District Court
New South Wales
- Amendment notes
Medium Neutral Citation: Allianz Australia Insurance Limited v Dinov [2016] NSWDC 342 Hearing dates: 23 November 2016 Date of orders: 05 December 2016 Decision date: 05 December 2016 Jurisdiction: Civil Before: Dicker SC DCJ Decision: (1) Judgment for the plaintiff against each of the defendants in the amount of $185,000;
(2) The defendants are to pay the plaintiff’s costs of the proceedings as agreed or assessed;
(3) Liberty to the parties to apply to vary order (2) above, on giving three business days’ notice.Catchwords: Deed of Indemnity – whether action in damages for breach of Deed was prohibited by statute – statutory construction principles - words and phrases – “loss or damage arising out of or concerning defective building work” – purpose and object of provision – mischief sought to be overcome by provision – held action not prohibited Legislation Cited: Building Act 1993 (Vic)
Environmental Planning and Assessment Act 1979 (NSW)
Environmental Planning and Assessment Amendment Act 1997 (NSW)
Home Building Act 1989 (NSW)
Interpretation Act 1987 (NSW)Cases Cited: AQO v Minister for Finance and Services [2016] NSWCA 248
Australian Rail Track Corp Ltd v Leighton Contractors Pty Ltd [2003] VSC 189
Brirek Industries Pty Ltd v McKenzie Group Consulting (Vic) Pty Ltd [2014] VSCA 165
Bryan v Maloney (1994) 182 CLR 609
Inter-Continental Travels Pty Ltd v Heuppauff [2000] SASC 7
Project Blue Sky Inc v Australian Broadcasting Authority (1998) 194 CLR 355; [1998] HCA 28
Wardley Australia Ltd v State of Western Australia (1992) 175 CLR 514Category: Principal judgment Parties: Allianz Australia Insurance Limited (Plaintiff)
Dino Dinov (First Defendant)
Stefan Dinov (Second Defendant)
Jona Dinov (Third Defendant)
Jugoslav Zivanovic (Fourth Defendant)
Veselka Zivanovic (Fifth Defendant)
Natasha Zivanovic (Sixth Defendant)Representation: Counsel:
Solicitors:
T Lynch SC (Plaintiff)
P J Bambagiotti (Defendants)
Mills Oakley (Plaintiff)
Stanton Legal (Defendants)
File Number(s): 2015/00251386
Judgment
-
This is a claim by the plaintiff, Allianz Australia Insurance Ltd (‘Allianz”), against six defendants who signed Deeds Poll (“Deeds”) providing indemnities to the plaintiff, for damages for breach of the indemnity obligations in the Deeds.
Amended Statement of Claim
-
The plaintiff relies on an Amended Statement of Claim filed on 4 March 2016. In essence, the plaintiff pleads that each of the defendants provided in the Deeds an indemnity to the plaintiff, and, as a result, the plaintiff provided residential building work insurance to Great Wall Constructions Pty Ltd (“Great Wall”), a builder, which built 13 residential townhouses at 68-70 White Street, Lilyfield in Sydney in New South Wales.
-
Defects were claimed in the building work by the successor in title to the original owner in July 2009. It is alleged that on or about 17 November 2010, Great Wall deregistered and ceased to be a legal entity. The successor in title then claimed against the plaintiff as the residential building work insurer. The plaintiff accepted certain of the defects alleged and entered into terms of settlement with the owner for a third party builder…
Keep reading for free
Create a free CaseChat account to read Allianz Australia Insurance Limited v Dinov and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2016] NSWDC 342
- Decision Date
CaseChat Overview and Summary
The court found that the purpose of section 58 of the Act was to provide a statutory cause of action for defects in building work but did not intend to preclude common law claims for damages arising from contractual obligations such as the indemnity deed. The court applied principles of statutory construction, examining the purpose and object of the statutory provision, and the mischief it sought to address. The court concluded that the statutory language was not intended to cover contractual indemnity claims and therefore Allianz’s action was not prohibited by the statute. The court held that Allianz was entitled to seek damages under the indemnity deed as it was not precluded by section 58 of the Act.
In light of the above, the court awarded judgment to Allianz in the amount of $185,000 against each defendant. The defendants were ordered to pay Allianz’s costs of the proceedings as agreed or assessed. The court also granted liberty to the parties to apply to vary the costs order, provided they gave three business days’ notice.
Orders
Orders of the court
(1) Judgment for the plaintiff against each of the defendants in the amount of $185,000;
(2) The defendants are to pay the plaintiff’s costs of the proceedings as agreed or assessed;
(3) Liberty to the parties to apply to vary order (2) above, on giving three business days’ notice.
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi