Alstom Power Ltd v Yokogawa Australia Pty Ltd (No 6)

Link copied
Case Copied 15 min read

SUPREME COURT OF SOUTH AUSTRALIA

(Civil)

ALSTOM POWER LTD v YOKOGAWA AUSTRALIA PTY LTD & ANOR (No 6)

[2011] SASC 71

Reasons for Ruling of The Honourable Justice Bleby

2 May 2011

EVIDENCE - ADMISSIBILITY AND RELEVANCY - FACTS RELEVANT TO FACTS IN ISSUE

PROCEDURE - SUPREME COURT PROCEDURE - SOUTH AUSTRALIA - PROCEDURE UNDER RULES OF COURT - PLEADINGS - GENERALLY

PROCEDURE - SUPREME COURT PROCEDURE - SOUTH AUSTRALIA - PROCEDURE UNDER RULES OF COURT - PLEADINGS - DEFENCES AND COUNTERCLAIM

Objection to question asked in cross-examination of defendant's witness – question related to whether defendants acted pursuant to the terms of the contract between the parties – objection raised on the grounds that the question does not arise on the pleadings – defendants in their counterclaim pleaded contractor-directed changes were not valued by the plaintiff in accordance with the contract – plaintiff pleaded compliance with the terms of the contract – question directed at a clause of the contract requiring notice to be provided by the defendant – whether that clause constituted a condition precedent as contemplated by r 46.07 – question fairly arises on the pleadings – objection overruled.

Supreme Court Rules 1987 r 46.07, r 46A.05, r 46A.06, referred to.
H Stanke & Sons Pty Ltd v O'Meara (2007) 98 SASR 450, applied.
Antique House Pty Ltd v Security and General Insurance Co Ltd (1984) 3 ANZ Ins Cas 60-556, distinguished.

ALSTOM POWER LTD v YOKOGAWA AUSTRALIA PTY LTD & ANOR (No 6)
[2011] SASC 71

Civil:       Ruling on Evidence

BLEBY J.

Background

  1. The plaintiff, Alstom Power Limited (“Alstom”), was a contractor to a partnership known as Flinders Power Partnership (“FPP”) which owned the Playford B coal-fired power station at Port Augusta. The contract (“the head contract”) related to the refurbishment of the power station and its conversion to a fully automated electric power generator. The defendants Yokogawa Australia Pty Ltd and Downer Engineering Power Pty Ltd were the members of a joint venture (“YDRML”) who entered into a subcontract with Alstom to perform the electrical, control and instrumentation (“EC&I”) works associated with the refurbishment.

  2. The EC&I subcontract adopted the provisions of the head contract with certain variations contained in a set of special conditions constituting the EC&I subcontract.

  3. There are many items of dispute arising under the EC&I subcontract. One of them is a claim brought by way of counterclaim by YDRML for work done under the EC&I subcontract by way of variation to the subcontract, or what the subcontract describes as “Contractor-directed Changes”.

  4. Before describing the circumstances in which the immediate issue arises, it is necessary to set out some of the relevant provisions of the head contract as varied by the EC&I subcontract. Alstom is described in the EC&I subcontract as “Contractor” and YDRML is described as “Subcontractor”.

  5. Article 4.2 of the subcontract is headed “Contract Changes”. Article 4.2.1 provides:

    4.2.1     No adjustment to Contract Price

    Subcontractor shall not be entitled to any increase in the Contract Price for any reason other…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Alstom Power Ltd v Yokogawa Australia Pty Ltd (No 6) and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2011] SASC 71
Decision Date

CaseChat Overview and Summary

The case of Alstom Power Ltd v Yokogawa Australia Pty Ltd (No 6) involved a dispute between the parties regarding the valuation of changes to a project under a contract. The case was heard in the Supreme Court of South Australia, and the primary issue was the admissibility of a question posed during cross-examination of a witness for the defendant. The question related to whether the defendants had acted in accordance with the terms of the contract, and the objection was raised on the grounds that the question did not arise from the pleadings. The defendants had pleaded in their counterclaim that the contractor-directed changes were not valued by the plaintiff in accordance with the contract, while the plaintiff had pleaded compliance with the terms of the contract. The court had to determine whether the question fairly arose from the pleadings and, if so, whether it was admissible.
The court found that the question did indeed arise from the pleadings, as it was directed at a clause of the contract that required notice to be provided by the defendant. The court considered that this clause constituted a condition precedent as contemplated by rule 46.07 of the Supreme Court Rules. The court overruled the objection, holding that the question was relevant to the facts in issue and was therefore admissible. The court held that the question was directed to the fact that the alleged Contractor-directed Changes set out in annexure B1 were not Contractor-directed Changes at all, and in respect of which Alstom says there was also compliance with the contract because there was no obligation on Alstom in the circumstances to fix a value.

The final orders of the court were not specified in the text, but it can be inferred that the court allowed the question to be asked during cross-examination, and the trial proceeded accordingly. The case highlights the importance of ensuring that questions asked during cross-examination are relevant to the facts in issue and arise from the pleadings. The court's decision in this case provides guidance to practitioners on the admissibility of questions in cross-examination and the importance of pleading issues with specificity to avoid objections during trial.

Orders

Orders of the court

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

BLEBY J

Ratio Decidendi

Legal Principle Established

Established by: BLEBY J

YDRML argues that the first part of article 4.2.2(i) of the subcontract which provides that the Subcontractor must notify the Contractor if it considers that an instruction is a Contractor-directed Change falls within the category of a condition precedent to any entitlement by YDRML to payment, and that if Alstom is to rely on that part of the article in the way in which the question suggests, then Alstom ought to have pleaded YDRML’s failure to notify Alstom that the instructions concerned involved to a Contractor-directed Change.Consideration of the argument I do not accept the premise on which YDRML’s argument is based. Paragraph 243 of the counterclaim does not plead that the changes referred to in that paragraph were changes the subject of article 4.2.2(i). Paragraph 243 pleads only that at various times Alstom directed Contractor-directed Changes. By definition in the EC&I contract that means changes to the EC&I works instructed by the contractor “pursuant to a change order issued in accordance with Article 4.2”.[2] The issuing of a Change Order in respect of any Contractor-directed Change is a condition precedent to the existence of Contractor-directed Change. As such, it was not necessary to be pleaded in para 243 of the counterclaim.[3] The remainder of para 243 pleads that Alstom, in its capacity as superintendent, failed or refused to value the Contractor-directed Changes as required by the EC&I subcontract.[2] Definition of “Contractor-directed Changes”. See para 4 above.[3] 1987 Rules, r 46.07. By its defence Alstom merely pleads that in respect of those Contractor-directed changes pleaded, Alstom complied with the EC&I contract. It was not for Alstom to raise in is plea the failure of YDRML to give notice under article 4.2.2(i) of the contract. The assumption behind the plea in para 243 of the counterclaim is that all the changes referred to were Contractor-directed Changes as defined, and not instructions which YDRML considered ought to have been the subject of a Change Order. If YDRML were to claim the value of work carried out by what it alleged was a Contractor-directed Change not the subject of a Change Order, it was for YDRML to allege that certain instructions were given, that YDRML considered such instructions involved a Contractor-directed Change not contained in a Change Order, and that it notified Alstom accordingly before implementing the instruction. Other pleas would then have to follow if it claimed the value of the work then performed, namely either that it became the subject of a Contractor-directed Change as defined or that Alstom was in breach of its contract by not issuing a Change Order. Those are different questions with which I am not presently concerned. What Alstom did do was to allege, as YDRML concedes, that in respect of those Contractor-directed Changes pleaded in para 243 of the counterclaim it complied with the contract. The question objected to would appear to be directed to the fact that the alleged Contractor-directed Changes set out in annexure B1 were not Contractor-directed Changes at all, and in respect of which Alstom says there was also compliance with the contract because there was no obligation on Alstom in the circumstances to fix a value.