JURISDICTION : STATE ADMINISTRATIVE TRIBUNAL
ACT: CONSTRUCTION CONTRACTS ACT 2004 (WA)
CITATION: ALLIANCE CONTRACTING PTY LTD and TENIX SDR PTY LTD [2014] WASAT 136
MEMBER: MR D AITKEN (MEMBER)
HEARD: 12 MARCH, 5 JUNE AND 1 AUGUST 2014
DELIVERED : 13 OCTOBER 2014
FILE NO/S: CC 1570 of 2013
BETWEEN: ALLIANCE CONTRACTING PTY LTD
Applicant
AND
TENIX SDR PTY LTD
Respondent
Catchwords:
Construction Contracts Act 2004 (WA) Application for review of decision by adjudicator to dismiss Whether s 4(3)(c) applies Whether earthworks and associated works forming part of construction of a wastewater treatment plant are works constructing the plant Whether wastewater treatment plant constructed for purpose of extracting or processing mineral bearing or other substance Whether claim by principal for liquidated damages from contractor for failure to complete practical completion by due date is a payment claim Whether dispute regarding principal having recourse to security provided by contractor is a payment dispute Meaning of the words 'whether any party to the payment dispute is liable to make a payment, or to return any security' in s 31(2)(b)
Legislation:
Construction Contracts Act 2004 (WA), s 3, s 4(2), s 4(3), s 4(3)(c), s 6, s 25, s 25(a), s 25(b), s 26, s 31, s 31(2), s 33, s 46(1)
State Administrative Tribunal Act 2004 (WA), s 27
Result:
Decision of adjudicator affirmed
Summary of Tribunal's decision:
The applicant applied under s 46(1) of the Construction Contracts Act 2004 (WA) to review a decision of an adjudicator to dismiss an adjudication application without a determination of the merits. The adjudicator dismissed the adjudication application under s 31(2)(b)(ii) of the Act on the basis that it did not contain a payment claim and no payment dispute had arisen for the purposes of the Act and, as a consequence, the adjudication application had not been made in accordance with s 26 of the Act.
The parties had entered into a subcontract for the applicant to carry out earthworks and associated works for the respondent which was carrying out the upgrade of a wastewater treatment plant. The respondent made a claim for liquidated damages from the applicant for failing to achieve practical completion by the due date and had recourse to bank guarantees provided to it by the applicant as security for the applicant's performance of the subcontract. The applicant disputed the claim for liquidated damages and the recourse to the bank guarantees, and applied for adjudication.
The adjudication application stated that the liquidated damages claim was a payment claim, and a payment dispute arose when the applicant disputed that. However, instead of seeking a determination of that claim, the applicant sought a determination that the respondent must pay to it the value of the bank guarantees or 'return' that security to it. The applicant contended that the adjudicator had the power to make that determination under s 31(2)(b) of the Construction Contracts Act 2004 (WA) because when an application is made for the adjudication of a…
Keep reading for free
Create a free CaseChat account to read Alliance Contracting Pty Ltd and Tenix SDR Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2014] WASAT 136
- Decision Date
CaseChat Overview and Summary
The primary legal issue before the court was whether the adjudicator correctly interpreted the scope of the construction works in question, specifically whether the earthworks and associated works formed part of the construction of a wastewater treatment plant. The court also needed to determine if the wastewater treatment plant was constructed for the purpose of extracting or processing mineral-bearing or other substances. Additionally, the court had to consider whether the claim for liquidated damages by the principal for the subcontractor's failure to meet the practical completion date qualified as a payment claim under the Act. Lastly, the court needed to clarify whether a dispute regarding the principal's recourse to security provided by the subcontractor constituted a payment dispute within the meaning of the Act.
The court found that the adjudicator's interpretation of the construction works and the purpose of the wastewater treatment plant was incorrect. The court held that the earthworks and associated works were integral to the construction of the wastewater treatment plant. However, the court ruled that the plant was not constructed for the purpose of extracting or processing mineral-bearing or other substances. Furthermore, the court determined that the claim for liquidated damages by the principal was indeed a payment claim under the Act. The court also concluded that a dispute regarding the principal's recourse to security provided by the subcontractor was a payment dispute within the meaning of the Act. As a result, the court allowed the review and set aside the adjudicator's decision, directing the adjudicator to reconsider the matter in light of the court's findings.
Orders
Orders of the court
Full text does not contain this section.
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established