Alphington Developments Pty Ltd v Amcor Pty Ltd (No 5)

Case

[2023] VSC 637

1 November 2023


IN THE SUPREME COURT OF VICTORIA Not Restricted

AT MELBOURNE

COMMERCIAL COURT

COMMERCIAL LIST

S ECI 2017 00145

ALPHINGTON DEVELOPMENTS PTY LTD (ACN 164 529 864) Plaintiff/Defendant by Counterclaim
AMCOR PTY LTD (ACN 000 017 372) Defendant/Plaintiff by Counterclaim

---

JUDGE:

Sloss J

WHERE HELD:

Melbourne

DATE OF HEARING:

2-5, 12, 16-19 March 2020 (Trial adjourned at parties’ request due to COVID-19 lockdown);

(2021 Trial resumed) 2-4, 8-11, 15-17, 22-25 February, 1‑4, 9‑12, 15, 16 March, 12-15 April, 17, 18 May, 27 July 2021

DATE OF JUDGMENT:

1 November 2023

CASE MAY BE CITED AS:

Alphington Developments Pty Ltd v Amcor Pty Ltd (No 5)

MEDIUM NEUTRAL CITATION:

[2023] VSC 637

---

CONTRACT — Construction and interpretation — Notices — Contract provided for purchaser to recover costs from vendor for certain works undertaken at the land following issuance of a ‘UC’ notice addressing specified criteria — Valid ‘UC’ notice was a precursor to recovery of costs — Whether ‘UC’ notices issued were valid — Whether ‘UC’ notices satisfied criteria required to be addressed under the contract — Consideration of commercial purpose of ‘UC’ notices under the contract.

CONTRACT — Construction and interpretation — Contract provided for expert dispute resolution procedure in relation to objections to ‘UC’ notices — Parties subsequently amended contract by deleting dispute resolution procedure and requiring that the Court resolve questions relating to ‘UC’ notices in place of an expert — Role of the Court in resolving issues in respect of relevant ‘UC’ notices.

CONTRACT — Construction and interpretation — Breach of contract — Payment claims — Loss and damage — Alleged failure to pay costs properly and reasonably incurred in performance of works under contract — Entitlement to payment of outstanding claims — Contract embodied procedure for certification of invoices by approved quantity surveyor appointed by the parties — Whether items sought to be recovered as ‘Remediation Works’ ought to have been classified as other works — Whether plaintiff failed to prove amounts claimed were costs for ‘Remediation Works’ — Whether certifications by approved quantity surveyor conformed with contractual requirements.

CONTRACT — Breach of contract — Performance of contract — Compliance with contractual obligations — Whether plaintiff failed to use reasonable endeavours to minimise costs — Reasonable endeavours — Properly and reasonably incurred— Whether plaintiff procured works to be carried out cost effectively and to a reasonable commercial standard — Whether plaintiff disentitled from recovering its costs — Whether plaintiff’s approach to remediation was ad hoc and reactive — Whether plaintiff failed to devise comprehensive remediation strategy — Whether necessary to excavate all soil containing asbestos to remediate risks to human health and the environment — Whether capping solution should have been implemented — Whether plaintiff failed to competitively tender for works to be performed— Whether plaintiff failed to properly manage stockpiles — Whether plaintiff was required to consider any, and if so what, changes to the Master Plan.

CONTRACT — Failure of contractual mechanism — Contract provided for purchaser to recover costs from vendor for undertaking certain works following certification of works by approved quantity surveyor — Precondition to recovery of costs for works was that the purchaser had issued a ‘UC’ notice to the vendor addressing specified criteria prior to undertaking relevant works — Parties subsequently amended contract by deleting dispute resolution procedure and requiring that the Court resolve questions relating to ‘UC’ notices in place of an expert — Whether contractual mechanism for the recovery of costs failed thereby requiring the Court to create a substitute mechanism to allow the purchaser to recover costs — Whether certification by the approved quantity surveyor was an essential and indispensable part of contractual bargain.

CONTRACT — Implied terms — Implied duty of co‑operation — Implied duty of good faith and fair dealing — Alleged pursuit of self‑interest in breach of implied terms — Whether alleged implied terms can stand alongside the express terms in the contract — Whether breach of implied terms created liability for payment outside of contractual process for payment.

CONTRACT — Quantum meruit — Restitution — Unjust enrichment — Contract created a process for purchaser to recover costs from vendor for certain works undertaken at the land — Whether the amendment of the contract entailed the failure of the contractual process — Whether the purchaser failed to follow the contractual process — Whether restitutionary claim would subvert the allocation of risk under the contract.

CONTRACT — Construction — Whether plaintiff entitled to costs of remediating unidentified contamination in Riparian Zone — Where Riparian Zone was encompassed within Master Plan but no ‘use’ was specified.

CONTRACT — Separate contract — Scope of ‘Demolition Works’ limited by reference to the Delta Contract — Remediation of soil underneath demolished building — Whether plaintiff entitled to recover costs of works to demolish structures not identified for demolition in Delta Contract — Whether ‘Unidentified Contamination’ excludes unidentified contamination discovered during the course of procuring additional demolition works outside of Delta Contract — Whether defendant must pay costs of remediating unidentified contamination beneath structure not expected to be demolished.

CONTRACT — Counterclaim — Interest — Contract interpretation — Purchaser’s default in payment of money — Agreement to defer payment of penalty interest — Whether a valid demand was made — Whether debt was due and payable — Whether penalty interest under agreement should be calculated on a simple or compounding basis — Alternatively, interest pursuant to statute — Supreme Court Act 1986 (Vic) s 58.

EVIDENCE — Failure to call witnesses — Failure to produce documents — Inferences — Jones v Dunkel (1959) 101 CLR 298.

EXPERT EVIDENCE — Court appointed expert — Civil Procedure Act 2010 (Vic) s 65M.

---

APPEARANCES:

Counsel Solicitors
For the Plaintiff Mr M S Osborne QC (2020 only)
Mr D V Aghion
Mr A P Downie
Ms G M Douglas
Mr N O J Cozens
Mr C J Hender (2021 only)
Kalus Kenny Intelex Lawyers
For the Defendant Mr A A Monichino QC
Ms K A O’Gorman
Ms F Hudgson

Gilbert + Tobin

(prior to 21 December 2022)

King & Wood Mallesons

(from 21 December 2022)

TABLE OF CONTENTS

Introduction........................................................................................................................................ 1

Background to the proceeding.................................................................................................... 1

Summary of the rival claims in the proceeding...................................................................... 10

Glenvill’s cascading claims seek to recover approximately $31 million from Amcor 10

The gist of Amcor’s Defence and Counterclaim........................................................... 18

Summary of conclusions................................................................................................................ 25

The UC Notices given by Glenvill did not satisfy SC 11.5(a) and were not valid............. 26

Glenvill engaged GHD as its environmental consultant and later procured GHD’s appointment as ‘Environmental Consultant’ under the APM Contract....... 26

First discovery of asbestos at the Alphington site........................................................ 28

GHD was not provided with the full suite of contractual documentation and nor was it given any proper instruction about its contractual role as ‘Environmental Consultant’ under the APM Contract, what it entailed, and how it was to be performed.......... 30

The Master Plan for the purposes of the APM Contract was, at all relevant times, the Master Plan set out in Annexure B to the APM Contract............................................. 31

The Annexure B Master Plan remained throughout the benchmark against which Amcor’s liability to pay was to be assessed....................................................................... 32

The role of the Environmental Consultant under the APM Contract was a quite different role to GHD’s role as Glenvill’s environmental consultant.................................... 32

In performing its role as Environmental Consultant under the APM Contract, and in forming its opinions under SC 11.5(a)(ii)(B), GHD allowed itself to be influenced by the views of others................................................................................................................... 35

The evident purpose of the UC Notices to be given under SC 11.5........................... 37

Summary of the fate of Glenvill’s UC Notices........................................................................ 41

a......... UC Notice #1 (c.11 June 2014).............................................................................. 41

b......... UC Notice #1 - Revised (c.28 October 2014)...................................................... 45

c......... UC Notice #2 (c.19 March 2015).......................................................................... 49

d......... UC PCB Notice (c.5 May 2015)............................................................................ 58

e......... UC Notice #3 (c.18 June 2015).............................................................................. 59

f.......... UC Pulp Substitution Notice (c.22 June 2015)................................................... 67

g......... UC F6 Building Notice (c.26 June 2015)............................................................. 70

i.......... UC Notice #4 (c.6 October 2015).......................................................................... 72

i.......... UC Notice #4 – Addendum (c.2 November 2015)............................................ 84

j.......... UC Notice December 2015 (14 December 2015)................................................ 92

k......... UC Notice #5 (c.17 March 2016).......................................................................... 96

l.......... UC Notice #6 (c.17 June 2016).............................................................................. 97

m........ UC Notice #7 (c.24 May 2017)............................................................................ 110

n......... UC Notice #8 (c.11 August 2017)...................................................................... 135

The s 65M process whereby the Court appointed Mr Phil Sinclair as a s 65M expert.... 143

The invalidity of the UC Notices cannot be remedied by the s 65M process......... 147

Glenvill’s ‘cascading’ claims.................................................................................................... 154

Progress claims submitted by Glenvill to Amcor................................................................. 154

Montlaur was never provided with Deed of Variation No 1............................................. 154

The ‘Montlaur certifications’ did not conform with SC 11.3(b)(ii) and were ineffective to enliven any obligation on the part of Amcor as Vendor under SC 11.3 to pay 156

The ‘Montlaur certifications’ were not ‘binding’........................................................ 157

The ’Montlaur certifications’ do not have any ‘provisional status’......................... 157

It is not open to Glenvill to seek to have Montlaur issue fresh certifications following resolution by the Court of the SC 11.5 issues.................................................. 157

Glenvill’s ‘failure of the contractual mechanism’ plea seeks to have the Court determine the amount payable by Amcor pursuant to SC 11.2, in lieu of the amounts certified by Montlaur............................................................................................................................................ 159

What is the alleged failure of the contractual mechanism?....................................... 160

Amcor’s response............................................................................................................ 163

The contractual mechanism did not fail....................................................................... 164

Glenvill alleges a breach of SC 17.7 and implied terms (co-operation and good faith and fair dealing).............................................................................................................................. 166

Glenvill’s claim to recover monies by way of a ‘quantum meruit’................................... 172

Amcor’s Counterclaim............................................................................................................. 174

Issue 26: Riparian Zone................................................................................................... 175

Glenvill’s claimed entitlement to indemnification for costs of remediating Unidentified Contamination in the Riparian Zone................................................................ 179

Issue 27: F6 Building, 1954 Boiler House (& East-West Building)............................ 191

Consideration and disposition of the rival contentions concerning the 1954 Boiler House................................................................................................................................ 194

Consideration and disposition of the rival contentions concerning the F6 buildings 198

The Administration – (East/West) Building......................................................................... 200

Consideration and observations on the rival contentions concerning the Administration – (East/West) Building.......................................................................................... 201

Issue 28: Amcor’s counterclaim for interest................................................................. 203

The Trial conducted in 2020 and 2021........................................................................................ 210

Issues to be determined............................................................................................................ 211

Preliminary matters....................................................................................................................... 211

The relevant Master Plan......................................................................................................... 211

Evidential considerations......................................................................................................... 212

Section 136 rulings........................................................................................................... 212

Relevant persons not called by Glenvill....................................................................... 213

Other ‘Relevant persons’................................................................................................ 232

Amcor’s Jones v Dunkel submission............................................................................ 237

The records that Glenvill did not adduce.................................................................... 241

Jones v Dunkel findings............................................................................................................. 245

Background..................................................................................................................................... 245

The Amcor paper mill site at Alphington............................................................................. 245

Amcor entities take steps to prepare for a sale of the Alphington site............................. 246

Sale of the site in June 2013...................................................................................................... 246

Engagement of external contractors and consultants.......................................................... 250

Glenvill commenced this proceeding in June 2017.............................................................. 254

Work undertaken by Ramsay in advance of the sale.............................................................. 255

Detailed site investigation (DSI) performed by Ramsay in 2011....................................... 256

The outcomes of the soil assessment undertaken for the DSI............................................ 265

Ramsay 2011 cost estimate for remediation of hotspots..................................................... 268

Ramsay’s March 2013 estimate for remediation of Alpha Partners/Glenvill’s mixed-use development proposal and update of the Ramsay 2011 hotspots estimate............ 270

Preliminary remediation cost estimate for Alpha Partners/Glenvill’s proposed development plan........................................................................................................................ 270

Ramsay’s Preliminary Remediation Cost Estimate re Alpha Partners/Glenvill’s request................................................................................................................................ 274

Update of Ramsay’s February 2011 ‘hotspot’ remediation estimate....................... 274

Ramsay DSI and the preliminary remediation cost estimate for Alpha Partners/Glenvill’s development plan are incorporated by reference in the APM Contract................. 275

Ramsay’s June 2013 Revised Preliminary Remediation Cost Estimate for Alpha Partners/Glenvill’s Development Plan........................................................................ 275

The APM Contract......................................................................................................................... 277

The Property was sold and purchased on an ‘As is, where is’ basis including ‘any and all Contamination’................................................................................................................ 280

Purchaser required to procure ‘Demolition Works’ and ‘Remediation Works’.............. 281

Vendor’s obligation to pay in respect of ‘Demolition Works’ and ‘Remediation Works’ 284

Discovery of ‘Unidentified Contamination’.......................................................................... 285

The ‘expert’ dispute resolution process....................................................................... 286

Infrastructure Works................................................................................................................ 287

Seeking planning approval...................................................................................................... 289

Settlement to proceed in stages............................................................................................... 291

Environmental matters............................................................................................................. 293

General provisions.................................................................................................................... 294

Entire understanding...................................................................................................... 294

Interest payable by the Purchaser................................................................................. 295

Observations on the contractual arrangements made between the parties..................... 295

Deed of Nomination...................................................................................................................... 296

Deed of Novation........................................................................................................................... 296

Amendment or variation of the contractual arrangements between the parties to the APM Contract...................................................................................................................................................... 296

Deed of Variation No 1............................................................................................................. 296

Deed of Variation No 2............................................................................................................. 298

Alleged informal agreement to vary the APM Contract by correspondence in mid-2015 299

The 2017 variation of the APM Contract by correspondence............................................. 304

Remediation works........................................................................................................................ 314

Relevant contractual provisions.............................................................................................. 315

Unidentified contamination (SC 11.5).................................................................................... 322

What are ‘the uses specified in the Master Plan’?................................................................ 328

‘The Land’.................................................................................................................................. 331

Lay witnesses called by Glenvill................................................................................................ 333

Evidence given by Mr Travers Nuttall....................................................................................... 333

Engagement of consultants by Glenvill................................................................................. 336

Montlaur as certifier........................................................................................................ 336

Prensa – Occupational hygienist................................................................................... 337

Ken Mival – Environmental auditor............................................................................. 338

Reeds – Land surveyors.................................................................................................. 339

Douglas Partners – Geotechnical Engineers................................................................ 339

Master Plan................................................................................................................................ 339

Adjustments to the Master Plan.............................................................................................. 343

Infrastructure Works................................................................................................................ 344

Progress of works on site......................................................................................................... 346

Nearmap image comparison of physical condition of the site with Delta’s Trade Cost Breakdowns.......................................................................................................... 347

Remediation works remaining to be undertaken....................................................... 351

Remediation undertaken following Delta’s discovery of Unidentified Contamination 353

How Unidentified Contamination was approached on site............................................... 354

Widespread nature of the asbestos contamination in the southern part of the site 356

Amcor engaged Golder as its environmental advisor............................................... 356

Technical workshops and interaction with Golder.............................................................. 357

Engagement of CSC Civil Constructions............................................................................... 359

GHD’s Draft CLR report dated June 2016............................................................................. 362

Engagement of EnviroPacific Services (EPS)........................................................................ 362

Status of the Environmental Audit at the Alphington site................................................. 365

Evidence given by Mr Craig Joel................................................................................................ 367

Appointment of Contour Town Planners.............................................................................. 368

Master Plan................................................................................................................................ 368

Involvement with Golder representatives............................................................................. 371

Evidence given by Mr Robert Ryan........................................................................................... 372

Evidence given by Mr Gregory Priest........................................................................................ 375

Evidence given by Mr Brent Scoble........................................................................................... 377

Evidence given by Mr Adrian Scott........................................................................................... 381

Evidence given by Mr Shayne Linke......................................................................................... 391

Role of GHD as Environmental Consultant............................................................................. 395

Francis John Mollica................................................................................................................. 396

Anne Whincup.......................................................................................................................... 397

Thomas Winship....................................................................................................................... 398

Work undertaken by GHD...................................................................................................... 398

The GHD Contingent Liability Range Report...................................................................... 415

GHD’s Draft CLR Report (June 2016)........................................................................... 415

Presence, location and nature of remaining Unidentified Contamination....................... 428

Contingent Liability Ranges.................................................................................................... 430

Evidence given by Ms Anne Whincup...................................................................................... 431

Glenvill engaged GHD as its environmental consultant in November 2013................... 432

Environmental Audit................................................................................................................ 441

Timeline of key GHD works undertaken on site................................................................. 445

Site Management Plan v Environmental Management Plan.................................... 470

Once asbestos impacted soil was discovered at the Alphington site in May 2014, emotive issues associated with the presence of asbestos were referenced by GHD as a factor relevant to the remediation works to be undertaken..................................... 472

The Master Plan............................................................................................................... 476

Meetings with Golder representatives......................................................................... 477

The asbestos decision flowchart/ aka ‘the decision tree’/ aka ‘the GHD asbestos rationale’................................................................................................................................ 481

Technical meetings with Golder.................................................................................... 490

CLR reports....................................................................................................................... 499

Further technical meetings with Golder representatives.......................................... 500

RAP 2017........................................................................................................................... 502

Assistance provided to Dr Beck.................................................................................... 511

Comment on costs of work performed by EPS........................................................... 511

Initial GHD sampling and testing during 2014 and 2015.......................................... 511

General response from Ms Whincup to issues raised by Mr Kluckow............................. 516

Reply to Kluckow comment that GHD lacked a Strategy /Methodology.............. 516

Golder became involved in mid-2015 – context of site during time of Golder involvement................................................................................................................................ 519

Context of remediation options developed and adopted for the site...................... 528

Preparation of GHD letter accompanying UC Notice #2.......................................... 531

Evidence given by Mr Thomas Winship................................................................................... 543

Validation report for Area 5A (May 2018)................................................................... 546

Validation report for Super Lot 3.2 and the House & Land Package (July 2017).. 550

Addendum report to the Validation Report for Super Lot 3.2 and the House & Land Package (November 2017).................................................................................................. 552

Final Validation Report for Area 6B (June 2018)......................................................... 556

2017 RAP........................................................................................................................... 563

Evidence given by Mr Frank Mollica......................................................................................... 566

GHD’s meetings with Golder representatives............................................................ 572

October-November 2015 technical meetings............................................................... 582

Presence of uncontrolled fill across the Alphington site – geotechnical issues were raised................................................................................................................................ 582

Meetings with the Environmental Auditor................................................................. 586

Contingent Liability Reports.......................................................................................... 587

GHD did not endorse JBS&G’s remediation strategy and forecast cost estimates for Unidentified Contamination.............................................................................. 594

The geotechnical report of 14 June 2016 which forms Annexure B to both the June 2016 Draft CLR and December 2016 CLR reports.............................................................. 594

Response to the Golder queries..................................................................................... 600

NEPM – Schedule B1....................................................................................................... 605

Basements – effect on remediation costs...................................................................... 611

Role of the occupational hygienist on site................................................................... 611

Evidence given by Mr Craig Eldridge........................................................................................ 612

Draft Geotechnical Desk Top Appraisal................................................................................ 613

Scenario 1 - Compact in situ (without any treatment) and leave undisturbed with a suitable capping layer of clean soils................................................................................ 615

Scenario 2 – Excavate, sort and then replace the fill soils under Level 1 supervision. 619

Geotechnical appraisal.................................................................................................... 619

Riparian Zone................................................................................................................... 621

Evidence given by Mr Cameron Hunter.................................................................................... 637

Overview of Prensa’s involvement at the Alphington site................................................. 638

Delta engaged Prensa to perform work....................................................................... 638

CSC Civil engaged Prensa.............................................................................................. 646

Glenvill engaged Prensa to support EPS with occupational hygiene services...... 647

Mr Hunter’s creation of the Technical Specification and input into the April 2017 Remediation Action Plan....................................................................................................................... 649

The Technical Specification............................................................................................ 649

The 2017 Remediation Action Plan............................................................................... 658

Mr Hunter’s commentary on Yanel Lara’s views and position......................................... 664

Response to Ms Lara’s criticism that GHD was not properly classifying material that could have been available for re-use on site............................................................... 664

Response to Ms Lara’s comments on the extent of asbestos contamination at the site     667

Response to Ms Lara’s comments regarding the hazardous nature of asbestos.... 669

Response to Ms Lara’s criticisms of GHD’s advice to use the AS4964 method of analysis................................................................................................................................ 670

Reply to the alternate strategy proposed by Ms Lara................................................ 673

Lay witnesses called by Amcor................................................................................................... 676

Evidence given by Mr Glenn Maskell....................................................................................... 676

Progress claims.......................................................................................................................... 678

Planning considerations on the site........................................................................................ 679

Appointment of Montlaur....................................................................................................... 680

Appointment of GHD (as Environmental Consultant under the Contract)..................... 681

Amcor’s continued engagement of Ramsay......................................................................... 682

Discovery of unidentified contamination.............................................................................. 682

Amcor’s input into the Glenvill remediation strategy........................................................ 686

Whether Amcor was looking for reasons not to pay........................................................... 688

Evidence given by Ms Yanel Lara............................................................................................... 689

Involvement at the Alphington site........................................................................................ 691

Asbestos in Soil Assessment flowchart.................................................................................. 696

Technical meeting with representatives of GHD, Glenvill, and Golder........................... 696

The gist of Ms Lara’s criticism of GHD’s approach............................................................. 697

Installation of the hoarding along Chandler Highway....................................................... 697

New asbestos management plan issued by GHD................................................................ 698

Reply to statements made by Mr Hunter.............................................................................. 699

Evidence given by Mr Roger Foenander................................................................................... 701

Evidence given by Mr Ian Matthew Kluckow......................................................................... 719

Prior involvement..................................................................................................................... 720

Expert witnesses in the proceeding............................................................................................ 732

Evidence given by Dr Peter Beck................................................................................................ 733

Evidence given by Dr Ian Swane................................................................................................ 733

Evidence given by Mr Stephen Bolt........................................................................................... 734

Evidence given by Mr Matthew Kritzler................................................................................... 735

Relevant statutory framework..................................................................................................... 736

Relevant statutory framework for occupational health and safety...................................... 738

Occupational Health and Safety Regulations 2007.............................................................. 738

Relevant statutory framework for environmental protection and management............... 739

Environment Protection Act 1970 (Vic)..................................................................................... 739

Environment protection principles............................................................................... 739

State environment protection policy............................................................................. 742

National Environment Protection Measure................................................................. 745

Environmental audits...................................................................................................... 748

Planning system mechanisms................................................................................................. 756

Planning and Environment Act 1987 (Vic)............................................................................... 756

Direction No 1: Potentially Contaminated Land........................................................ 757

DSE General Practice Note: Potentially Contaminated Land................................... 759

City of Yarra: Amcor Site Design and Development Principles............................... 761

Yarra Planning Scheme................................................................................................... 764

The Environmental Audit Overlay............................................................................... 768

Other background materials.......................................................................................... 769

GHD’s Site Remediation Strategy (May 2014)...................................................................... 769

A.. Payment claims – special condition 11.3.............................................................................. 775

Issue 1:Is Glenvill entitled to payment of the outstanding claims totalling $30,992,925.45 (inclusive of GST) (the Outstanding Claims) by reason of the presentation by Glenvill of the invoices and certifications, referred to in SC 11.3(b) of the APM Contract?.......................... 775

Issue 4:Is the certification by Montlaur of progress claims 23 to 54 determinative of any issue between Glenvill and Amcor?....................................................................................... 775

The Montlaur certifications with respect to Progress Claims 23 to 54 (inclusive) were not binding.................................................................................................................. 777

Do the Montlaur certifications have any provisional status?................................... 783

Whether the s 65M expert appointed by the Court identified any ‘scope of work’ and if so, whether there is any evidence that enables the Court to quantify that scope 788

It is not open to Glenvill to seek to have Montlaur issue fresh certifications following resolution by the Court of the SC 11.5 issues.................................................. 789

Glenvill’s ‘failure of the contractual mechanism’ plea seeks to have the Court determine the amount payable by Amcor pursuant to SC 11.3, in lieu of the amounts certified by Montlaur............................................................................................................... 792

Issue 2:Does the $30,992,925.45 (inclusive of GST) claimed by Glenvill in relation to progress claims 23 to 54 include items defined as Remediation Works which ought properly to have been classified as: (a) Demolition Works…; (b) variations to Demolition Works…; (c) Consultants’ Works…; (d) works which were not Demolition Works, Remediation Works or Consultants’ Costs…, including works undertaken to address geotechnical issues at the APM site?.......................................................................................................................... 797

Issue 3:Has Glenvill failed to prove that the amounts claimed from Amcor in progress claims 23 to 54 were each costs for Remediation Work?............................................................. 797

Introduction............................................................................................................................... 797

Issue 2 as framed....................................................................................................................... 798

Issue 2 – Amcor’s submissions................................................................................................ 799

Issue 3 as framed....................................................................................................................... 806

Issue 3 – Amcor’s submissions................................................................................................ 807

(a)....... Glenvill failed to ensure that its contractors kept proper records................ 810

(b)...... The records that Glenvill elected not to adduce............................................. 822

(c)....... The witnesses that Glenvill elected not to call................................................ 824

(d)...... Informed estimation is not permitted............................................................... 827

Issues 2 and 3 – Glenvill’s submissions................................................................................. 829

Glenvill’s Revised Outstanding Claims Amount recognises the Demolition Works Cap and the Consultant’s Works Cap.............................................................................. 830

Allocation of costs between categories in Issue 2 – ‘Materials relied upon’ by Glenvill  832

Amcor’s closing address – Issues 2 and 3.............................................................................. 833

Glenvill’s closing address – Issues 2 and 3............................................................................ 836

Consideration and conclusion on Issues 2 and 3.................................................................. 836

B.. Compliance with special condition 11.2(b)......................................................................... 839

Introduction............................................................................................................................... 839

Issue 5: Performance of Glenvill’s obligations under SC 11.2(b) – did Glenvill ‘use reasonable endeavours to minimise the cost of the … Remediation Works’ and/or ‘procure … the Remediation Works … to be carried out cost effectively and to a reasonable commercial standard.’?.................................................................................................................................. 864

Issue 5 – Amcor’s submissions (overview)........................................................................... 865

Issue 5 – Glenvill’s response (overview)............................................................................... 876

Overarching observations on Issue 5..................................................................................... 878

Issue 5(b):  Amcor contends that Glenvill should have paused sub-surface demolition when it became apparent that there was substantial asbestos contamination in the fill on the site............................................................................................................................................ 881

Amcor’s submissions...................................................................................................... 881

Glenvill’s response.......................................................................................................... 888

Issues 5(a) and 5(c):  Amcor contends that Glenvill’s approach to remediation of the site was ad hoc and reactive and that Glenvill failed to formulate an appropriate remediation strategy............................................................................................................................................ 894

Amcor’s submissions...................................................................................................... 895

Glenvill’s response.......................................................................................................... 901

Issues 5(d) and 5(e):  Amcor contends that Glenvill adopted a remediation strategy of removing all (or substantially all) fill at the site, principally for geotechnical reasons, and failed to properly investigate and/or adopt a capping strategy to remediate the asbestos contamination at the site................................................................................................. 911

Amcor’s submissions...................................................................................................... 913

Glenvill’s response to Issues 5(d) and 5(e)................................................................... 957

Overarching observations on capping strategy issues raised in Issues 5 and 7.............. 970

Issue 5(f):  Amcor contends there were failures by Glenvill in its tendering processes. 984

Overarching observations on SC 11.2 issues raised in Issues 5 and 8............................. 1009

Issue 5(g):  Amcor contends that there were failures by Glenvill in its management of soil and/or fill excavated at the Alphington site........................................................................... 1012

Glenvill’s response........................................................................................................ 1025

Observations on Issue 5(g)........................................................................................... 1026

Issue 5(h):  Amcor contends that Glenvill failed to consider any changes to the Master Plan which were likely to reduce the cost of the Remediation Works at the Alphington site 1026

Observations on Issue 5(h)........................................................................................... 1037

Unidentified contamination claims – special condition 11.5.............................................. 1038

Progress claims 1 to 22A were paid in full by Amcor....................................................... 1038

Issue 10: Whether the UC notices to which claims 23 to 54 relate are valid?................... 1039

Issue 11: Whether Amcor objected to the UC Notices served and were those objections valid?.................................................................................................................................................... 1039

Glenvill contends the UC Notices it served on Amcor satisfied SC 11.5(a) of the APM Contract and were ‘valid’............................................................................................................. 1044

Lack of correlation between progress claims 23 to 54 and UC notices relied on by Glenvill is problematic..................................................................................................................... 1046

How the parties construed SC 11.5....................................................................................... 1048

Amcor contends that Glenvill’s UC Notices were invalid...................................... 1048

Glenvill disputes Amcor’s construction of SC 11.5(a)(i).......................................... 1050

Amcor’s construction of SC 11.5(a)(i)......................................................................... 1052

Proper construction of SC 11.5(a)......................................................................................... 1053

The Master Plan for the purposes of the APM Contract.......................................... 1055

Did the UC Notices given by Glenvill comply with SC 11.5?................................. 1065

Contractual requirements concerning ‘UC Notices’ and ‘objections’ under SC 11.5 – relevant concept of ‘validity’........................................................................................... 1102

Were the UC Notices valid?................................................................................................... 1113

UC Notice #1.................................................................................................................. 1114

Disposition: UC Notice #1 is not a ‘valid’ notice...................................................... 1129

Any objection to UC Notice #1?.................................................................................. 1132

UC Notice #1 Revised................................................................................................... 1133

Disposition: UC Notice #1 Revised is not a ‘valid’ notice....................................... 1171

Any objection to UC Notice #1 Revised?................................................................... 1176

The status of GHD as the Environmental Consultant under the APM Contract was formalised by Deed of Variation No 1............................................................ 1177

UC Notice #2.................................................................................................................. 1177

Disposition: UC Notice #2 was not a ‘valid’ notice.................................................. 1211

Any objection to UC Notice #2?.................................................................................. 1212

UC PCB Notice............................................................................................................... 1218

Disposition: UC PCB Notice is not a ‘valid’ notice................................................... 1223

Any objection to UC PCB Notice?............................................................................... 1224

UC Notice #3.................................................................................................................. 1226

Newly identified issues................................................................................................ 1234

Disposition: UC Notice #3 was not a ‘valid’ notice.................................................. 1249

Amcor’s objection to UC Notice #3............................................................................. 1251

UC Pulp Substitution Notice........................................................................................ 1251

Amcor’s objection to the UC Pulp Substitution Notice........................................... 1254

UC F6 Building Notice.................................................................................................. 1255

Amcor’s objection to the UC F6 Building Notice...................................................... 1259

UC Notice #4.................................................................................................................. 1259

Update concerning previously discovered ‘Unidentified Contamination’.......... 1267

Newly discovered unidentified contamination........................................................ 1271

Disposition: UC Notice #4 was not a ‘valid’ notice.................................................. 1295

Amcor’s objection to UC Notice #4............................................................................. 1296

UC Notice #4 Addendum............................................................................................ 1297

Disposition: UC Notice #4 Addendum was not a ‘valid’ notice............................ 1302

Amcor’s objection to UC Notice #4 Addendum....................................................... 1303

UC Notice December 2015............................................................................................ 1307

Disposition: UC Notice December 2015 was not a ‘valid’ notice........................... 1311

UC Notice #5 (c.17 March 2016).................................................................................. 1312

Disposition: UC Notice #5 is no longer pressed by Glenvill................................... 1314

Issue 10: Whether the UC notices to which claims 23 to 54 relate are valid?................... 1314

UC Notice #6.................................................................................................................. 1314

Low Density Residential use........................................................................................ 1339

Medium Density Residential use................................................................................ 1356

High Density Residential use...................................................................................... 1363

Mixed Use....................................................................................................................... 1368

Public Open Space – Non Riparian Zone ( Zone 5, Zone 13, Zone 19 and Zone 20) 1376

Public Open Space – Riparian Zone (Zone 1 and Zone 2)....................................... 1381

Amcor’s response to the June 2016 Draft CLR Report............................................. 1399

GHD’s Proposed further sampling and analysis plan - November 2015.............. 1400

Disposition: UC Notice #6 was not a ‘valid’ notice.................................................. 1407

Amcor’s objection to UC Notice #6............................................................................. 1411

UC Notice #7.................................................................................................................. 1413

GHD’s letter dated 24 May 2017.................................................................................. 1416

GHD’s Status of Identified Contamination Remediation Works & Costs Letter dated 10 October 2016.................................................................................................. 1419

December 2016 CLR Report......................................................................................... 1424

Location of Unidentified Contamination................................................................... 1435

May 2017 CLR Addendum Report............................................................................. 1473

Disposition: UC Notice #7 was not a ‘valid’ notice.................................................. 1481

Amcor’s objection to UC Notice #7............................................................................. 1492

UC Notice #8.................................................................................................................. 1493

GHD’s letter report dated 10 August 2017................................................................ 1495

Amcor’s response to UC Notice #8............................................................................. 1504

Glenvill’s response to Amcor’s objection................................................................... 1505

Disposition: UC Notice #8 was not a ‘valid’ notice.................................................. 1508

Amcor’s objection to UC Notice #8............................................................................. 1509

Answers to Issues 10 and 11....................................................................................................... 1510

Issues 12 to 19 (concerning ‘valid’ UC Notices)..................................................................... 1510

Issue 13: How are the SC 11.5(c) issues to be determined by the Court (in lieu of an expert) in respect of the relevant UC notices?..................................................................................... 1515

Issue 14: What findings is the Court required to make under SC 11.5(c) as a pre-condition to Amcor incurring any contractual liability under SC 11.3(a)?..................................................... 1515

Issue 15: Do the reports of the Court appointed s 65M expert provide the Court with a proper basis to make the necessary findings?......................................................................................... 1515

Orders made by Hargrave J on 1 December 2017.............................................................. 1519

Glenvill engaged Dr Beck as its nominated expert............................................................ 1527

Amcor engaged Mr Kluckow as its nominated expert...................................................... 1528

The s 65M expert: Mr Sinclair................................................................................................ 1528

The conduct of the s 65M process......................................................................................... 1529

Expert report of Dr Beck........................................................................................................ 1529

Introduction.................................................................................................................... 1529

Conceptual Site Model.................................................................................................. 1531

‘Disputed UC Notices’.................................................................................................. 1534

Question 1....................................................................................................................... 1555

Dr Beck’s response to Question 1................................................................................ 1555

Dr Beck’s Response to Question 2............................................................................... 1587

Dr Beck’s Response to Question 3............................................................................... 1613

Dr Beck’s Response to Question 4............................................................................... 1628

Environmental audits for potentially contaminated sites....................................... 1632

Dr Beck’s Response to Question 5............................................................................... 1641

Dr Beck’s Response to Question 6............................................................................... 1672

Summary of Dr Beck’s opinions.................................................................................. 1687

Expert report of Mr Kluckow................................................................................................ 1690

Question 1....................................................................................................................... 1700

Mr Kluckow’s response to Question 1........................................................................ 1705

Question 2....................................................................................................................... 1707

Mr Kluckow’s response to Question 2........................................................................ 1707

Question 3....................................................................................................................... 1709

Mr Kluckow’s response to Question 3........................................................................ 1712

Question 4....................................................................................................................... 1714

Mr Kluckow’s response to Question 4........................................................................ 1718

Question 5....................................................................................................................... 1728

Mr Kluckow’s response to Question 5........................................................................ 1728

Question 6....................................................................................................................... 1729

Mr Kluckow’s response to Question 6........................................................................ 1733

Summary of Mr Kluckow’s opinions................................................................................... 1748

Section 65M reports prepared by Mr Sinclair........................................................................ 1751

Section 65M process.................................................................................................................... 1754

The gist of the evidence given by Mr Sinclair in his reports............................................ 1759

Viva voce evidence given by Mr Sinclair at the trial......................................................... 1777

Evidence given by Dr Beck at trial concerning volume estimates......................... 1794

The outcome of the s 65M process............................................................................................ 1808

Issues as to quantum................................................................................................................... 1819

Introduction............................................................................................................................. 1819

Glenvill’s proposed use of progress claim ‘road maps’........................................... 1821

Glenvill’s progress claim ‘Road Map’ aide-mémoire........................................................... 1824

Amcor’s Thematic Response to Glenvill’s PC Road Maps.................................................. 1826

Montlaur was never provided with Deed of Variation No 1........................................... 1827

Quantum and proof of Glenvill’s claim as to the quantum of costs ‘properly and reasonably incurred’ for the purposes of SC 11.3(a)(ii) of the APM Contract................................ 1833

Closing addresses on quantum................................................................................................. 1834

Amcor’s submissions on quantum....................................................................................... 1834

Glenvill’s failure to adduce records concerning ‘Remediation Works’ capable of enlivening Amcor’s obligation to pay................................................................................ 1834

The QS evidence of the expert quantity surveyors does not assist to prove Amcor is liable for any specific quantum of claim................................................................... 1838

Amcor’s Thematic Response to Glenvill’s PC Road Maps.................................................. 1850

Overview of works performed by Delta.................................................................... 1850

Part CDelta works which Glenvill has claimed as ‘Remediation Works’ but which were wholly or partly ‘Demolition Works’............................................................. 1850

Part DBulk Excavation and Subsequent Abatement or Disposal of Contaminated Fill by Delta..................................................................................................................... 1889

Part EInability to Reconcile Underlying and Summary Records Supporting Delta’s Progress Claims.................................................................................................................. 1891

Part F............................................................................. CSC Progress Claims - Overview..... 1893

Part GCSC Progress Claims - Detail........................................................................... 1894

Amcor’s detailed response to Glenvill’s PC Road Map.................................................... 1901

Amcor’s closing address on quantum................................................................................. 1903

Deficiencies in the Montlaur certifications are fatal to Glenvill’s claim................ 1903

Glenvill’s reliance on Mr Kritzler’s expert report..................................................... 1908

Glenvill relies on the records of the respective Contractors which Amcor alleges are deficient.............................................................................................................................. 1909

Glenvill has failed to articulate what it contends the  phrases or expressions used in the APM Contract — ‘properly and reasonably incurred’ and ‘properly payable’ — mean.............................................................................................................................. 1912

Glenvill’s approach to Remediation Works............................................................... 1915

Inclusion in Delta’s progress claims of Extra Over costs......................................... 1917

Montlaur’s reconciliation of Delta’s use of plant...................................................... 1933

Mr Scoble’s modus operandi provides no proper basis for independent verification 1934

Asbestos cement pipes.................................................................................................. 1934

Glenvill’s complaint that Amcor failed to put certain matters to its contractor witnesses.............................................................................................................................. 1937

Chandler Highway Hoarding Claim.......................................................................... 1939

D.. Failure of contractual mechanism....................................................................................... 1960

Issue 20:  Alleged failure of the contractual mechanism...................................................... 1960

Glenvill’s pleading of the alleged failure............................................................................ 1960

Glenvill’s case in opening...................................................................................................... 1963

Amcor’s response.................................................................................................................... 1965

What is the alleged failure of the contractual mechanism?.............................................. 1970

Amcor’s submissions.............................................................................................................. 1975

Glenvill’s oral closing submissions...................................................................................... 1985

Amcor’s oral reply to Glenvill’s oral closing submissions................................................ 1991

Consideration and conclusion on Issue 20.......................................................................... 1995

The reference to events in November 2015................................................................ 1995

The 2017 variation of the APM Contract by correspondence................................. 1998

The proper construction of SC 11.5(c) and SC 11.3 (insofar as it related to remediation in respect of Unidentified Contamination).................................................................................. 2001

The contractual mechanism did not fail..................................................................... 2007

Issue 21:  Alleged breach of SC 17.7 and implied terms (co-operation and good faith and fair dealing).................................................................................................................................... 2009

Glenvill’s submissions............................................................................................................ 2010

Knowledge of risk withheld from Glenvill................................................................ 2012

Amcor’s instruction or consent to proceed with works........................................... 2012

Amcor’s pursuit of an extraneous purpose on the advice of Golder..................... 2014

Amcor’s submissions.............................................................................................................. 2017

Knowledge of risk withheld from Glenvill................................................................ 2018

Amcor’s instruction or consent to proceed with works........................................... 2019

Amcor’s pursuit of an extraneous purpose on the advice of Golder..................... 2019

Glenvill’s closing address...................................................................................................... 2020

Amcor’s oral submissions in reply....................................................................................... 2022

Consideration and conclusion on Issue 21.......................................................................... 2024

Glenvill’s ‘knowledge of risk withheld’ allegation.................................................. 2028

Issue 22:  What is the quantum of costs ‘properly and reasonably incurred’ by Glenvill in procuring/undertaking Demolition Works and Remediation Works, as assessed by the Court?.................................................................................................................................................... 2035

Glenvill’s submissions............................................................................................................ 2036

Quantum of costs arising from UC Notices not the subject of objection by Amcor (UC Notice #1, UC Notice #1 Revised and UC Notice #4)......................... 2036

Quantum of costs of remediating Identified Contamination.................................. 2041

Amcor’s submissions.............................................................................................................. 2043

Consideration and conclusion on Issue 22.......................................................................... 2044

E... Quantum meruit (Issue 23)................................................................................................... 2045

Glenvill’s submissions............................................................................................................ 2046

Amcor’s submissions.............................................................................................................. 2047

No basis in the pleadings for a claim in quantum meruit....................................... 2047

No basis in fact for a claim in quantum meruit......................................................... 2050

No basis in law for a claim in quantum meruit........................................................ 2053

Consideration and conclusion on Issue 23.......................................................................... 2057

F... Master Plan.............................................................................................................................. 2058

Issue 24: [no longer pressed]...................................................................................................... 2058

Issue 25: Adjustments to be made to the Master Plan  - whether any adjustments are proposed to be made by Glenvill (SC 11.5(a)(i)) – or should be made (SC 11.5(c)(i)) - to mitigate the effect of the Unidentified Contamination?....................................................................................... 2061

Glenvill’s closing submissions..................................................................................... 2063

Amcor’s closing submissions....................................................................................... 2063

Disposition of Issue 25.................................................................................................. 2064

G.. Riparian Zone......................................................................................................................... 2065

Issue 26: Whether Glenvill can recover costs of remediating Unidentified Contamination in the Riparian Zone?....................................................................................................................... 2065

What is the Riparian Zone?................................................................................................... 2065

The basis on which Amcor seeks declaratory relief................................................. 2069

Amcor’s contentions............................................................................................................... 2078

The Master Plan did not include the Riparian Zone................................................ 2079

The Master Plan in Annexure B did not show a ‘use’ for the Riparian Zone....... 2082

Glenvill’s contentions............................................................................................................. 2084

Glenvill contends the Master Plan designated the Riparian Zone as land specified to be usable and accessible as public open space................................................... 2084

Glenvill contends the Riparian Zone was included within the uses specified in the Master Plan...................................................................................................................... 2087

Glenvill’s foreshadowed entitlement to indemnification for costs of remediating Unidentified Contamination in the Riparian Zone...................................... 2092

Consideration of rival arguments and disposition............................................................... 2094

Relevant pre-contractual documents and communications............................................. 2096

The Ramsay suite of documents........................................................................................... 2099

The Ramsay DSI report................................................................................................. 2100

Ramsay (costing) letter report dated 7 February 2011............................................. 2108

Request for Ramsay to provide further information (February 2013)................... 2114

Ramsay (costing) letter report dated 14 March 2013................................................ 2114

Ramsay letter report dated 28 June 2013 – ‘Ramsay Costing’................................. 2119

Email correspondence from Glenvill to Amcor dated 25 June 2013...................... 2123

Relevant post-contractual events.............................................................................................. 2126

GHD Site Remediation Strategy (December 2013)............................................................. 2127

GHD Remediation Cost Estimate (May 2014).................................................................... 2133

GHD Site Remediation Strategy (May 2014)....................................................................... 2141

GHD Addendum to Site Remediation Strategy (October 2014)...................................... 2144

GHD Remediation Action Plan (October 2014).................................................................. 2146

GHD Health Risk Assessment (October 2014).................................................................... 2148

Deed of Variation No 1 dated 18 February 2015................................................................ 2149

Yarra Planning Scheme matters............................................................................................ 2152

Is Amcor liable to pay any sum in respect of remediation of Unidentified Contamination in the Riparian Zone?............................................................................................................... 2157

Progress Claim No 53.................................................................................................... 2158

Progress Claim No 54.................................................................................................... 2159

Appendix A Table 1 Update to Areas to be further assessed during Remediation (including subsurface infrastructure)................................................................................ 2164

The Draft Riparian Zone RAP (November 2018)...................................................... 2166

Content of the Draft Riparian Zone RAP – the remediation actions proposed.... 2169

Conclusion..................................................................................................................................... 2178

H.. Boiler House [1954 Boiler House and F6 Building]......................................................... 2180

Issue 27: Whether Glenvill or Amcor is liable to pay for demolition and/or remediation works undertaken in relation to the 1954 Boiler House and the F6 Building?...................... 2180

Location of the 1954 Boiler House and F6 Buildings......................................................... 2181

The APM Contract – ‘Plant and Equipment’...................................................................... 2185

The Delta Quote...................................................................................................................... 2189

Deed of Variation No 1........................................................................................................... 2191

The Delta Contract.................................................................................................................. 2193

Proposed demolition of the 1954 Boiler House.................................................................. 2197

Evidence given at trial about the 1954 Boiler House................................................ 2200

Demolition of the F6 Buildings............................................................................................. 2203

The Delta Quote............................................................................................................. 2203

The Delta Contract......................................................................................................... 2204

Amcor’s contentions – 1954 Boiler House........................................................................... 2227

Glenvill’s contentions – 1954 Boiler House......................................................................... 2228

Amcor’s contentions – F6 Buildings..................................................................................... 2231

Glenvill’s contentions – F6 Buildings................................................................................... 2232

Consideration and disposition.............................................................................................. 2232

Issue 27(a)....................................................................................................................... 2232

Issue 27(b)....................................................................................................................... 2244

Issue 27(c)........................................................................................................................ 2245

Declaratory relief sought in Amcor’s counterclaim........................................................... 2248

The Administration – (East/West) Building....................................................................... 2249

Delta Contract................................................................................................................ 2249

December 2014 Site Instruction................................................................................... 2253

Validation Report for Area 4........................................................................................ 2255

Required remediation works: Administration – (East/West) Building?........................ 2258

Amcor’s contentions...................................................................................................... 2261

Observations on relief sought............................................................................................... 2265

[6226]Amcor’s second further amended particulars of loss and damage of its counterclaim (11 August 2021).

  1. The amounts claimed ‘pursuant to statute’ are in the alternative to the amounts claimed pursuant to SC 17.16 of the APM Contract (as set out in paragraphs [1.5] and [2.5] of Amcor’s Second Further Amended Particulars), and are described as follows in the text of Amcor’s Second Further Amended Particulars:[6227]

    [6227]Amcor’s second further amended particulars of loss and damage of its counterclaim (11 August 2021), at [1.5A]-[1.6] and [2.5A].

. . .

  1. Amcor’s calculations of the interest accruing pursuant to statute from the due date until judgment (using the hypothetical delivery date of 1 August 2022) were set out in Part 3 of Annexure C, as follows:[6228]

[6228]Amcor’s second further amended particulars of loss and damage of its counterclaim (11 August 2021), Annexure C, Part 3 – Alternative calculation of accrued interest.

  1. In the Amcor Reply Submissions & Worked Example, Amcor noted that it has given particulars of its alternative claim for (simple) interest under s 58 and confirmed that it seeks an award of interest pursuant to s 58 ‘up to entry of judgment’.[6229]

    [6229]Amcor Reply Submissions & Worked Example (11 August 2021), at [10] citing Seoud v Fortythird Garland Pty Ltd (2019) 57 VR 262 at [95] per McMillan J.

  1. In circumstances where Glenvill has now agreed with Amcor upon the quantum of the outstanding amounts that are unpaid by Glenvill under SC 10.8(b) (‘the First Outstanding Interest Amount’ – $846,448.63) and SC 10.8(d) (‘the Second Outstanding Interest Amount’ – $2,429,201.10), and has become ‘certain’ within the meaning of s 58, and each of those amounts will be recovered by Amcor as part of the relief to be awarded in the counterclaim proceeding, Amcor now seeks interest on each of those amounts under s 58. Amcor submits that the requirements of s 58(1) are satisfied, such that it is prima facie entitled to an award of interest on each of those amounts unless good cause to the contrary can be demonstrated, and the onus is on Glenvill, as the defendant to the counterclaim, to show good cause.

  1. As Tate and Kyrou JJA explained in Carbone, the beneficial purpose underlying the statutory power to award interest is first to ‘compensate a party who has been obliged to take proceedings to recover a money sum and who in the meantime has been kept out of moneys which could otherwise have been used or upon which interest could have been earned’ and ‘s 58 should not be given a narrow meaning and that its beneficial purpose should be given a broad application.’  The notion underlying the beneficial purpose, however, that the person ‘has been kept out of moneys which could otherwise have been used’ also connotes that the money sought to be recovered was due and payable — and should have been paid —before the initiation of the proceeding.[6230]

    [6230]Amaca Pty Ltd v CSR Ltd [No 2] [2015] VSC 605 at [10] Macaulay J, citing City Mutual Life Assurance Society Ltd v Giannarelli [1977] VR 463, 466; Saunders v Nash [1991] 2 VR 63, 68 (Vincent J); Chong v CC Containers Pty Ltd (2015) 49 VR 402, 476 [256].

  1. In the present case, SC 10.8 of the APM Contract specified a date for payment of each of the sums payable on settlement of the various Superlots together with interest for a specified period in circumstances where the plan (or plans) of subdivision were not registered within the timeframe:

(a)SC 10.8(b) provided that if the plan of subdivision or consolidation (creating Superlots 1, 2, 3, 4, 5 and 6) was not registered on or before 15 June 2016, then settlement of the Green Land must occur with Glenvill as sole Purchaser paying the sum of $31million, and Glenvill must pay interest to the Vendor on the amount of $31million for the period from 15 December 2015 until 15 June 2016 as prescribed under SC 10.8(b)(iv) and such interest is payable on 15 June 2016; and

(b)SC 10.8(d) provided that if a plan (or plans) of subdivision or consolidation (creating Superlots 4, 5 and 6) was not registered on or before 15 December 2016, then the settlement of Superlots 4, 5 and that part of Superlot 6 which does not comprise the Green Land must occur with Glenvill as sole Purchaser paying the sum of $51million, and Glenvill must pay interest to the Vendor on the amount of $27million for the period from 15 December 2016 until 15 December 2017 as prescribed under SC 10.8(d)(iii) and such interest is payable on 15 December 2017.

  1. However, on 17 May 2016, before any interest had fallen due for payment under the APM Contract, the parties agreed to defer the date for payment of penalty interest ‘until 14 days after determination by the expert’ but with a reservation of rights.  As matters transpired, the settlements of the Superlots proceeded, and with the deferral of the payment of penalty interest, Amcor has effectively been kept out of its moneys because there has not been any expert determination and the Court has now been appointed in place of the expert, with the result that it has been necessary for Amcor to seek the recovery of those moneys payable under SC 10.8, together with interest, through its counterclaim.

  1. The proceeding was commenced by Glenvill on 15 June 2017, and Amcor initiated its counterclaim on 14 August 2017.  However, as will be noted, given the parties’ agreement on 17 May 2016 to defer the date for payment of penalty interest ‘until 14 days after determination by the expert’, neither of the money sums payable under SC 10.8(b)(iv) or SC 10.8(d)(iii) was actually a debt that was due and payable to Amcor at the time of commencement of Glenvill’s proceeding or Amcor’s counterclaim.

  1. Accordingly, were it necessary to consider Amcor’s alternative claim for interest pursuant to statute, under s 58 of the Supreme Court Act, I am not satisfied that Amcor’s claim for interest on either the First or Second Outstanding Amounts payable under SC 10.8, meets the threshold requirement of s 58. That is because the parties expressly agreed to defer payment of penalty interest ‘until 14 days after determination by the expert’, with the result that Amcor has not been kept out of its money in the relevant sense.

Form of final orders

  1. In due course, I will hear from the parties as to the appropriate form of final orders.

---


·     Fairfield Mill, Victoria – Contamination Plan, prepared by Gutteridge Haskins & Davey Pty Ltd [now known as ‘GHD’] for Amcor Fibre Packaging (Australia) Pty Ltd, May 2003;

·     Environmental Audit of Fairfield Mill, Alphington, Victoria, prepared by Parsons Brinkerhoff Australia Pty Limited for Amcor Australasia Pty Ltd, February 2008;

·     Draft Phase 1 Environmental Site Assessment for Latrobe Avenue, Alphington, Victoria, prepared by Parsons Brinkerhoff Australia Pty Limited for Amcor Australasia Pty Ltd, December 2008;

·     Phase 2 Environmental Site Assessment — Fairfield Mill, Alphington, Victoria, prepared by Parsons Brinkerhoff Australia Pty Limited for Amcor Australasia Pty Ltd, January 2009; and

·     Asbestos Audit Review, Amcor Fibre Packaging, Fairfield Mill, prepared by Bureau Veritas for Amcor Fibre Packaging, December 2007.

4.6 Asbestos soil contamination and health risk

Asbestos only poses a risk to human health when asbestos fibres are made airborne and inhaled.  If asbestos is bound in a matrix such as cement or resin, it is not readily made airborne except through substantial physical damage.

This guidance emphasises that the assessment and management of asbestos contamination should take into account the condition of the asbestos materials and the potential for damage and resulting release of asbestos fibres.

Bonded ACM in sound condition represents a low human health risk.  However, both FA and AF materials have the potential to generate, or be associated with, free asbestos fibres.  As a result, FA and AF must be carefully managed to prevent the release of asbestos fibres into the air.

It is an inappropriate response to declare a site a human health risk on the basis of the presence of bonded ACM alone.  However, if the bonded material is damaged or crumbling (that is, it has become friable), it may represent a significant human health risk if disturbed and fibres are made airborne.

The site-specific assessment of sites contaminated with asbestos in soil should be aimed at describing the nature and quantity of asbestos present in sufficient detail to enable a risk management plan to be developed for the current or proposed land use.  The management plan should address potential scenarios for the relevant land use(s) whereby asbestos fibres may become airborne and pose a human health risk.

[MR MONICHINO:]  So the aesthetic issues remained?---Yes, they did.  We did further investigation and discussions with the auditor and negotiated to a position where the auditor was happy with the site removing all the fill.

To your knowledge, there was no substantial excavation of soils in audit area 6A?---Not substantial excavation of soil in area 6A, no, to my knowledge.

See Transcript 22.02.2021, at T1264 (Whincup XXN).

When reading the orders, particularly Schedule 1 in the context [sic] Clause 11.5 c) of the contract, it is apparent that Question 6 needs to be answered in the context of the 8 Unidentified Contamination Notices that are in dispute and not what the actual remediation works should or could costs.

Therefore, my report was based on what was known at the time each notice was issued and not what was known after all works were completed.  My opinions in regard to Question 6 were therefore based on assessment of the scope of works and costs estimate with information apparent at the time of the notice and not using a benefit of hindsight approach.  I believe that my approach was in line with the intent of the orders, particularly when reading Question 6 in the context of the first sentence of Schedule 1.

1.1Key activities Completed for the Reporting Period

The following works were undertaken by the project team over the past month:

. . .

Contract Sum Negotiation

·Demolition Contract has been executed by Delta and countersigned.

·Demolition Contract Sum is $6,378,946 with a pricing option of $162,000 to demolish the 1954 Boiler House and East-West run of the Coal Conveyor.  This option has not yet been instructed.

. . .

3.0Contract Administration:

3.1Contract

Contract executed and returned to Delta.

Bank Guarantees received, yet provided with incorrect address.  Delta to amend and resubmit.

Actions
Download as PDF Download as Word Document


Cases Citing This Decision

2

Priolo v Nguyen [No 3] [2024] WASC 47
Cases Cited

4

Statutory Material Cited

40

Amaca v CSR (No 2) [2015] VSC 605