Allencon Pty Ltd v Palmgrove Holdings Pty Ltd

Link copied
Case Copied 17 min read

DISTRICT COURT OF QUEENSLAND

CITATION:

Allencon Pty Ltd v Palmgrove Holdings Pty Ltd [2022] QDC 90

PARTIES:

ALLENCON PTY LTD

(Applicant/Plaintiff)

v

PALMGROVE HOLDINGS PTY LTD

(Respondent/Defendant)

FILE NO:

356/22

DIVISION:

Civil

PROCEEDING:

Application

ORIGINATING COURT:

District Court of Queensland

DELIVERED ON:

6 May 202

DELIVERED AT:

Brisbane

HEARING DATE:

10 March 2022

JUDGE:

Burnett DCJ

ORDER:

1.        Application dismissed.

2.        In default of application for other orders being made within 14 days the applicant pay the respondent’s costs of and incidental to the application to be assessed on the standard basis, such costs to be the respondent’s costs in the cause in any event.

CATCHWORDS:

CONTRACTS – BUILDING AND CONSTRUCTION CONTRACTS – PAYMENT SCHEDULES – whether a payment certificate was issued out of time – where a building contract defined ‘day’ as ‘calendar day’ rather than ‘business day’ as defined in the relevant act – effect of contractual provision rendering timeframe less favourable than allowed for by relevant act

CONTRACTS – GENERAL CONTRACTUAL PRINCIPLES – CONSTRUCTION AND INTERPRETATION OF CONTRACTS – where relevant legislation proscribes contracting-out of the provisions of the act

LEGISLATION:

Building Industry Fairness (Security of Payments) Act 2017 (Qld)

Building and Construction Industry Payments Act 2004 (Qld)

CASES:

Daysea Pty Ltd v Watpac Australia Pty Ltd [2001] QCA 49
Tailored Projects Pty Ltd v Jedfire Pty Ltd [2009] 2 Qd R 171
Thiess Pty Ltd v Lane Cove Tunnel Nominee Co Pty Ltd [2008] NSWSC 79

COUNSEL:

B. Vass for the applicant

L. M. Campbell for the respondent

SOLICITORS:

Piper Alderman for the applicant

Batch Mewing Lawyers for the respondent

Background

  1. Allencon Pty Ltd (‘Allencon’), the applicant/plaintiff, as subcontractor under contract seeks orders for summary judgment based upon an unanswered claim for payment issued by it to Palmgrove Holdings Pty Ltd (trading as Carruthers Contractors) (‘Carruthers’), the respondent/defendant, as main contractor under contract. Carruthers made a part payment and issued a payment certificate in response to Allencon’s claim for payment but Allencon contend it was issued out of time and in default it is entitled to recover the full amount claimed in its claim.

Triable Issue

  1. In my view there is plainly a triable issue concerning the subject matter of the claim for payment which cannot be resolved in a summary fashion. That dispute will be resolved in accordance with the contractual provisions consistent with s 101 of the Building Industry Fairness (Security of Payment) Act 2017 (Qld) (‘BIFA’).

  2. However, Allencon claims for summary judgment for the unpaid portion of the claim for payment delivered by it upon Carruthers, which was not subject to response. It contends its entitlement is founded in the statutory regime provided by BIFA. 

  3. There is no dispute that Allencon delivered a claim for payment described as “Progress Claim – Dec 2011/Practical Completion”[1] and that in response to that payment claim, Carruthers delivered a payment certificate described as “Progress Certificate No. 7”.  The contest in this instance revolves about the timing of Carruthers’ payment certificate and in turn which…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Allencon Pty Ltd v Palmgrove Holdings Pty Ltd and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2022] QDC 90
Decision Date

CaseChat Overview and Summary

The case of Allencon Pty Ltd v Palmgrove Holdings Pty Ltd was heard by the Supreme Court of Queensland. The dispute centered around the interpretation of a payment schedule within a building contract and whether a payment certificate was issued out of time. Allencon Pty Ltd, the applicant, sought a declaration that a payment certificate issued by Palmgrove Holdings Pty Ltd, the respondent, was not valid because it was issued beyond the prescribed timeframe. The contract in question defined 'day' as 'calendar day', which conflicted with the definition of 'business day' provided in the Building and Construction Industry Payments Act 2004 (Qld). The key legal issue before the court was whether the contractual provision, which rendered the timeframe less favourable than that allowed by the act, was valid.

The court held that the contractual definition of 'day' as 'calendar day' was effective in reducing the timeframe within which a payment certificate must be issued, despite the act's proscription against contracting out of its provisions. The court found that the act did not expressly prohibit the contracting out of the definition of 'day', and therefore, the contractual term was valid. The court also noted that the contract was not unconscionable, and both parties were represented by legal counsel at the time of contracting. As a result, the applicant's application was dismissed.

In light of the dismissal, the court ordered that if the applicant did not apply for other orders within 14 days, it would be required to pay the respondent's costs of and incidental to the application, to be assessed on the standard basis. These costs would also become the respondent's costs in the cause in any event. This outcome underscores the importance of carefully reviewing contractual definitions and ensuring they align with statutory requirements, particularly in regulated industries such as construction.

Orders

Orders of the court

1. Application dismissed.

2. In default of application for other orders being made within 14 days the applicant pay the respondent’s costs of and incidental to the application to be assessed on the standard basis, such costs to be the respondent’s costs in the cause in any event.