| IN THE SUPREME COURT OF VICTORIA | Not Restricted |
AT MELBOURNE
COMMERCIAL COURT
COMMERCIAL LIST
S ECI 2017 00145
| ALPHINGTON DEVELOPMENTS PTY LTD (ACN 164 529 864) | Plaintiff/Defendant by Counterclaim |
| v | |
| AMCOR PTY LTD (ACN 000 017 372) | Defendant/Plaintiff by Counterclaim |
---
JUDGE: | Sloss J |
WHERE HELD: | Melbourne |
DATE OF HEARING: | 2-5, 12, 16-19 March 2020 (Trial adjourned at parties’ request due to COVID-19 lockdown); (2021 Trial resumed) 2-4, 8-11, 15-17, 22-25 February, 1‑4, 9‑12, 15, 16 March, 12-15 April, 17, 18 May, 27 July 2021 |
DATE OF JUDGMENT: | 1 November 2023 |
CASE MAY BE CITED AS: | Alphington Developments Pty Ltd v Amcor Pty Ltd (No 5) |
MEDIUM NEUTRAL CITATION: | [2023] VSC 637 |
---
CONTRACT — Construction and interpretation — Notices — Contract provided for purchaser to recover costs from vendor for certain works undertaken at the land following issuance of a ‘UC’ notice addressing specified criteria — Valid ‘UC’ notice was a precursor to recovery of costs — Whether ‘UC’ notices issued were valid — Whether ‘UC’ notices satisfied criteria required to be addressed under the contract — Consideration of commercial purpose of ‘UC’ notices under the contract.
CONTRACT — Construction and interpretation — Contract provided for expert dispute resolution procedure in relation to objections to ‘UC’ notices — Parties subsequently amended contract by deleting dispute resolution procedure and requiring that the Court resolve questions relating to ‘UC’ notices in place of an expert — Role of the Court in resolving issues in respect of relevant ‘UC’ notices.
CONTRACT — Construction and interpretation — Breach of contract — Payment claims — Loss and damage — Alleged failure to pay costs properly and reasonably incurred in performance of works under contract — Entitlement to payment of outstanding claims — Contract embodied procedure for certification of invoices by approved quantity surveyor appointed by the parties — Whether items sought to be recovered as ‘Remediation Works’ ought to have been classified as other works — Whether plaintiff failed to prove amounts claimed were costs for ‘Remediation Works’ — Whether certifications by approved quantity surveyor conformed with contractual requirements.
CONTRACT — Breach of contract — Performance of contract — Compliance with contractual obligations — Whether plaintiff failed to use reasonable endeavours to minimise costs — Reasonable endeavours — Properly and reasonably incurred— Whether plaintiff procured works to be carried out cost effectively and to a reasonable commercial standard — Whether plaintiff disentitled from recovering its costs — Whether plaintiff’s approach to remediation was ad hoc and reactive — Whether plaintiff failed to devise comprehensive remediation strategy — Whether necessary to excavate all soil containing asbestos to remediate risks to human health and the environment — Whether capping solution should have been implemented — Whether plaintiff failed to competitively tender for works to be performed— Whether plaintiff failed to properly manage stockpiles — Whether plaintiff was required to consider any, and if so what, changes to the Master Plan.
CONTRACT — Failure of contractual mechanism — Contract provided for purchaser to recover costs from vendor…
Keep reading for free
Create a free CaseChat account to read Alphington Developments Pty Ltd v Amcor Pty Ltd (No 5) and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2023] VSC 637
- Decision Date
CaseChat Overview and Summary
The court found that the ‘UC’ notices were not valid as they did not satisfy the criteria required under the contract. The court held that the notices did not address the specified criteria and therefore were not a valid precursor to the recovery of costs. The court also held that the certification by the approved quantity surveyor was an essential and indispensable part of the contractual bargain and that the failure of this mechanism required the court to create a substitute mechanism to allow the purchaser to recover costs. Furthermore, the court found that the plaintiff had failed to use reasonable endeavours to minimise costs and had not competitively tendered for the works to be performed, disentitling it from recovering its costs.
The court held that the plaintiff was not entitled to recover the costs of remediating unidentified contamination in the Riparian Zone, as the Riparian Zone was encompassed within the Master Plan but no ‘use’ was specified. The court also found that the plaintiff was not entitled to recover costs of works to demolish structures not identified for demolition in the Delta Contract. Finally, the court found that the defendant was not liable for the costs of remediating unidentified contamination beneath a structure not expected to be demolished. The court also considered the defendant’s counterclaim for interest, finding that the plaintiff had defaulted in payment of money and that penalty interest should be calculated on a compounding basis.
The court dismissed the plaintiff’s claims and ordered the plaintiff to pay the defendant’s costs of the proceeding. The court also ordered that the defendant’s counterclaim for interest be referred to a Master to determine the amount of interest due. The court made no orders as to costs on the counterclaim.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.