Allen v Queensland Building and Construction Commission

Case [2019] QCAT 20


QUEENSLAND CIVIL AND ADMINISTRATIVE TRIBUNAL

CITATION: Allen & Anor v Queensland Building and Construction Commission [2019] QCAT 20
PARTIES:

REECE JUSTIN ALLEN

(first applicant)

CHANTELL RENEE MARIA TAYLOR

(second applicant)

v

QUEENSLAND BUILDING AND CONSTRUCTION COMMISSION

(respondent)

APPLICATION NO/S: GAR136-18
MATTER TYPE: General administrative review matters
DELIVERED ON: 17 January 2019
HEARING DATE: On the papers
HEARD AT: Brisbane
DECISION OF: Member Cranwell
ORDERS: The application for miscellaneous matters filed on 29 November 2018 is dismissed.

CATCHWORDS:

PROCEDURE – CIVIL PROCEEDINGS IN STATE AND TERRITORY COURTS – JOINDER OF CAUSES OF   ACTION   AND   OF   PARTIES   –   PARTIES   –

GENERALLY – where excessive delay in seeking joinder

Queensland Building and Construction Commission Act 1991 (Qld), s 71

Queensland Civil and Administrative Tribunal Act 2009

(Qld), s 21, s 42

REPRESENTATION:
Applicant: Project Legal
Respondent: Self-represented
APPEARANCES:

This matter was heard and determined on the papers pursuant to s 32 of the

Queensland Civil and Administrative Tribunal Act 2009 (Qld).

2

REASONS FOR DECISION

  1. On 19 March 2018, the Queensland Building and Construction Commission (QBCC) decided to decline a claim by Mr Allen and Ms Taylor under the statutory insurance scheme.

  2. On 11 April 2018, Mr Allen and Ms Taylor filed an application to review that decision in the Tribunal.

  3. Directions were subsequently made in relation to the conduct of the proceedings. The QBCC filed documents pursuant to s 21(2) of the Queensland Civil and Administrative Tribunal Act 2009 (Qld) (QCAT Act) on 5 July 2018. Mr Allen and Ms Taylor filed voluminous statements on 4 September 2018 and 19 October 2018. A compulsory conference was held on 20 September 2018. The QBCC had been directed to file any further statements of evidence in reply by 16 November 2018, but none had been filed. The matter was listed for a directions hearing before me on 29 November 2018. The matter appeared for all intents and purposes ready to be listed for hearing.

  4. On 29 November 2018, the QBCC lodged an application to join Contrast Constructions Pty Ltd (Contrast Constructions) as a respondent to the proceedings. The joinder application was made on the basis that the interests of Contrast Constructions may be affected by the proceeding pursuant to s 42(1)(b) of the QCAT Act. This is undoubtedly the case because if Mr Allen and Ms Taylor are successful, the QBCC may recover any payment under the statutory insurance scheme from Contrast Constructions pursuant to s 71(1) of the Queensland Building and Construction Act 1991 (Qld).

  5. However, the joinder of parties is a discretionary matter. The fact that the interests of Contrast Constructions may be affected by the proceedings should have been apparent from 11 April 2018, when the proceeding was first commenced. The very nature of the decision under review should have alerted the QBCC to that possibility from the outset. Rather than make an application for joinder in a timely fashion, the QBCC decided to wait until the proceedings were apparently ready to be listed for hearing before making the application. No explanation was provided for this delay.

  6. Mr Allen and Ms Taylor have expended considerable effort and no doubt cost in preparing their material. They should not be forced to incur additional costs and delays as a result of the excessive and unexplained delay by the QBCC relating to the joinder application.

  7. I dismiss the joinder application.

Details
AGLC
Allen v Queensland Building and Construction Commission [2019] QCAT 20
Case
[2019] QCAT 20
Decision Date

CaseChat Overview and Summary

In the matter of Allen v Queensland Building and Construction Commission, the dispute involved the joinder of a cause of action and additional parties in an ongoing legal action. The case was heard in the Queensland Court of Appeal. The primary issue before the court was whether the applicant had demonstrated sufficient grounds to permit the joinder of the cause of action and additional parties, particularly considering the substantial delay in seeking to do so. The court had to consider whether the delay was excessive and whether it would cause substantial prejudice to the respondents.

The court examined the principles guiding the joinder of causes of action and parties, emphasising the need for fairness and the absence of undue delay. It noted that while the law provides for the joinder of related claims and parties, such joinder is not an absolute right and can be refused if it results in substantial prejudice or if there has been an unreasonable delay. The court scrutinised the applicant's reasons for the delay and the potential impact on the respondents if the joinder were to proceed. Ultimately, the court concluded that the delay was excessive and would prejudice the respondents, leading to the dismissal of the application for joinder.

Given these considerations, the Queensland Court of Appeal dismissed the application for miscellaneous matters filed on 29 November 2018. The court found that the excessive delay and potential prejudice to the respondents outweighed the merits of allowing the joinder of the additional cause of action and parties. This decision reinforces the importance of timely applications and the potential consequences of significant delays in legal proceedings.

Orders

Orders of the court

The application for miscellaneous matters filed on 29 November 2018 is dismissed.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

Full text does not contain this section.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.