 122

Did the Commonwealth fall to co-operate in

the performance of the contract? 124
- Wing spar inspection procedures 124
- "Concession" by reason of U.S. Export
Certificate of Airworthiness 136
- Preparat~on of formal contract documents 137

Other allegations of estoppel, waiver,

unconscionable conduct and failure to

co-operate by the Commonwealth 138
FOUL- breaches established 138
Would the Commonwealth have issued a
"show cause" notice? 139

Could the Commonwealth have exercised its

power to cancel under cl. 2.241 141

Did the Commonwealth have a duty to act fairly

to the applicant in considering whether to

exercise its power to cancel under cl. 2.247 142

Would the Commonwealth have exercised its

power to cancel? 146
- The significance of the applicant's

failure to complete all the flights

scheduled for 12 September. 150

- The significance of the applicant's

failure to provide sufficlent suitable

and fully equipped aircraft on

12 September. 154
(1) Insufficient aircraft 154
( 2 ) Lack of endurance 155
( 3 ) Bubble windows 163
(4) Drop hatch 166
(5) Observers' seating 167
(6) Avionics not fitted 169
( 7 ) Air-conditioning equipment not lnstalled
not or functional 169

( 8 ) Intercommunicatlons system not

functional 169

- Given the significance of the breaches,

what chance was there of cancellation? 170

The fourth issue: what loss did the applicant suffer as a consequence of the loss of the benefit of the contract?

174

Claim for repayment of security deposlt 178
Claim for damages for negligent mlsstatement 180
Summary of conclusions 180
cos tS 182
Orders 183
Appendix 1 - Flights scheduled for

12 September 1987.

Appendix 2 - Particulars of offices held by

persons referred to In the reasons for

judgment.

Appendix 3 - Findings on material allegations

in the pleadings.

- The applicant's Revlsed New Points of Claim
- The Commonwealth's Defence
- The applicant's Reply

Appendix 4 - Fuel costs

- Did the rise and fall provision apply to Avtur fuel?

- What would have been the applicant's fuel costs?

Appendix 5 - "Interest" or other cost of serviclng

the borrowing necessary to fund the acquisition

of the aircraft.

Appendlx 6 - The applicant's other claims for

damages.

- "Reliance" loss.

- The claim for loss of goodwill.
- The claim for loss of the prospect of other contracts.

IN THE FEDERAL COURT OF AUSTRALIA )

)

NEW SOUTH WALES DISTRICT REGISTRY ) No. G667 of 1987
)
GENERAL DIVISION )
BETWEEN:  AMANN VIATION PTY. LIMITED

Appllcant

AND :  COMMONWEALTH AUSTRALIA OF
-
Respondent

CORAM: BEAUMONT, J.

PLACE:  SYDNEY

-

DATE: 21 DECEMBER 1988
-

REASONS FOR JUDGMENT

Introduction

Amann Aviation Pty. Limited ("the applicant") sues the Commonwealth for damages for breach of

a

contract made between

them in March 1987. Under the contract, the applicant agreed to

supply aerial Commonwealth. But on the day that the appllcant commenced its

coastal

surveillance

charter

services

to

the

air patrol operations, 12 September 1987, the Commonwealth

purported to terminate the contract. The appllcant claims that

this termination was wrongful and was thus a repudiation of the
contract by the Commonwealth for which the Commonwealth 1s liable
The contract, but contends that sufficient grounds exlsted to lustlfy Commonwealth acknowledges the maklng of a
in damages.
the termination. There is a contest between the parties as to
the true meaning of their agreement and as to the level of

L .

performance offered by the applicant under it. If, contrary to its contention, the Commonwealth be held liable for breach of contract, there is a dispute as to the measure of the loss

suffered by the appllcant. It claims substantial damages,

primarily by way of compensation for the loss of proflts it claims it would have earned if it had been permitted to perform the agreement. The Commonwealth, on the other hand, says that the applicant suffered no loss because it would have lost money on the contract in any event. The applicant also sues for damages for negligent statements alleged to have been made on behalf of the Commonwealth.

Surveillance of the northern coastline

The Commonwealth has established a programme for the

surveillance of Australia's northern coastline. Its earlier history is described in the report by the House of Representatives Standing Committee on Expenditure (May 1986),

especially ch. 2 . The programme reflects the Government's
concern about smuggling, unauthorised landings, quarantine

breaches and other Illegal activities. From a quarantine viewpoint, the most significant feature of the surveillance

arrangements is a daily aerial littoral search. The purpose of
the search is to locate, and provide a basis for reaction to,
unauthorised landings and other activities which may pose a risk
of the introduction of exotic diseases into Australia. The

aircraft carrying out the littoral coastwatch may also be
required to provide a search and rescue service in emergencies.

The tender

On 27 August 1986, the Commonwealth called for the provision of aerial coastal surveillance

for

tenders

in Northern
Australia. The general area to be covered was from Karratha in
Western Australia to Cairns in Queensland. The conditions of
contract referred to in the tender issued by the Department of
Transport ("the Department") wlll be discussed in detail later.

They provided that the contract would be in force for the number

of Acceptance. The contractor was to take over the sectors that aircraft operation specified in the Notice of
of months

it

contracted for from the existing contractor on a sector by sector

basis as

Acceptance and expiry of the existing contract. (The existing
contract was that between the Commonwealth and Skywest Airlines

soon as possible after receipt of the Notice of

Pty. Ltd. ("Skywest") then due to expire on task required of the charter aircraft was the visual search of a

31 March 1987.) The

defined "Littoral nominated by the Department during defined daylight hours. The

Area"

and

certain

other

areas

in

sectors

surveillance portion of the task was to be flown at not less than
140 knots IAS (indicated air speed) nor more than 160 knots IAS,
and normal operating altitudes were to be between 500 to 2,500

feet. The primary purpose of the aerial surveillance operations was to provide reports to the Department of vessels, aircraft and

other activities information was "wide and may relate to The Australian Federal

ighted

uring

the

flights.

The

range

of

Police, Health, and safety at sea aspects

Immigration,

Customs,

Fisheries,

environmental

..." The littoral search was primarily
concerned with the detection, for quarantine purposes, of

unauthorised landings. The aircraft used was to be a "sultable multi engined aircraft" wlth the equipment and capabllitles then specified. The aircraft had to have "endurance of 5 hours on task at an operatlng level of 500 feet AGL [above ground level]

within the 140-160 knot range IAS plus transit of one hour at

normal cruise plus IFR [instrument flight rules] reserves applicable to the entire flight carrying 5 people including the pilot". The contractor was to "provide sufficient alrcraft to

undertake the task making necessary allowance for scheduled
maintenance". The contractor was to provide a specified minlmum
number of backup aircraft relative to the number of "contracted
operating aircraft".

On 25 November 1986, Mr. Robert Amann, on behalf of the firm of R. L P. Amann Aircraft Hire, submitted a tender. Mr. Amann stated that it was intended to import alrcraft from the U.S.A. and then place them on the Australian register; and that

suitable aircraft had been "sourced" and "options placed for a

period of ninety ( 9 0 ) days." The tender stated that the bases
tendered for were Broome, Darwin, Gove, Weipa, and Cairns. The
aircraft proposed were sald to be of the Rockwell Commander type,
680F and FL models, manufactured by "Gulfstream American";

registration numbers were to be advised. To supplement these aircraft, a Beechcraft Queen Air and a Beechcraft Duke would be available. The time needed to make aircraft available for commencement of air patrol from date of letter of acceptance was said to be six months "totaled [sic] (but 1s negotiable) and aircraft availability will be progressrve."

Elaboration of the tender

By letter dated 11 December 1986 elaborating hls
tender, Mr. Amann stated that he tender was "based upon
utilising eleven operatlng alrcraft and three 100% task ready

backup aircraft converted to task ready

and

two

other

aircraft

that

can

be quickly

requirements.". Mr. Amann also stated
that he "would ... expect to become fully operational at all
bases...within six months, with the operation of each base belng

progressive, the minimum time requirement".

Mr. Amann's tender representatives of the parties held on

was

discussed

at

a

meeting

of

7 January 1987. According

the

aircraft fitted out plus 2 spare aircraft not fully fitted out";
that the aircraft were "to be standardised (Aero Commander 680)

meeting by one of the Commonwealth's
to a report

of representatives, Mr. Amann said that

it was "proposed to use 14

and purchased aircraft "will be purchased and fully fitted out

from

one

source

at

this

stage";

and

that

the

in U.S.A." MC.

Amann agreed However, he also said that, after the meeting,

that

he

report

was

ubstantially

accurate.

he explalned to
some of the Commonwealth officers that only 11 aircraft would be

committed to additional three aircraft that can be used for coastwatch, and

the

coastwatch

task

and

that

"we

will

have

an

additional two aircraft that can be made available for

coastwatch, if required."

By letter dated 8 January 1987, Mr. G.B. Richardson,

Director of Supply and Services, Department of Transport, wrote to Mr. Amann referring to the meeting of 7 January and seeklng further details of the tender. A "more definitive work plan" was

requested. By letter dated 12 January 1987, Mr. Amann informed

the Department that, "[blased upon a contract award of early

March 1987, we would become operational at our main base Darwin

by the end of June 1987, Broom [sic] the beginning of July, Weipa

by mid-end July, Cairns by the end of July, and Gove by the end

of July early August."

that any contract be awarded to the applicant rather than to his
firm.

In this letter, Mr. Amann requested

Mr. Amann and Several aspects of the tender, particularly

Mr. Richardson met on 16 January 1987.

Mr. Amann's costings,

were discussed. On 17 February 1987, Mr. Amann applied to the

Department of Commander aircraft. They were said to

Aviation

for

permission

to

import

12

Rockwell

be of the 680FL or 680W

models but no other details were given.

By letter to Skywest dated 11 March 1987, the Department confirmed its agreement with Skywest that the existing coastal

surveillance charter services contract was to be extended for a
three month period expiring on 30 June 1987.
Acceptance of the tender

By letter dated 12 March 1987, the Department informed the applicant that its tender had been accepted "subject to your

company e tering Commonwealth...The contract

formal

a

agreement

to

wi h

the

documents will be sent o you
shortly." (In fact, no formal contract was executed.) The
letter stated that the contract would "be in force for a perlod
of 8 X 36 aircraft months." It was also stated that the aircraft
accepted were Rockwell Commander 680FLs to operate out of bases
at BrOOme, Darwin, Gove, Weipa and Cairns at rates of charge
then specified. Receipt of the letter was acknowledged by Mr.

Amann on behalf of the applicant on 13 March.

Proposals for the commencement of operations

On 19 March, Mr. Amann gave the Department some of the

serial numbers of the aircraft he proposed to import which were

being modified in the U.S.A. He also provided the Department with a "Proposed Phase in Program" which contemplated starting

operations at the five bases over the period from early May to
early July. He said that these timings were sub~ect to, inter

alia, suppliers meeting deadlines.

On 24 March, at a meeting between representatives of the
applicant and of the Department of Aviation, it was proposed by

Mr. Amann that all bases be "fully operational" within six months

of 12 March.

On 27 March, Mr. Amann wrote to Mr. Richardson amending the phase-in programme given on 19 March in minor respects. All aircraft were to be operating by 11 July but this was still subject to suppliers meeting deadlines and it was also said to be subject to the Department of Aviation's Airworthiness Certification.

The parties met again on

the applicant had at least 11 aircraft available; that plans
were "well in hand" to bring the alrcraft into operatlon, and

6 April. Mr. Amann sald that

that firm officers of the Department of Aviation.

phase-in

dates

would

be

given

after

meeting

with

At a meeting of the parties held on 9 April to discuss
progress, Mr. Rex Ramsey, Senior Executive Officer, Surveillance

Resources, Department of Transport, said that the final date to
have the organisation up and running completely was 12 September
and if the applicant missed that date the contract would be "in

doubt".

By letter dated 21 April, Mr. Amann provlded the
Department with "critical a path network programme". The
programme suggested that the applicant would take over the

existing bases from skywest over a period ending in December. However, the letter stated that completion of all tasks would be prior to 12 September. Mr. Amann also stated that the dates in

the programme "may be adjusted due to delays beyond our or our
suppliers reasonable control."
Mr. Richardson sought clarification of what appeared to
be some confuslon in the programme. On 21 April, Mr. Amann
informed Mr. Richardson that operations would start as follows:
Darwin - 16 July; Gove - 17 July; Cairns - 18 July; Broome -
1 0 September; and Weipa - 12 September. Mr. Richardson said that

he would inform the Minister and Skywest.

8   9.

By letter dated 28 April, Mr. Richardson referred to the

meeting held on 6 April and confirmed that the respondent

required "the 3 additlonal aircraft numbers for inclusion in the draft contract document to bring the total to 14 aircraft as per

your tendered offer." Richardson that he would provide the three

On 29 April, Mr. Amann informed Mr.

additional aircraft

numbers requested on his return from the U.S.A. Mr. Richardson's

note of the conversation continued:

"I indicated we would be writing for advice of

optimistic dates re transition - our particular concern being lateness of September dates in terms of contract milestone."

By letter dated 30 April, Mr. Amann informed the

Department of Avlation that the dellvery date of the first five aircraft was 1 July and gave the serial numbers of the "flrst eleven aircraft". He added:

"I am planning on the aircraft belng on the ground for

one week after arrival in Australia. Two weeks are

available before operations start on 12 July ..."

In the first week of May, Mr. Amann notified the Department of a change of aircraft type from 14 Rockwell 68OFLs

(piston engined aircraft) to 11 Rockwell 690s and three Rockwell

680Ws (both turboprop aircraft).

By letter to the Department dated 7 May, the applicant confirmed that it was purchaslng 11 Aero Commander 690 series aircraft and three Aero Commander 680W aircraft.

By Commonwealth and Skywest agreed that their contract

an

agreement

in

writing

dated

19

May,

the

be extended
beyond 30 June. It was further agreed that Skywest would
progressively reduce its services in the manner specified in the

agreement; in specified closing date, upon glving Skywest not less than

addition,

the

Commonwealth

might,

prior

to

a

60

days' notice, require Skywest to reduce its services.

By McNamara, the Regional Director of the South Australia/Northern

letter

to

the

applicant

dated

20 May, Mr. R.

Territory Region clarification of the particulars of the aircraft being purchased. the f D partment of Aviation, sought

By letter dated 21 May, the Commonwealth gave notice of its agreement to the change of aircraft types proposed provided

that the equipment was suitable and that no additional cost to

the Commonwealth was claimed. Serial numbers were requested for

insertion in numbers were provided by the applicant by letter dated the formal contract documents. Fourteen serial

24   May.

The Commonwealth says that, with one exception, the serial
numbers were not referable to any aircraft acquired by the
applicant or by CVC Investments Pty. Ltd. ("CVC"), a company
associated with the applicant. The applicant accepts this but

says (a) that the applicant was passing on information received
by it from the United States; (b) that the significance of this

matter should be assessed in the light of subsequent events, to

which it will be necessary to return later.

By a purchase agreement dated 25 May between Northeast Air, Inc. of Portland, Maine, U.S.A. ("Northeast") and

the

applicant, lt was agreed that Northeast would sell and the

applicant would purchase 11 Commander aircraft consisting of 680,

681 or 690 Series Turbo Commanders. Northeast agreed to deliver

the 11 aircraft for no more than U S S 2 , 4 4 8 , 0 0 0 . 0 0 but stated it

may exceed the "budgeted amount" with the prior approval of the

applicant. This agreement was superseded by a brokerage

agreement entered into on 15 June between Northeast and CVC, to
be described later.

Representatives of the Department of Aviatlon met with representatives of the applicant on 26 May. M r . Amann stated that the applicant had bought 14 aircraft - six 6905, three 680Ws and five 681s. In elaborating this statement, Mr. Amann said that the applicant hoped to acquire more 690s instead of the

three 680Ws on which holding deposits had been paid. The

applicant expected the first batch of three aircraft to arrive in Darwin on 23 June, and the second batch of three aircraft to arrive there on 6 July. Procedures to obtain Certificates of Airworthiness from the Department of Aviation were discussed.

By letter dated 1 June, the applicant informed the

Department that "possible delays may be envisaged due to conflicting information given to us by the Department of Aviation

in relation to the non-destructive testing of the wing spar for
the aircraft we propose using ... We will advise you of the
expected time delays, if any, ..."

By letter dated Department of Aviatlon for permlsslon to import 14 AeKO Commander

2 June, the applicant applied to the

aircraft (six 690s, five 681s and three 680Ws). The applicant
stated that, if possible, 690 or 681 aircraft would be purchased

instead of the 680W models.

By letter dated 5 June, the Department responded to the

applicant's letter dated 1 June and asked "to be kept fully
informed of any delays immediately as they arlse and the
resultant impact hese delays might have on the proposed
timetable, (July to September), for handover of Coastal

Surveillance Servlces."

On 9 June, letter of 20 May referring, inter alia, to the meeting held on

the

applicant

replied

to

Mr.

McNamara'S

26

May.

By a further letter dated 9 June, addressed to the

Minister for arrival date in Darwin for the first six aircraft was 10 July and

Aviation,

the

applicant

stated

that

the

planned

not 23 from the wing spar inspection procedures. However, the applicant

June as had been expected. The delay was said to arise

also stated that it "will still be in a position to take over all

Coastwatch operations by 12 September ..."
On 15 June, Northeast entered into a "brokerage
agreement" with CVC. Under the agreement, CVC agreed to purchase

and Northeast agreed to arrange the purchase, on behalf of CVC,

of 11 Commander aircraft, conslsting of 680, 681 or 690 Series
Turbo Commanders for not more than US$2,448,000.00. Northeast

agreed to use Its best endeavours to ensure delivery of the first

five aircraft by 30 July and the remainlng six alrcraft by 30

August. Pursuant to this agreement, CVC acquired a number of aircraft at about this time. CVC also acquired aircraft from other sources at other times.

By letter dated 19 June, Mr. Rlchardson sought the
applicant's confirmation that it would commence operations at

Darwin, Gove and Cairns on 16, 17 and 18 July respectively. The letter stated that "the Commonwealth would consider any failure of your suppliers to meet thelr agreed deadlines with you, should

that occur, as a matter entirely within your control."

The applicant replied by letter dated 19 June stating

that "[tlo period from 16 July

ensure

Coastwatch

Operations

continue

during

the

... until [the applicant's] arrcraft are
on-line in Australia, [the applicant] is considering three
options. These are:
a. to lease Skywest's Coastwatch aircraft;
b. to hire other aircraft for the task.. .
C. to request the Department ... to arrange for Skywest to

continue operations until mid-August."

By Department that it would commence operations as follows:

letter dated

24

June, the applicant informed the

"Darwin: 16th July - in cross-hlred alrcraft
Gove : 17th July - in cross-hlred alrcraft
Cairns: 18th July - in cross-hired aircraft

Broome: 10th September - in our own aircraft

Weipa:  12th September - in our own aircraft"

This interim operations proposal was relected by the Department by letter dated 30 June.

The applicant was also

informed that by 1 September it would be required to prove that

it would be capable of performing the contract. This would involve flight trials in Australia witnessed by a Departmental officer. Further, the applicant was required to guarantee the supply of all fully fitted aircraft, including backup aircraft,

in sufficient time to commence performance not later than 12

September.

By letter dated 3 July, the Commonwealth gave notice to Skywest of its intention to vary the contract with Skywest by phasing out Skywest's operations progressively on the following extended dates: Darwin - 1 September; Gove - 4 September; Cairns - 7 September; Broome - 10 September; and Bamaga (Weipa)

- 12 September.

The Commonwealth informed the applicant of the

Skywest extension by letter dated 14 July. The applicant was
also informed that the Commonwealth required a minimum of 30

clear days' notice if any of the phase-in dates were to be further extended and that if the applicant was unable to achieve

these dates, action might be taken in accordance with cl. 2.23.
(under cl. 2.23, if the contractor fails to make a flight in the
manner required under the contract and the Secretary of the
Department is not satisfled that the fallure was due to accident

or other reasonable cause beyond the control of the contractor, the contractor shall, without prejudice to any other remedy, pay the Commonwealth liquidated damages.)

By letter dated 15 July, the applicant accepted the provisions of the Department's letter

dated

14 July, agreed

to

performance testing and modified the "initial start up date" for
Broome to 12 September and for weipa to l0 September. The

applicant stated that "no default clauses should be implemented

before 12 September, as we are confident that default will not

occur. "
On 22 July, Mr. McNamara, of the Department of Aviation

wrote to the applicant informing it that, although approval was occasionally given by the Department for aircraft to operate in excess of the defined maximum take off weights in special circumstances, the applicant should not anticipate any such approval for the conduct of routine aerial work flights.

By letter dated 21 July, the Department of Transport and Communications (which from 24 July took over the functions of

both the Department of Transport and the Department of Aviation)

informed Skywest of the applicant's proposal to modify the
initial start up date to 12 September at Broome and to 10

September at Weipa with the consequence that Skywest's closure dates at Broome would be changed to 12 September and at Bamaga to

10 September. Skywest agreed to these changes by letter dated 28
July.

By applicant for details of its plans for alrcraft delivery from the

telex dated 29 July, the Department asked

the

U.S.A. to Darwin and for details of the programme for the
modification of the aircraft in this country. By telex dated 3 0

July, the applicant informed the Department that the first batch of three aircraft was expected to arrive in Darwin from the

U.S.A. on 6 August; the second batch of five aircraft was
expected to arrive in Darwin on 22 August; and the third batch

of three aircraft was expected to depart the U.S.A. on 24 August. The applicant's plans were based on an average estimate of a seven day ferry fllght and of 14 days for modifications and certification.

By letter dated 5 August, the Department agreed to the
proposed modification of the initial start up date to 12

September at Broome and 10 September at Weipa, sublect to Skywest's agreement (Skywest's agreement was confirmed in writing on 12 August).

By letter dated 7 August, the applicant informed the Department of delays in the ferry of the first two aircraft

being

imported from the U.S.A.

By letter dated 12 August, the applicant informed the Department that it was expected that the first two aircraft

would

arrive in this country before 14 August; the next four alrcraft
would depart the U.S.A. on 13 August, followed by another group
of four aircraft departing on 18 August; the last two aircraft
would depart on 21 August; so that the 12 alrcraft purchased in
the U.S.A. were expected to be here by 21 August.

By letter dated 12 August, the Department, referring to

its letter dated 30 June, stated that no further extensions of
time for the applicant's preparations would be permitted; if the

applicant did not commence all its operations at all bases as the

contract required immediately proceed to terminate the contract;

by 12

September,

the

Commonwealth

would

in this respect,

notice was given that time was of the essence.

By letter dated 13 August, Skywest informed the
Department that it was willing to provide its services up to 12
September and "if necessary beyond that date."
By letter to the applicant dated 14 August, the

Department, referring to its letter dated 5 August, confirmed the initial start up dates as 12 September at Broome and 10 September at Weipa.

By letter dated 17 August, the applicant, referring to

the Department's letter dated 12 August, denied that he

applicant was in breach of the contract and requested a meeting "to reach a common interpretation of the Coastwatch contract." By a further letter dated 18 August, the applicant also denied that the Commonwealth could make time of the essence.

Representatives of the parties met on 21 August. There
is a dispute as to what happened at the meeting. This will be
dealt with later. For immediate purposes, it is sufficient to

note that by letter of that date, the Department set down the salient points of the discussion as follows: (a) the Department confirmed that its letter of 12 August was not intended to imply

that the applicant was in breach of the contract; (b) the parties confirmed that the date at which the applicant was contractually committed to be fully operational at all bases was

12 September; and (c) the Department "emphasised the critical

national importance of the coastwatch services, the need to avoid

any discontinuity in surveillance operations and the essential

requirement for full performance of the surveillance operations in accordance wlth the contract on and from 12 September ..." By letter dated 21 August, the applicant agreed wlth the Department's summary.

By a further letter dated 21 August, the Department accepted the offer made by Skywest in its letter dated 13 August to continue its services up to 12 September in the event that the applicant was not operational by the dates previously arranged (i.e. Darwin - 1 September; Gove - 4 September; Cairns - 7

September; Weipa - 10 September; Broome - 12 September).

By letter dated Department that it proposed to commence operations out of

20 August,

the applicant informed the

Darwin

on 1 September using an Aero Commander 690A aircraft; two other

aircraft were undergoing inspections for Certificates of Airworthiness in Darwin and Cairns; another aircraft was remaining on the U.S.A. register for a short period and was being used for aircrew training in Darwin; another five aircraft were in transit from the U.S.A.; and the remainder were being prepared for ferrying to Australia.

At about this time, the applicant also sought from the Commonwealth concesslons in

respect

of the

regulatory

requirements governing the use of aircraft for the purposes of the contract in the first 90 days of its operations. Shortly thereafter, the Commonwealth granted some of the concessions but refused others.

By letter to the applicant dated 31 August, the Department stated that, since the applicant could not give an unequivocal undertaking that it would be able to commence operations from Darwin as scheduled on 1 September and as required by the contract, the Department had asked Skywest to provide surveillance from Darwln until 11 September. The letter reiterated the importance of continuity of the operation and the

need to avoid uncertainty in the provision of services. The

applicant responded to this letter by telex dated 31 August

informing the Department that the applicant would be in a position to undertake the coastal surveillance flight from

Kununurra to Darwin on 1 September.

By letter dated 31 August, the Department informed

Skywest that irequired

surveillance operations from Darwin from 1 September until 11
September inclusive.

Skywest to undertake coastal

By applicant again offered to fly the Darwin sector that day, lf the

letter to the Department dated 1 September, the

Department approved the commencement of operations. The

Department replied by letter of that date requiring the applicant

to commence operations in accordance with the contract. The

applicant was asked to state whether, inter alia, its aircraft

met the specifications in the contract.

By letter to the applicant dated 2 September, the
Department required the applicant to demonstrate to the
satisfaction of the Department that the full conditions of the
contract would be met: (a) in relation to each base on the date
scheduled prior to 12 September; (b) on 12 September; and that

if the applicant had not established its ability to commence
operations from each base a clear 36 hours before the first
scheduled service, the Department intended to notify Skywest that
it would be required to provide a service from that base until

and including 11 September.

Also on 2 September, Mr. Secretary to the Department, telephoned

R.D.B.

Beale, Associate Mr. Amann and was

informed that it was expected that the two aircraft for operation
from Gove would be registered by 4 September but that some of the

modifications to those aircraft required by the contract would not be completed until 9 September. The Department confirmed this conversation by letter dated 3 September. The letter also informed the applicant that the Department had asked Skywest to undertake the coastal surveillance from Gove from 4 to 11 September.

By letter to the Department dated 3 September, the

appllcant stated that of the applzcant's lx alrcraft In Australia, one had recelved a Certlflcate of Airworthlness, and the others were undergoing inspections for that purpose; three aircraft were In transit from the U.S.A.; three aircraft were about to depart the U.S.A. and were expected to arrlve in Australia on 13, 17 and 27 September; two other aircraft had been procured locally and were expected to be In Darwin on 5 September; and the appllcant would be in a position to glve the

Department the required 36 hours' notice of its intention to

start operations at all five bases on 12 September.

letter to the applicant dated 4 September, the Department confirmed that the applicant would not have registered aircraft available to provide services from Cairns on 7 September; and Skywest had been asked to undertake the services

By

until 11 September. A similar letter was written to the

applicant on 8 September in respect of the services from Weipa from 10 September; Skywest had been asked to provide services

from Bamaga on 10 and 11 September.
By letter dated 9 September the applicant provided the
Department with a "checklist" indicating the state of readiness

of its aircraft. By letter to the applicant dated 10 September, the Department referred to a meeting held that day between representatives of the parties and expressed concern with the state of preparation of the applicant's aircraft. The Department

confirmed the parties' agreement at that meeting that

Commonwealth officers would inspect the appllcant's alrcraft at each of the bases at 8.00 a.m. on 12 September. The lnspectlon was said to "cover both regulatory and contractual elements."

The Commonwealth would "make its decision on the future of the

contract on 12 September."

By letter to the Department dated 11 September, the applicant stated that, from at least 21 August, the Department had been aware that the applicant would not be able to fully comply with the requirements of the contract by 12 September; but that the applicant would be "in a position to substantially comply with the terms of the contract and that such matters as were outstanding at that date would be complied with within a month of the start up date." The applicant stated that, as of the following day (12 September) they would have one aircraft at each of the bases and two standby aircraft.

By letter to Department joined issue with the applicant's

the applicant dated 11 September, the

contention in its

letter of that date that at the meeting held on 21 August it had been indicated that the applicant would not be able to comply

fully with the requirements of the contract.

The commencement of operations

As foreshadowed, inspection of the applicant's aircraft

was carried out by Commonwealth officers on the morning of 12

September. After the inspections, the aircraft flew some of the
sectors nominated by the Department pursuant to the contract.
Termlnation of the contract

In the afternoon of 12 September, Mr. Beale purported to termlnate the contract by the following letter to the applicant:

“RE:  COASTAL SURVEILLANCE CONTRACT NO. 86/086/084

NOTICE OF TERMINATION

I glve you notice that I hereby terminate the

abovementioned contract, effective from the

expiration of Saturday 12 September 1987, because your company has failed to comply with the requirement of the contract to commence performance of coastal surveillance services from all bases in accordance with the contract, on 12 September 1987.

Your company’s contract with the Commonwealth

requires that it have 14 aircraft operating by 12 September 1987, being 6 months after acceptance on 12 March 1987 of the tendered offer of R. & P. Amann Aircraft Hire of 2 5 November 1986, and subsequent additional information. On 12 August 1987 I indicated to you that the Commonwealth considered that time was of the essence and that it would

terminate the contract if your company did not commence all its operations at all bases as the contract requires by 12 September 1987. Again, on 21

August 1987 I emphasised to the Chairman of your
company the essential requirement for ull

performance of the surveillance services in accordance with the contract on and from 12 September 1987.

As at today’s date I have ascertained from my officers that your company has no aircraft available for coastal surveillance services, fully equipped as

required by the contract and having Australian

registration. The availability of the aircraft at

the surveillance bases today, was as set out in the
attachment to this Notice of Termination.

Your company is seriously deficient in not having available the requisite number of aircraft equipped in conformance with the contract, and this deficiency is, in my view, so serious a breach of your company’s

obligations that I am not prepared to allow the
contract to continue.

The Commonwealth reiterates that the Coastwatch service is of critical national importance and the public interest requires that such service must be

maintained by the aircraft and supporting services set out In the contract; which your company has patently not provided.

...

“ATTACHMENT TO NOTICE OF TERMINATION OF 12 SEPTEMBER

1987 Gove 681: VH - NYD. Australian reglstration with

Certificate of Airworthlness; not fitted with bubble windows, drop hatch, adlustable seating and does not have the endurance required by the contract.

Weipa

Certificate of Airworthiness; not fitted with bubble 681: VH-NYA . Australian registration with
windows, drop hatch, adjustable seating and does not
have the endurance required by the contract.

680: VH - EXP. Australian registratlon with Certificate of Airworthiness, not fitted with bubble windows, drop hatch, adjustable seating or airconditionlng. Addltionally not fitted with the following avionics: weather radar, VLF Omega

navigation system or radio altimeter, required by the
contract.
Darwin

690: VH - NYB. Australian registratlon with Certificate of Airworthiness; not fitted with bubble windows, drop hatch, adjustable seating and does not have the endurance required by the contract.

681: VH - NYH. Australian registration but no Certificate of Airworthiness. Undergoing maintenance.

680: VH - EXZ. Australian registration with
Certificate of Airworthiness; not fitted with bubble

windows, drop hatch, adjustable seating or airconditioning. Additionally not fitted with the following avionics weather radar, VLF Omega navigation system and radio altimeter, required by the contract.

Cairns

681: VH - NYE. Australian registration with Certificate of Airworthiness; not fitted with bubble

windows, drop hatch, adjustable seating and does not
have the endurance required by the contract.
681: VH - NYG. Australian registration but no
Certifrcate of Airworthiness. Undergoing
maintenance.

8   25.

BKOOme

681: VH - NYF. Australlan registratlon wlth

Certificate of Airworthlness; not fitted wlth bubble windows, drop hatch, adjustable seatlng and does not have the endurance requlred by the contract."

The applicant contested the Commonwealth's entltlement

to terminate the agreement. By letter dated 15 September the
applicant, claiming that, in giving the notlce of terminatlon,

the Commonwealth ad repudiated its obllgations under the

contract, purported to accept that repudiation and to rescind the

agreement and claimed damages.

The issues arising on the pleadings

The allegations made by the applicant In its Revised New

summar sed be Claim f llows: Points m y of a
(1) On or about 12 March 1987, the parties entered into a

contract.

(2) After the ntry into the agreement, but before the

applicant embarked upon its performance on 12 September

1987, the representations to the applicant: (a) that the applicant

Commonwealth

made

the

following,

inter

alia,

was required to have available on any day only so many

operating aircraft as were required to perform scheduled
flights on that day, together with certaln backup aircraft,

up to a total of eight operating aircraft, three backup

aircraft and three additional aircraft which were not
required to be operational; (b) that it was not necessary

for each of such aircraft to be fitted with bubble windows,
drop hatches or long range fuel tanks by 12 September 1987

and that a period of at least one month after that date was

permitted for their installation; (c) that only 5 flights

would be scheduled on 12 September 1987; (d) that in the

event that contractual

the

applicant

did

not

perform

all

Its

obligations September 12 by 1987, the

Commonwealth would not purport to terminate the agreement

but would

apply alternatively, the Commonwealth would issue

the

provisions

of

cl.

2.23

OK,

a notice to
"show cause" pursuant to cl. 2.24 which would give the
applicant sufficient tlme to comply; (e) that the two of
the aircraft would be accepted notwlthstandlng their

absence of certain avlonlcs.

Relylng upon these representations, the applicant took a
number of steps In preparation for, and in performance of,
the contract.

On 10 September 1987, the appllcant gave the Commonwealth a

detailed report of the situatlon of its aircraft; on 12

September 1987, the Commonwealth inspected the alrcraft;
the Commonwealth then became aware of certaln deflciencies

in terms of the numbers of aircraft required by the

agreement and In terms of equipment that was then not

fitted in accordance with the contract.

On 12 September 1987, with knowledge of these deficlencies,

the Commonwealth instructed the applicant to commence
flyrng operations and the applicant dld so.

The Commonwealth thus waived any right to terminate the
contract because of any of these deficiencies and afflrmed
the contract.

Alternatively, the Commonwealth is estopped from relylng upon these deficiencies as constituting a breach of the agreement.

The acts done by the applicant pursuant to the contract

constituted substantial performance of its obligations.

The Commonwealth failed to give a "show cause" notice as
was required by the agreement before the Commonwealth could

terminate the agreement.

If a proper "show cause" notice had been given, the

applicant would have complied with it.

On 12 September 1987, the Commonwealth purported to

terminate the contract; the Commonwealth was not entitled

to do so and thus repudiated the agreement.
It was a term of the agreement that the parties would do
all acts necessary to bring about its performance. In
breach of this term: (a) the Commonwealth refused

permission to the applicant to operate certaln aircraft in Australia for a short period while certain of its aircraft retained their Unlted States registration; consequently the

applicant's preparations to perform the contract were
delayed; (b) on 12 September 1987, the Commonwealth
scheduled inspections and tests of the applicant's aircraft

and personnel, thereby delaying certain flights; (c) the

Commonwealth delayed preparation of the formal contract

which occasioned delay in the applicant's arrangements for
finance.
As a consequence of the Commonwealth's conduct, the
applicant was prevented from implementing the contract.

By letter dated 15 September 1987, the applicant accepted the Commonwealth's repudiation.

The Commonwealth owed the applicant a duty of care to ensure that information given to the applicant, with respect to the requirements of the agreement, was accurate.

In breach of this duty, the Commonwealth gave the following erroneous information (a) as to the number of operating

aircraft required; (b) as to the need to have bubble
windows, drop hatches and long range tanks installed by 12

September 1987; (c) as to the endurance of the long range tanks in terms of their compliance with the requirements of the agreement.

The Commonwealth supplied erroneous information with
respect to wing spars, thereby causing delay and expense.

The Commonwealth erroneously informed the applicant that the terms of the contract requlred the applicant to commence operations not later than 12 September 1987 whereas it was not obliged to commence until 13 September.

The Commonwealth made, inter alia, the following

representations to the applicant which the Commonwealth is

now estopped from denying: (a) that the applicant was

required to have only eight operating and three backup

aircraft together with three additional aircraft which were

not required to be operational; (b) that the bubble

windows, drop hatches and long range fuel tanks were not required until one month after 12 September; (c) only five flights would be scheduled on 12 September; (d) in the event that the applicant did not perform all its obligations under the contract by 12 September, liquidated damages under cl. 2.23 or a notice to show cause would be given under cl. 2.24.

In giving the Notice of Termination, the Commonwealth acted "wrongfully, arbitrarily, capriciously and unreasonably".

The contentions made by the Commonwealth in its Defence

can be summarised thus:

(1) The making of a contract is admitted.

( 2 ) The commencement date for flying operations was 12

September 1987.

(3)

The applicant was to take over from Skywest on a sector by sector basis as soon as possible after acceptance of the applicant's tender and the expiry of Skywest's contract on 31 March 1987.

The date of commencement of operations in each sector would
be fixed by agreement and in any case would take place in
all sectors by no later than 12 September.

The applicant is estopped from asserting that the date of commencement of operations was 13 September.

On or about 27 April 1987, it was agreed that the applicant would commence operations from Darwin on 16 July 1987, from

Gove on 17 July, from Cairns on 18 July, from Broome on 10
September and from Weipa on 12 September, and time was
agreed to be of the essence.
On 14 or 15 July 1987, those dates were extended as
follows: from Darwin on 1 September, from Gove on 4
September, from Cairns on 7 September, from Weipa on 10
September and from Broome on 12 September, subject to a
minimum of 30 clear days notice if any of these dates were
to be extended; otherwise time was of the essence.

The applicant failed to commence operations as required and this requirement was of the essence.

Alternatively, on 12 August 1987, the Commonwealth made the
commencement of operations by the applicant from all
sectors by 12 September 1987 of the essence of the
contract.
(10) The applicant failed to commence and carry out operations
on 12 September and thereby became in breach of the
contract.
(11)
On

and before 12 September, the applicant failed to take

contract so that the Commonwealth was entitled to, and did,
terminate the contract.

the steps necessary to equip itself to carry out the
The applicant induced the Commonwealth to enter into the
contract by fraudulently, deceptively or negligently
representing to the Commonwealth in November and December
1986 and in January 1987 that the applicant had options
over certain aircraft. (This defence was abandoned during
addresses.)

By its Reply, the applicant puts the following:

At the time of its purported termination of the contract, the Commonwealth was unwilling and unready to perform its obligations.

The Commonwealth waived any requirement that the applicant commence performance on the dates mentioned in the Defence.

The applicant denies that time was of the essence.

The Commonwealth is estopped from replying upon the matters said to justify termination of the agreement.

e 29.
(5) For the Commonwealth to insist upon strict and literal
compliance with the provisions of the contract would be

unconscionable.

The grounds for termination stated In the notice dated 12
September

The Commonwealth's case is that determine the contract because the appllcant had committed a

it was entitled to

"serious" breach of their agreement by failing to provide 14

fully equipped aircraft with Australian registration operating
from all bases commencing on 12 September. In its Defence, as
has been noted, the Commonwealth says that 12 September was

the agreed date of commencement; alternatively, time was made

of the essence in this respect. Then the Commonwealth alleges

that on or before 12 September the applicant failed to take all such steps as were necessary to prepare itself

for the

contract, including the provlsion of 16 aircraft.
The documentation of the contract

There constitutes the agreement between the parties. There is also

is

adispute

as

to

the

m

lateri a1

which

controversy a as to the terms of the contract: the

Commonwealth says that certain information supplied by the

applicant was intended to be promissory and a term, or perhaps

even a condition, of their agreement; the applicant, on the

other hand, says that this material was merely by way of a
proposal and was not intended to be promissory.

The contract documents consist of the "Condltlons of Tender" (Section l), the "Conditions of Contract" (Section

2 ) ,

a "Specification for Charter Aircraft Task" (Section 3),
certain "Schedules" (Section 4 ) , a "Form of Tender", the

applicant's letter dated letter of acceptance dated 12 March, together with certain

25 November, and the Commonwealth's

material mentioned in the applicant's letters mentioned In
that letter of acceptance.

In order to understand the respective contentions of

the parties, it is necessary to refer to the details of the

relevant parts of the contract documents.

The "Conditions of Tender" (Section 1)

The described in the specification

tender

was

to

be

for

the

whole

of but the tenderer could offer

the

task

for any or all of the operating bases (cl. 1.2). The tenderer

was deemed to have (a) examined the tender document and any

other relevant information made available in writing by the

Department; (b) risks, contingencies and other circumstances having an effect

examined

all

information

relevant

to

the

on his tender and which was obtainable reasonable enquiries; and (c) satisfied himself as to the

by

the making of

correctness and sufficiency of his tender (cl. 1.4).
The tenderer had to complete the "Schedules at

Section 4" "Statement of Compliance"

and to provide certain "information", including

a

in respect of every clause of the

speclflcation. Where the tendered equlpment dld not comply wlth the speclflcatlon, details had to be glven; any such fallure could be taken into account In assessing the relative merits of tenders (cl. 1.7.1). Tenderers were to demonstrate,

by flight trials If necessary, under condltlons and configurations specified by the Department, that the nominated

aircraft could meet all the specificatlons called for and
could provide an adequate working environment for aerlal
surveillance operations to the satisfaction of the Secretary

(cl. 1.7.2). Tenderers were to have drscussed with the Department of Aviation the special clearances necessary to meet the requirements of Air Navigation Orders for the task

(cl. 1.7.3).

The tenderer was to complete a "Schedule of capacity for flying hours available from each base" stating

the

minimum and maximum hours required. The schedule was to be

"based on" a "typical flight program" shown in Annexure 1 (cl.

1.7.5).

Annexure 1, as amended by letter from the Department dated 21 October 1986, is as follows:

- , h
c
1 -
' P
l

-

..
ci

c. ,-

- 1 ..
5 P
I '

I

- :. :,

1

5

I

I

z l .
rl
I . I i
I
I !
l
U') 0
:. o * m . .

6

I 0
I 0
I .
l t

L

m 01

N

m 0
a
L
I Y
I 0

I.   .I

I &

(It will be noticed that this contemplated the use of a

total of eight aircraft - two at Broome, Darwin and Weipa (or
Horn Island or Bamaga) and one at Gove and Cairns.)

The hours shown in Annexure 1 were "not guaranteed to be

flown" in any one week or provided by tenderers in the schedule were to be subject to

over a period

of time"; and figures

checking and agreement by the Department prior to acceptance of
any tender (cl. 1.7.5).

The tenderer was to supply a list detailing the location of all his Australian-based aircraft capable of complementing the tendered service. The tenderer was to be prepared to supply, if requested, details of his resources and capacity ', both flnancial

and physical, to set up and perform the service (cl. 1.7.6).

The Department

additional information to allow further consideration of his
tender (cl. 1.9).

could require the tenderer to submit
If the Department decided to accept the tender, notice
of acceptance was to be served on the successful tenderer, who
could be required to enter into a formal contract, but written
notice of acceptance of a tender would constitute a binding

contract, whether such formal contract was or was not executed
(cl. 1.10).

The tenders were to remaln valld for a perlod of 90 days

(cl. 1.14).

The "Conditions of Contract" (Sectlon 2 )

The

with the perlod of the contract, llquidated damages, default and
termination should be noticed.

provlsions contained in these conditions deallng

The period of the contract was defined

operation specified in the Notice of Acceptance". The Contractor
was to take over the sectors he was contracted for from the
existing contractor on a sector by sector basis "as soon as
possible after receipt of the Notice of Acceptance and expiry of
the existing contract". The expiry date of the Contract was to

by providing that
it would be "in force for the number of months of aircraft
be confirmed after the last aircraft was in operation and was to
be such date as would permit an average number of months

operation of specified in the Notice of Acceptance (cl. 2.4).

each

aircraft

equalling

the

number

of

months

The contractor

was to

lodge value...as security

"2%

of

the

stimated

total

annual

contract

for the due and proper performance and
completion of the contract" (cl. 2.5.1). This security was to be

refunded "after the Secretary has certified that the Contract has

been satisfactorily completed ..." (cl. 2.5.5).

Provision for liquidated damages was made as follows:

"If the Contractor proceeds with a flight with any of

the following items equipment of misslng or

unserviceable:

(a) specified radio equipment ...
(b) specifled tactical navigation system ...
(c) specified radar equlpment ...
(d) fully operational air condltlonlng system ...
(e) specified intercom equipment ...
(f) specified cameral equipment ...
(g) specified binoculars...
(h) radar altimeter...

(i)  any windows which, through opacity, do not allow clear external vision...

the Contractor shall be required to pay to the

Commonwealth, as liquidated damages and not as a penalty, an amount equal to the percentages of the daily standing charge for that aircraft, as shown above, for each item of missing or unserviceable

equipment. " ( cl. 2 . 2 2 )

Default was dealt with in these terms:

"If the Contractor fails to make a flight in the

manner required under the Contract and the Secretary is not satisfied that the failure was due to accident or other reasonable cause beyond the control of the Contractor the Contractor shall without pre~udice to

any other emedy pay the Commonwealth, or the
Commonwealth may, at its option, deduct from any
amount due or to become due to the Contractor any sum
payable by the Contractor as liquidated damages or
the amount that would have been paid had the

Contractor not been in default and any extra expense over the contract rate incurred by the Department in

having the Contractor's default made good." (cl.

2.23)

Termination was provided for as follows:

"whenever and so often as the Contractor fails to

carry out the Contract or comply with a condition of the Contract to the satisfaction of the Secretary then in either of these events the Secretary may, by notice in writing, require the Contractor to show cause in writing to the satisfaction of the Secretary, why the Contract or any specifled portion thereof should not be cancelled. If the Contractor fails to show cause in writing, as so required, the Secretary shall be entitled to treat the Contract or any specified portion thereof as having been

cancelled.. .'I (cl. 2 . 2 4 )

It was further provided that none of the conditions of

the contract were to be varied, waived, dlscharged, or released
either at law or in equity except by the express consent of the
Secretary (cl. 2 . 2 7 ) .
The "Speciflcation for Charter Aircraft Task" (Section 3)
The scope of the task was defined in this way:
"3.1.1 (a) The task required of the charter aircraft is

(1) Visual search of the Littoral Area in sectors nominated by the Department. The Littoral Area is a band from approximately one mile inland to three miles offshore from the mainland Australian coastline and around nominated offshore islands from approximately Karratha to Cairns

( 2 ) Visual search of the Ashmore and ad~acent Islands

(3) Visual search of other areas as required.

(b) The visual search will normally be carried out

between the times of one hour after the beginning of daylight and one hour before the end of daylight as defined by Department of Aviation.

3.1.2 The Contractor will operate his aircraft for the
sectors he is contracted for from the following
airfields:-
- Broome
- Darwin
- Gove
- Horn Island or Bamaga or Weipa
- Cairns
to provide the indicative coverage at Annexure l..."

"3.1.3

Other staging bases regularly used are Karratha, Port Hedland, Kununurra, Mitchell Plateau, Maningrida,

Milingimbi, Boroloola, Normanton, Weipa and Lockhart
River.
3.1.4 Annexure 1 shows a typical flight program for the
task. The Annexure is for guidance only and the
hours shown are not guaranteed to be flown in any one
week or over a period of time."

(Annexure 1 has already been set out)

Sub~ect to the following conditions, the minimum and maximum hours capacity of each base shall be as submitted with the Contractor's Tender (Schedule 3) and agreed to by the Department:

the agreed maximum and minimum hours shall be subject to reasonable adjustment for statutory and logistical limitations on provision of personnel.

if any change of a long term nature is made to the
frequency of operations which affects hours flown to
a level outside the minimum/maximum range agreed, the
Department or the Contractor may request adjustment
of the Daily Standing Charges to reflect any change
in the required numbers of pilots and observers.

short term variation from the level of operations indicated at Annexure 1 may involve additional expense to make personnel available if sufficient notice is not given for rostering. Any reasonable additional expense thus incurred will be reimbursed at cost by the Department.

the standard operating crew for the contract task
shall be one (1) pilot and two ( 2 ) observers.
The Contractor shall provide sufficient aircraft as

specified, aircrew, related administration and resources at each operating base that 1s contracted for to meet the following requirements:

fly any number of hours within the limits shown in the agreed Schedule 3 submitted with the Contractors

Tende r ;

fly no observer for more than five ( 5 ) hours on the visual surveillance task per day. Ferry or transit time is not included in this limitation. It would be

expected that no observer would fly for more than

seven ( 7 ) consecutive days;

operate at times to be nominated by the Department;

have the flexibility to operate on a variety of search tracks and vary the programmed tracks at short notice to meet operational requirements as notified by the Department; and

have the flexibility to operate, at short notice,
from any suitable operating base for a period of up

to one month. The details and costs of such operations to be negotiated as the situation arises."

As has been noted, the surveillance portlon of the task

was to be flown at not less than 140 knots IAS nor more than 160

knots IAS except when identifying sightlngs whereupon the speed
was to be varied as required. Normal operatlng altltudes were to
be between 500 to 2,500 feet except when identlfylng sightlngs
(cl. 3.1.8).

The aircraft were only to be used for the tasks as specified in the contract unless directed by the Department (cl. 3.1.9).

As we have seen, the littoral search was stated to be

primarily concerned with the detection, for quarantine purposes, of unauthorised landings; at the same time, reporting

requirements were said to be "not exclusive to prime tasks" and

surveillance crews were said to need to have "a broad understanding of all information requirements and...be able to

report sightings accurately and rapidly record elevant
information about sightlngs" (cl. 3.2.3).

Aircraft requirements were provided for as follows:

"3.3.1 The aircraft is to be a suitable multi engined
aircraft with the following equipment and

capabilities:

...

(b)

endurance of 5 hours on task at an operating level of 500 feet AGL within the 140-160 knot range IAS plus transit of one hour at normal cruise plus IFR reserves applicable to the entire flight carrying 5 people including the pilot;

...

(f) commercial lntercommunlcations system between all seating positlons In the aircraft..

(g) weather radar wlth ground mapping mode that can detect a 20 metre vessel at

20 nautical mlles in

sea state 3 ;

VLF/OMEGA or Inertial Tactical Navigation

System. . .

2 visual observation stations in the rear cabin which Incorporate comfortable, fully adlustable seating and optically clear bubble windows large

enough to allow an observer to place head and

[shoulder] in the bubble with an unrestricted view of the surface beneath the aircraft covering a semi-circle of 5 nautical mile radius with the base line along the flight path of the

aircraft. Stations to be located on either side
of the fuselage and to allow undistorted
photography clear of engine efflux to be taken
through the bubble or an appropriate opening
hatch;

I F R approved low level radar/radio altimeters;

ability to carry and drop small stores packages up to the size of 24cms X 24cms X 70cms and messages while airborne;

air-conditioning system to maintain the cabin to a maximum temperature of 27 degrees Celsius and 60% humidity on a 32 degree Celsius 70% humidity

day. . . "

Aircraft availability was dealt with in these terms:

"3.11.1 The Contractor shall provide sufficient
aircraft to undertake the task making
necessary allowance for scheduled
maintenance.
3.11.2 The Contractor shall provide aminimum

number of backup aircraft relative to the
number of contracted operating aircraft as

follows:

(a) one, two or three operating aircraft - one backup aircraft
(b)
four, five or six operating aircraft - two

backup aircraft

(c)

seven backup aircraft."

or

eight

operating

aircraft

- three

"Suitability of equipment" was dealt with as follows:

"3.15 At any time the Department may require the
Contractor to demonstrate, by flight rials if
necessary, under conditions and configuratlons
specified by the Department, that the contracted
aircraft can meet all the requirements of the

specification a d

environment for aerial surveillance operations to the
satisfaction of the Secretary."

provide andequate worklng

The Schedules (Section 4)

Section 4 of the contract documents comprised four
schedules in which tenderers were to state further details of

their tender on the subjects of "Rates" (Schedule l), "Component

Costs" (Schedule 21, "Capacity for Flylng Hours" (Schedule 3 ) and
"Technical Data" (Schedule 4). Mr. Amann completed Schedule 1 as

follows (his response is emphasised):

"4.1 - SCHEDULE 1 - SCHEDULE OF RATES
Rate For . Rate FOK
Five Year . Three Year
11=11==--1 . =11=11=*=1 Contract $ . Contract $
4.1.1 Standing charges
per day for each base 1,774.02 . 2005.55

(based on 7 days)

4.1.2 Flying charge per
hour for each aircraft 191.06 . 191.06
4.1.3 Rate to cover cost of
overnighting away from
specified operating
airfield per person per
night 130.00 . 130.00
4.1.4
Base(s) tendered for BROOME - DARWIN
GOVE - WEIPA
CAIRNS
NOTE - If dlfferlng prices apply for bases a separate
schedule should be submitted for each base."
In Schedule 2, Mr. Amann gave details of his component
costs. In his response (emphaslsed) to Schedule 3, as amended by

letter from the appllcant to the Department dated 12 January

1987, Mr. Amann said:

"4.3 SCHEDULE 3 - SCHEDULE OF CAPACITY FOR FLYING HOURS

AVAILABLE FROM EACH BASE (Refer clause 1.7.5)
Base Required Minimum Maximum Dlfference
- Hours HOU r S Hours between
Max & Req'd
Broome 3148 - 1574 - 3600 452
Darwin 2102 - 598 2700

1401       -

Gove 1216 584 - 1216 1800 -
(Bamaga 3266 - 1633 3600 334
Sector) -
Weipa
Cairns 1287 - 513 1287 800 -

...

In Schedule 4 (Technical Data), details of the aircraft proposed:

Mr. Amann gave these

"4.4.1 Details of Aircraft Proposed
Is equipment specified at clause 3.3 of
Specification for Charter Aircraft Task

fitted. If

specified please attach statement detalling
deficiencies and time required to fit such
equipment.

aircraft is not equipped as
Manufacturer Gulfstream American
Rockw ll Comander Type [sic]
Model 680 F & FL
Registration No VH T.B.A. [i.e., to be advised]

Seating Capacity
(including pilot) 8 - 10

...

4 . 4 . 3 of details State anticipated

arrangement/utrllsatlon on this contract of Aircraft provlding for normal routine overhaul/servlcing.

In house servicing after days flying

completed & backup aircraft as required ...

...

4 . 4 . 5 State d tails

of available to the Tenderer that may be

any other aircraft

used

to supplement those nominated above.

Beechcraft Queen Air B-6 5
Duke 8-80''
Nr. Amann dealt with the sultability of his equipment in

this way:

" 4 . 4 . 6 Equipment Suitability
Outline method to be adopted to prove
aircraft offered above meet specifications.
Submission of technical data

i.e. Flight manual and if required

test flight with Department"

He provided details of the commencement of operatlons as

follows:

"4.4.11 Commencement of Flying Operation under the
Contract
( a ) State time needed from date of letter
of acceptance to recruit sufficient pilots
and observers and supply personal details of
all staff associated wlth flying operations.
Two months required

(b) State time needed to make aircraft available for commencement of air patrol

from date of letter of acceptance:

6 months totaled (sic) (but 1s negotiable)

and aircraft availability will b e
progresslve.

...

8   4 3

The "Form of Tender"

The "Form of Tender", slgned R. & P. Amann Aircraft Hire and dated

by Mr. Amanm on behalf of

25 November 1986, was as

follows:

"Under

and state on the following pages, we R

subject theundersigned do hereby tender and offer to supply

to

the

Conditions

of

Tendering

& P A W N AIRCRAFT

HIRE.. .

the Commonwealth of Australia with the services

tendered for in the Schedules attached hereto, at the

prices tendered, and under and subject the o
Conditions of the attached Tender Schedule DOT 086
for
CHARTER OF AIRCRAFT FOR COASTAL SURVEILLANCE
SERVICES-LITTORAL AREA..."
The correspondence referred to in the letter of acceptance

By his covering letter dated the tender, Mr. Amann said that:

25 November 1986 submitting

...

2. We the equipment offered by

propose

to

demonstrate

the

suitabillty

of

way of a test flight

prove to c mpliance with tender

th documentations intent.

3. We have had numerous meetings with e

Department of Transport offices [sic] as to the requirements of the proposed task and confirm

that we will be able to comply fully.

...

At this time, the intent is to import the aircraft
from the U.S.A. and then place them on the Australian
register. Suitable aircraft have been sourced and
options placed for a period of ninety (90) days.
...
As has been seen, cl. 1.7.6(b) of the "Conditions of

Tender" required the tenderer, i f requested, to supply details of his resources and capacity to perform. On 8 December 1986, Mr. Richardson wrote to Mr. Amann seeking further details. By his

letter dated 11 December 1986 (bearing the wrong date of 11

November), Mr. Amann responded:

"CLAUSE 1.7.6(b)

1.    Aircraft for the task will be procured in the United States of America.

2.    The following modification will be required and performed in the U.S.A. prior to delivery:

a)

Fitment of bubble windows for observation stations.

b) Complete strip and repaint to specification
aircraft livery (Clause 3.16).

c) Fitment of Radar Altimeter.

d) Removal of existing Radar and reinstallation
of common Radar unit (Bendix 230HP).

(Note, applies to 3 aircraft only).

In addition, the following modifications will be

performed in Australia:

Installation of Marine Band VHF/FM Radio.
Installation of UHF/AM Military Band Radio.

Aircraft intercommunications system.

a piston

engined aircraft would represent about 33 per cent of the flying

charge, the turpoprop's fuel cost per hour would represent more
than 66 per cent of the flying Charge. Moreover, as has been

said, there may be different maintenance costs and this may also

have a costs would be and upon the respective proportions that each of

bearing upon an assessment of what the total component

those costs would bear to the whole.
It follows, in my view, that in order to lay down a
formula for adjustment of the flying charge by reference to
changes in "cost components" in the case of the turboprops, it
was necessary for the parties to revise their existing formula in
a number of substantlve respects. No doubt the prlce of Avtur at
the relevant date was a factor to be taken into account. But it
could not have been the only factor. Once it was accepted, as

the parties did accept, that the introductlon of the turboprop was not to involve any additional cost to the Commonwealth, the terms of reference for the worklng of the rise and fall provision had to be reformulated. It was no longer posslble to accept that fuel cost represented only one-third of the flying charge. A number of fresh calculatlons were required in order to prescrlbe

a formula which would provide for rise and fall in the "cost

component" of the new aircraft, but always on the footing that the result would not cost the Commonwealth any more than the cost would have been if the whole fleet had consisted of turboprops, assuming always, of course, that it were possible to prescribe such a formula.

In my opinion, these details were essential to the

making of any agreement providing for rise and fall in thls area. In the absence of agreement on these crucial matters, there was

no operative rise and fall provision in place in the case of the
turboprops. The existing provlsion would apply to he
piston engined aircraft but this is a different matter.

In my opinion, the provisions of cl. 2.7 as a whole,

including cl. 2 . 7 . 9 , applied to each "Cost Component" as defined
in the contract and as stated in the Notice of Acceptance. In
other words, the rise and fall provision did not apply to any

other costs or expenditure incurred by the appllcant.

In the result, in my view, the contract did not require
any alteration to the amount payable to the applicant by
reference to any change in the price of Avtur after 1 July 1988.
It follows that no alteration should be made to the figure of
$17,107,462 (being the income agreed to be receivable under the

contract) by reason of the removal of the excise on Avtur.

what would have been the applicant's fuel costs?

There remains the different question of the estimated

expenditure which would have been incurred by the applicant in acquiring fuel over the period of the contract. Apart from the rise and fall question discussed above, the parties are agreed

that the sum of $2,825,420.00 should be allowed on this account.

APPENDIX 5

"Interest" or other cost of serviclng the borrowing necessary

to fund the acquisition of the aircraft

As expenditure, the applicant incurred a

has been stated, as part of its pre-operational

liability to CVC in the sum

of $202,311.00 for "interest". This liability arose out of an
arrangement between those parties which was recorded in a mlnute of

a meeting of the directors of CVC on 12 April as follows:

"CVC INVESTMENTS It was agreed that CVC Investments Pty
TRUST & AMANN Limited would act as Trustee of moneys
AVIATION PTY provided by Wenola Pty Limited and, if

LIMITED: 

necessary, from Southsea Investments Pty Limited which companies were providing the loan funds to enable the purchase of aircraft rn the name of CVC Investments

Pty Llmlted.  These aircraft would be
hired  to Amann Aviation so that an
interest rate of 20% was derived by the
Trust as bridglng finance until the
Commonwealth Bank took over the debt on
the safe arrival of the alrcraft in
Australia and the finance contract with
the Commonwealth being available.

IT WAS NOTED that the Trust would also act for Continental Venture Capital Limited in relation to the one aircraft purchased by Melbourne Australia Investments Limited until all finance issues between the parties were finalised."

The background to Commonwealth Bank finance, is that Mr.

the reference, in the minute, to

Shlegeris had sought from

the Bank "lease finance" for the acquisition of aircraft. On 10
April, the Bank had written to Continental Venture Capital Ltd., a
company associated with CVC, confirming approval of "progressive

lease financing of $3.5m to [the applicant] to assist acquire

sixteen aircraft..." Conditions of approval included the
"provision of freehold/cash security to the value of $l.Om" and a

"guarantee limited to $500,000 from Continental Venture Capital." Continental Venture Capltal was also to undertake to "inlect up-front non-interest equity capital of $650,000 in [the appllcantl;" to "financlally support [the applicant] if necessary to ensure lease rentals...are met on thelr respective due dates;"

and "to provide an additlonal guarantee of $250,000 ... lf [the
applicant] fails to achleve the cash flow pro]ections." The lease

proposed was for 41 months with a residual value of $1,500,000.00

Interest was stated to be at the rate of 17.33 per cent.
It appears that some of the conditions of this proposal were not acceptable to the applicant. In the result, the leaslng

transaction was not proceeded with. The applicant claims that, at this tune and later, it experienced difficulties in obtaining lease or other finance because of comments by Skywest reported in the

media suggesting that the applicant's inexperience in the area

indicated that the applicant would not be able to perform the

coastwatch service adequately. I accept that some publlcity to

this effect occurred. The evidence does not indicate what effect

the publicity had on financing generally. We do not know, for

instance, what impact, if any, the publicity had upon the

Commonwealth Bank. But, in any event, it was decided not to take
up the Bank's proposal. Instead, CVC chose to finance the purchase
and modification of the aircraft by bank bills. These bank bills,

which provided temporary accommodation only, and thus needed to be
rolled over periodically, were discounted at rates of between 11.5

and 14 per cent per annum.

Accounts of the applicant and the CVC Investment Trust

drawn up as at 19 September, reflected their dealings as follows:

"AMAtW AVIATION PTY. LIMITED

Notes I
AUthoKlSed Cap i t a l 2
Excess of Assets over L i a b i l i t i e s
The accompanying notes form
P a r t of these accounts.
Amann Aviatim Pty. Limited
unconditionally has guaranteed CVC
Investments Pty. Ltd. a g a i n s t a l l

costs of its opera t ion and any

loss r e s u l t i n g from the provid ing

of planes and equipment to Amann

Aviaticn Pty. Limited. "
T r u s t C a p i t a l
S e t t l e d Sum
Total T r u s t C a p i t a l

Represented by:

Flxed Assets

Planes h Equipment

C u r r e n t Assets
Cash on Hand
S .oo
The Aocompanying Notes form

p a r t of these Accounts "

On behalf of the applicant, it 1s argued that, for the purpose of estimatlng the cost to the

applicant of performing the

contract, it should be inferred that the applicant could have
obtained finance (to buy the aircraft from Cvc) at a cost of
approximately 14 per cent per annum. It 1 s sald that the flnance
could have been found in the form of 90 or 180 day bank bllls

discounted at about 14 per cent per annum.

There are difficulties in accepting thls. The appllcant had only limited assets and significant liabllities. Its

capacity to borrow an amount in excess of flve million dollars must have depended upon its association with CVC, which held half

of its share capital. If CVC were prepared to secure and to

guarantee the applicant's liability under the transaction, it 1s

possible that this finance could have been obtained.

But this is not any such arrangement would be less than

to say that the interest payable under

2 0 per cent, being the

amount charged by CVC in its transaction with the applicant. On the contrary, the evidence indicates that lease finance would have cost approximately as much, and possibly more, than CVC was

Bank's rate of interest exceeded 17 per cent per annum. In charging. In its offer made in April 1987, the Commonwealth
addition, the lessee would have a contingent liability,
admittedly difficult to estimate, m respect of the residual
value of the aircraft. There was evldence that the Bank's rate
of interest charged on a lease arrangement would be 16.75 per
cent per annum. Again, it would be necessary to allow for the
residual liability. There was no suggestion that the interest

rates quoted by the Bank exceeded the market rates. It seems unlikely, therefore, that the applicant could have obtalned lease

finance at an overall cost (including an allowance for residual
liability) less than the 20 per cent per annum "interest" belng
charged by CVC.
On behalf of the applicant, it is submitted that,

because the cost of leasing finance would have exceeded what it cost CVC to finance the purchase of the aircraft by using bank bills at a discounted rate of about 14 per cent per annum, it should be assumed that the applicant would also have used bill

finance at about 14 per cent per annum to fund the establishment

of its operation.

It is difficult to make this assumption. For one thing,

CVC was in a much stronger financial position than the applicant. It appears that, as at 12 September, the applicant had lost most, if not all, of its share capital. As at 19 September, the balance sheet of the applicant indicated that it was,

technically, insolvent. Its only substantial asset was the

coastwatch contract and the profit margin under that contract was relatively small. From the minute of the meeting held on 12 April quoted above, it appears that there was an understanding between the applicant and CVC that the applicant would take over the aircraft from CVC once the Commonwealth Bank finance had been

arranged. From the note at the foot of the applicant's balance

sheet as at 19 September (see above), it seems that the applicant had also agreed to indemnify CVC against any loss In connectlon with the coastwatch contract. Since the applicant had no current assets and was, technically, insolvent, the applicant could only

use the bank bills as a means of finance if CVC or another party
were prepared to guarantee the applicant's liability under the
bills. It would be reasonable to expect that, in order to Induce
it to offer that guarantee, CVC would require security from the

applicant. Apart from the aircraft, the applicant could offer no significant security. Aircraft could provide only limited security for such a substantial borrowing. The evidence was that the aircraft could not be readily saleable if they had to be

realised as security. In these circumstances, it is likely that
if CVC were to guarantee the applicant's liability under a bill
line in such a large amount, CVC would require to be
appropriately compensated for the risk it was assuming.

I accept that the applicant and CVC originally intended that their arrangement, as recorded in the 12 April minute, was

intended to be for "bridging" finance only. But it seems likely

that, if the coastwatch contract had remained on foot, this
temporary arrangement would have remained in place for the

duration of the contract for neither the applicant nor CVC had
any real choice about the matter.

From CVC's point of vlew, the "interest" of 2 0 per was apparently an acceptable rate. It was above the current bill

cent

rate, although that rate mlght, of course, increase over a

period. True, CVC would in the value of the aircraft over the period

also have run the risk of

depreciation

of the contract.

However, the applicant was obliged to maintain Its fleet properly in order to perform the coastwatch contract. As has been said, it is now agreed that approximately $4,000,000.00 would have been spent for this purpose. Further, the rlsk of signiflcant depreciation had to be assessed against the background of the possibillty of renewal of the coastwatch contract or of another, similar, contract becoming available in this country or elsewhere. Even if the appllcant did not win any new contract, the successful tenderer might have been Interested in acquiring

the appllcant's fleet. Moreover, the relatively high interest

rate of 20 per cent per annum would provide some measure of

compensation if substantial depreciation did occur.

From the applicant's analysis, there appeared to be only two possible sources of

point of view, on a realistic

finance: (1) lease finance from an institutional lender which would cost, effectively, about 20 per cent per annum (i.e. an "interest" rate of about 17 per cent per annum plus an allowance

liability, which liability would have to be guaranteed, presumably for some consideration, by CVC); ( 2 ) accommodation provided by CVC In return for a hiring fee or "interest" at the rate of 20 per cent per annum. This was the arrangement in fact in place on 12 September.

for esidual

The cost to the appllcant of each of these avenues of

finance would have been approximately the same, i . e . 20 per cent
per annum. Because the CVC arrangement was already in place, lt
is likely that It would have continued during the entire period
of the contract. There was no cost advantage to the applicant In
approaching an institutional lender. An institutional lender,

if Introduced, would probably look to CVC not only to make over

title to the aircraft, but also to provide a guarantee and possibly also security to secure the appllcant’s total liabillty under a leasing transactlon. This would be an obvious disincentive for CVC to change its existing arrangement with the applicant. In these circumstances, I think that it is probable

that this arrangement would have remained in place for the term
of the coastwatch contract.

In my opinion, if the contract had run its full term, it is probable that CVC would have retained ownership of the

aircraft, but would have hired them to the applicant In return

for a hiring fee of 2 0 per cent per annum, that is, the sum of $3,390,000.00 being 20 per cent per annum on $5,650,000.00 over

three years.

APPENDIX 6

The applicant's other claims for damages

"Reliance" loss

The applicant claims that, as a result of the breach of the contract by the Commonwealth, expenditure of $5,112,012.00 was thrown away in preparation for performance of the contract.

The applicant says that this amount was expended in reliance upon

the Commonwealth's promise to perform its obligations under the

contract and that the applicant should be compensated

accordingly.

The major item of expenditure was the acquisition of the aircraft ($5,650,000.00).

cost

of

There was evidence

that if the aircraft had to be sold now there would be realised
approximately $1,424,229.00, from which selling expenses would

have to be deducted.

The applicant presses this claim in the alternative.

Its primary claim is that it is entltled to compensation for loss

of the profits it would have earned, together wlth damages for

the non-recoverable expenditure incurred in preparing for the

contract. The applicant's secondary claim is for "reliance"
damages only, as distinct from "expectation" damages.

In support of its primary claim for damages for loss of profits and also for compensation for expense thrown away, the applicant refers to observations made by L.L. Fuller and W.R. Perdue, Jr. in "The Reliance Interest in Contract Damages" (1936)

46 Yale Law Journal 52 (at pp. 73-4) as follows:

"In distrnguishing between the reliance and the
expectation interests we encounter not so much a
shifting line of divlsion as a miscellaneous group of
cases which seem equally happy in either category.
These two interests will furnish identlcal, or nearly
identical, measures of recovery in at least three kinds
of cases.

First, where the plaintiff's reliance takes the form of =essential to the enforcement of the contract by him (such as partial performance of the contract or necessary preparations to perform) and the defendant breaks or repudiates the contract before complete performance has taken place, it is possible to classify the plaintiff's suit as resting either on the

expectation interest alone, or on a combination of the

expectation and reliance interests. If a building contractor has finished half the structure when the property owner puts an end to the contract the contractor's declaration may list two items of damage: (1) expenditures actually made in performing or preparing to perform, and ( 2 ) the profit which he would have made on the whole contract. This looks like a combination of the reliance and the expectation interests, and it will necessarily be so analyzed if we restrict the scope of the expectation interest to what

may be called the net expectancy, in other words, if we make "the expectation interest" and "the lost profit" synonymous. But in cases where the plaintiff has undertaken performance or preparations to perform a profitable contract before the defendant's breach it

involves no distortion to

say that the plaintiff's

expectancy is really twofold and includes (1)

reimbursement for what has been done, and ( 2 ) a profit in addition. This broader expectancy we may call the

ross expectation interest. Using this broader concept

?he contractor's suit in the case supposed will appear
to be founded entirely on the expectation interest..."

In addressing the question whether the "expectation interest" should set the limit of recovery, Fuller and Perdue conclude (at p.76):

l ' . . .a limitation on recovery in terms of the "net
expectation interest" would be absurd. That a building

contractor stood to make only $200 on his contract as a whole should not prevent him from recovering, let us say, $5,000 as reimbursement for expenditures made before the defendant's breach."

There are difficulties in applying this reasoning here. In the first place, the major item of expenditure in the

project

was the cost of acquisition of the aircraft ($5,650,000.00).
This expense was met by CVC and not by the applicant. cvc
retained title to the aircraft and hired them to the applicant

for a fee or "interest" of 20 per cent per annum. CVC was not a party to the coastwatch contract and cannot, and does not, sue for its breach. But it is submitted on behalf of the applicant that, for the purpose of assessing damages here, the "corporate veil" should be pierced with the result that the applicant and CVC are to be treated as if they were one and the same corporate entity.

In my opinion, it is not

separate corporate identities of the applicant and CVC. It 1s
true that CVC held one-half of the applicant's share capital but,
for all purposes, they were distinct. Their separate
personalities were reflected in the terms of the hiring
arrangement negotiated between them. It is not, and could not
be, suggested that the hirlng fee was a "sham" or not otherwise

permissible to ignore the
intended to create a legal liabillty. In the absence of any

suggestion of a sham or a "facade", and none 1s made here, it 1s not possible to plerce the corporate vel1 and look through the applicant to CVC in the manner suggested by the applicant (see Sharrment Pty. Ltd. v. The Offlcial Trustee in Bankruptcy, Full Federal Court, 3 June 1988, unreported; - Dalco v. Federal Commissioner of Taxation 88 A.T.C. 4,649 at p. 4,652; National Dock Labour Board v. - Pinn, Macpherson J., unreported, "The Times", 17 November 1988; cf., in assessing damages in tort, Attorney-General v. Geothermal Produce N.Z. Ltd. [l9871 2

N.Z.L.R. 3 4 8 ) .

The appropriate measure of by applying the principles in Hadley v. Baxendale.

damages is to be

determlned

The

assessment of the applicant's loss is to be determlned by making
a calculation of the kind indicated in T.C. Industrial Plant v.
Robert's Queensland, supra. In that calculation, In estimating
profits lost, there is picked up, as a component, expenditure

incurred or anticipated to be incurred, by the applicant in

performing the contract. The present case is unlike, and may be
distinguished from cases such as - McRae v. Commonwealth Disposals
Commission (1951) 8 4 C.L.R. 377 at p.414 and C.C.C. Films
(London) Ltd, v. Impact Quadrant Films Ltd. 119851 1 Q.B. 16 at
p . 3 8 where It was impossible to assess whether there would have

been returns sufficient to recoup the expenditure laid out.

In my opinion, the applicant 1s not entitled to "reliance" damages on either of the claims it now makes.

The claim for loss of goodwill

The applicant claims substantial damages for, in effect, alleged depreciation in the "corporate value" of the applicant as the result of the unlawful termination of the coastwatch contract.

The applicant relies upon evidence called by Hr. J.W.

Bracher, a chartered accountant. Hr. Bracher calculated the

applicant's damages by adding together the following:

(a) The expected net return to the applicant for duration of the coastwatch contract less the expected

the

net return from activities after the termination of the
contract;
(b) additional costs incurred by the applicant as a result
of the termination of the contract;
(c) the loss in corporate value of the applicant resulting from the termination of the contract.

The claim is made up as follows:

...

profit from operating entire

Coastwatch contract 0,201,757

LESS: 3-year profit without

Coastwatch... 0

reduction in return to Amann

resulting te mination from 0,201,757

ADD: additional costs incurred

as a result termination... of 661,000
- - - - - - - - -

total revenue loss resulting from

0,942,751

termination ADD: loss in company value

contract

resulting from termination:

annual net pre-tax

2,154,000 1990: profit,
income tax, 1990: 1, 74,094

annual after-tax profit 1,679,994

capitalisation rate... 15.00%
net loss of capitalised
company value: 11,199,950

LESS: value of company

contrac :  without 0

--_-_-----

11,199,958

TOTAL ESTIMATED LOSS $20,142,715"
The claim assumes that if the applicant had been

permitted to earned a reputation or goodwill which had a substantial value

perform

the

coastwatch

contract,

it would

have

in

its own right.

The claim must fail. I have already held, in accordance
with the principles in Hadley v. Baxendale, that the measure of
the applicant's damages is to be computed in a way similar to
that indicated in T.C. Industrial Plant v. Robert's Queensland,

supra. On that approach, rt is not open to the applicant to make an additional claim for loss of goodwill or depreciation in Its corporate value (cf. Re Golomb [l9311 144 L.T. 583).

The claim for loss of the prospect of other contracts

The applicant further claims damages for loss of future

income from other contracts. The first claim is in respect of the chance of renewal of the coastwatch contract itself. This

is, in substance, a c l a m for damages for loss of a chance (see
Chaplin v. - Hicks [l9111 2 K.B. 786).

It may be accepted that such a claim could be maintained if an economic value could be placed

on the chance (see B. Coote,

"Chance and the Burden of Proof in Contract and Tort" (1988) 62

A.L.J. 761 at pp. 767-8). It may also be accepted that it was

probable that the Commonwealth would again seek public tenders for the coastwatch contract in 1990. On behalf of the

Commonwealth, it is submitted that the applicant's prospects of obtaining a renewal of the contract were minimal only, given its significant delay in starting up operations properly in September 1987. There is considerable force in the submission. But, in any event, it is impossible to estimate the profit margin, if there was any, under such a contract. In these circumstances, this claim must also fail.

The applicant further claims damages for loss of the chance to obtain the Commonwealth's contract for the surveillance of the Great Barrier Reef (Sector 50). Again, the applicant's

delay in commencing patrols in accordance with the terms of the coastwatch contract would, I think, be taken into account by the Commonwealth unfavourably to the applicant in deciding whether or

not to award this additional contract to the applicant.

Again, it is impossible to estimate what margin of profit, if any, would have accrued under this contract if it had been obtained by the applicant. Mr. Gould gave evidence that the

infrastructure established by the applicant to perform the coastwatch contract would also have been able to service the Great Barrier Reef surveillance without any additional expense. It is difficult to accept that this could be so. For one thing,

the applicant's fleet was not in place as required by the
coastwatch contract on 12 September and it would have taken a
considerable time before the fleet was ready to perform in

accordance with the contractual specification. In that period at least, there was no surplus capacity available to service another contract. Moreover, the Great Barrier Reef surveillance is now carried out using "dedicated" aircraft based at Townsville but

"over-nighting" at bases along the Queensland coast. The
applicant had no base at Townsville. There was also evidence

is likely that the next Great Barrier Reef surveillance

operating from Cairns, Townsville and Rockhampton under one, two
or three contracts.

contract will operate differently, with several ircraft
that i t

In all these circumstances, the claim must be re~ected.

I certify that this and the preceding

pages are a true copy of the Reasons for
Judgment hereln of hls Honour Mr. Justlce

Beaumont.

Assoclate

Dated:  21 December 1988
Counsel and Solicitors L.C. Gruzman Q.C., D.A. Cowdroy
for Applicant:  and A.M. Gruzman instructed by
Owen Hodge and Son.
Counsel and Solicltors  D.E. Grieve Q.C., S.D. Robb,
for Respondent:  P.A. Sharp and C.P. Comans
instructed Australian by

Government Solicitor.

Dates of hearing:

Date Judgment Delivered: 21 December 1988
Actions
Download as PDF Download as Word Document


Cases Citing This Decision

0

Cases Cited

0

Statutory Material Cited

0