DISTRICT COURT OF QUEENSLAND
CITATION:
Allencon Pty Ltd v Palmgrove Holdings Pty Ltd [2022] QDC 90
PARTIES:
ALLENCON PTY LTD
(Applicant/Plaintiff)
v
PALMGROVE HOLDINGS PTY LTD
(Respondent/Defendant)
FILE NO: 356/22
DIVISION:
Civil
PROCEEDING:
Application
ORIGINATING COURT:
District Court of Queensland
DELIVERED ON:
6 May 202
DELIVERED AT:
Brisbane
HEARING DATE:
10 March 2022
JUDGE:
Burnett DCJ
ORDER:
1. Application dismissed.
2. In default of application for other orders being made within 14 days the applicant pay the respondent’s costs of and incidental to the application to be assessed on the standard basis, such costs to be the respondent’s costs in the cause in any event.
CATCHWORDS:
CONTRACTS – BUILDING AND CONSTRUCTION CONTRACTS – PAYMENT SCHEDULES – whether a payment certificate was issued out of time – where a building contract defined ‘day’ as ‘calendar day’ rather than ‘business day’ as defined in the relevant act – effect of contractual provision rendering timeframe less favourable than allowed for by relevant act
CONTRACTS – GENERAL CONTRACTUAL PRINCIPLES – CONSTRUCTION AND INTERPRETATION OF CONTRACTS – where relevant legislation proscribes contracting-out of the provisions of the act
LEGISLATION:
Building Industry Fairness (Security of Payments) Act 2017 (Qld)
CASES:
Daysea Pty Ltd v Watpac Australia Pty Ltd [2001] QCA 49
Tailored Projects Pty Ltd v Jedfire Pty Ltd [2009] 2 Qd R 171
Thiess Pty Ltd v Lane Cove Tunnel Nominee Co Pty Ltd [2008] NSWSC 79COUNSEL: B. Vass for the applicant
L. M. Campbell for the respondent
SOLICITORS: Piper Alderman for the applicant
Batch Mewing Lawyers for the respondent
Background
Allencon Pty Ltd (‘Allencon’), the applicant/plaintiff, as subcontractor under contract seeks orders for summary judgment based upon an unanswered claim for payment issued by it to Palmgrove Holdings Pty Ltd (trading as Carruthers Contractors) (‘Carruthers’), the respondent/defendant, as main contractor under contract. Carruthers made a part payment and issued a payment certificate in response to Allencon’s claim for payment but Allencon contend it was issued out of time and in default it is entitled to recover the full amount claimed in its claim.
Triable Issue
In my view there is plainly a triable issue concerning the subject matter of the claim for payment which cannot be resolved in a summary fashion. That dispute will be resolved in accordance with the contractual provisions consistent with s 101 of the Building Industry Fairness (Security of Payment) Act 2017 (Qld) (‘BIFA’).
However, Allencon claims for summary judgment for the unpaid portion of the claim for payment delivered by it upon Carruthers, which was not subject to response. It contends its entitlement is founded in the statutory regime provided by BIFA.
There is no dispute that Allencon delivered a claim for payment described as “Progress Claim – Dec 2011/Practical Completion”[1] and that in response to that payment claim, Carruthers delivered a payment certificate described as “Progress Certificate No. 7”. The contest in this instance revolves about the timing of Carruthers’ payment certificate and in turn which…
Keep reading for free
Create a free CaseChat account to read Allencon Pty Ltd v Palmgrove Holdings Pty Ltd and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2022] QDC 90
- Decision Date
CaseChat Overview and Summary
The court held that the contractual definition of 'day' as 'calendar day' was effective in reducing the timeframe within which a payment certificate must be issued, despite the act's proscription against contracting out of its provisions. The court found that the act did not expressly prohibit the contracting out of the definition of 'day', and therefore, the contractual term was valid. The court also noted that the contract was not unconscionable, and both parties were represented by legal counsel at the time of contracting. As a result, the applicant's application was dismissed.
In light of the dismissal, the court ordered that if the applicant did not apply for other orders within 14 days, it would be required to pay the respondent's costs of and incidental to the application, to be assessed on the standard basis. These costs would also become the respondent's costs in the cause in any event. This outcome underscores the importance of carefully reviewing contractual definitions and ensuring they align with statutory requirements, particularly in regulated industries such as construction.
Orders
Orders of the court
1. Application dismissed.
2. In default of application for other orders being made within 14 days the applicant pay the respondent’s costs of and incidental to the application to be assessed on the standard basis, such costs to be the respondent’s costs in the cause in any event.