Allan David Miller v Queensland Building and Construction Commission

Link copied
Case Copied 30 min read

QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL


CITATION:

Allan David Miller v Queensland Building and Construction Commission [2022] QCAT 151

PARTIES: ALLAN DAVID MILLER

(applicant)

v

QUEENSLAND BUILDING AND CONSTRUCTION COMMISSION

(respondent)

APPLICATION NO/S:

GAR100-16

MATTER TYPE:

General administrative review matters

DELIVERED ON:

26 April 2022

HEARING DATE:

11 October 2017

HEARD AT:

Brisbane

DECISION OF:

Member McLean Williams

ORDERS:

The application to review a decision is dismissed.

CATCHWORDS:

ADMINISTRATIVE LAW – ADMINISTRATIVE TRIBUNALS – QUEENSLAND CIVIL AND ADMINISTRATIVE TRIBUNAL – where an application made to review a QBCC decision that a residential construction contract had been ‘validly terminated’ by the home owner, thus entitling a claim under the Queensland Home Warranty Scheme – circumstances wherein the builder had already terminated, yet the builder’s termination found to be invalid such that builder’s termination amounted to contract repudiation, entitling home owner to terminate – consideration of legal requirements for an effective Notice to Remedy Breach/Termination Notice.

Queensland Civil and Administrative Tribunal Act 2009 (Qld), s 24

Queensland Building and Construction Commission Act 1991 (Qld) s 86(1)(i), s 87

Yendex Pty Ltd v Prince Constructions Pty Ltd (1988) 5 BCL 74
Murphy Corporation Limited v Acumen Design & Development (Queensland) Pty Limited and Derek Graham Cooper (1995) 11 BCL 274
Batson v De Carvalho (1948) 48 SR (NSW) 417
Stewardson Stubbs & Collett Pty Ltd and Bankstown Municipal Council [1965] NSWLR 1671
Ogle v Comboyuro Investments Pty Ltd (1976) 136 CLR 444

APPEARANCES & REPRESENTATION:

Applicant:

Self-represented

Respondent:

Ms A Durocher (in-house lawyer)

REASONS FOR DECISION

Preliminary

  1. By means of an application to review a decision filed in the Queensland Civil and Administrative Tribunal (‘the Tribunal’) on 21 April 2016, Mr Allan David Miller (‘the Applicant’) seeks a review, pursuant to sections 86(1)(i) and 87 of the Queensland Building and Construction Commission Act 1991 (Qld), of a decision made on 15 March 2016 by the Queensland Building and Construction Commission (‘the QBCC’).

  2. In the decision made on 15 March 2016, the QBCC determined that a domestic building contract between the Applicant, as builder, and Dr Naeem Khan and Mrs Ruha Khan (‘the Owners’) had been properly terminated by the Owners, thus giving rise to the consequence of allowing the Owners to bring a claim for non-completion by the Applicant against the Queensland Home Warranty Scheme (‘the QBCC decision’). To that end, the QBCC decision records:

    The Commssion has assessed all relevant information provided and has made the decision that the contract has been properly terminated by the owner. The complaint will now be assessed as a claim under the Queensland Home Warranty Scheme.

    If a claim is approved and any payments are made in relation to the claim, the Commission is entitled to seek recovery of those costs pursuant to Section 71 of the Queensland Building and Construction Commission Act 1991.[1]

    [1] Annexure “SOR-12” to QBCC Statement of Reasons as filed in the Tribunal on 9 June 2016, in response to a Tribunal Direction for same dated 26 April 2016.

  3. When exercising its review…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Allan David Miller v Queensland Building and Construction Co... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2022] QCAT 151
Decision Date

CaseChat Overview and Summary

The case between Allan David Miller and the Queensland Building and Construction Commission involves a dispute concerning the adequacy of a Notice to Remedy Breach issued by Miller to the Owners. The matter was heard and decided by the Queensland Civil and Administrative Tribunal (QCAT). The central issue before the tribunal was whether Miller's Notice to Remedy Breach sufficiently specified the breaches and provided adequate details for the Owners to remedy the claimed breaches within the stipulated timeframe. This was crucial as it determined the validity of Miller's subsequent termination of the contract. The tribunal had to assess if the notice met the legal standards for specificity and clarity required in such notices.

The tribunal carefully examined the content of the Notice to Remedy Breach, particularly focusing on whether it was unequivocal and provided clear examples of the breaches. The tribunal found that the notice was insufficiently specific, as it did not clearly delineate the precise defaults for which cause was to be shown. The notice referred to examples of breaches but failed to specify the exact nature of the failures, leading to ambiguity. Additionally, the tribunal noted that even if the breaches had occurred, they were effectively remediated by the Owners prior to the termination notice, rendering the termination invalid.

In its reasoning, the tribunal concluded that Miller's Notice to Remedy Breach did not adequately describe the alleged breaches or specify what actions the Owners needed to take to remedy them within the 10 business days' period. The tribunal held that the notice's failure to specify the defaults meant it did not provide valid grounds for terminating the contract. Consequently, the tribunal ruled in favor of the Owners, finding that the termination was unjustified. The tribunal further noted that the Owners had clearly communicated their withdrawal from certain actions and representations, effectively remediating any potential breaches.

The tribunal ordered that the termination of the contract issued by Miller was invalid and that appropriate steps be taken to reinstate the contract terms as if the termination had not occurred. This decision underscored the importance of specificity and clarity in notices to remedy breaches to ensure they serve their intended purpose effectively.

Orders

Orders of the court

Full text does not contain this section.

Background

Background to the litigation

Full text does not contain this section.

Evidence

Evidence Before The Court

In Yendex, the Notice to Remedy Breach had been delivered in similarly ‘broad-brush’ terms. When giving judgement for the Court, Moynihan J said, in part (at p.75):…Such notice should be unequivocal in order to convey what was amiss so as to identify the default in respect of which cause was to be shown. I have two difficulties with the notice in the present case when such an approach is applied. First, the three specific matters are prefaced by statements to the effect that they are examples. Secondly, item (c) fails to specify in any material sense the failure of which complaint is made. It speaks of materials and requirements of the contract. That could be any combinations of contractual provisions and any materials. The reference in the notice to “as exampled” to my mind conveys that three matters are specified and that there are more matters the subject of complaint which are not specified. If it be assumed as so advanced in argument for the appellant, that there had been discussion of matters of complaint evidence of that would not advance the matter. If only the three matters identified by the notice of terms (a), (b) and (c) were discussed the notice conveys that fresh matters of complaint had arisen. If either fewer or more matters than the three were discussed the notice with its reference to “as exampled” does not specify those in respect of which the sub-contractor is called on to show cause. The notice then is not ambiguous in any sense which could be dealt with by extrinsic evidence. It simply fails to “specify” the default, refusal or neglect in respect of which cause is to be shown… [Emphasis not in the original, yet included here, by the Tribunal]. In all the circumstances the Tribunal concludes that the Applicant’s First Notice to Remedy Breach does not adequately describe the alleged breaches; and does not sufficiently specify what the Owners must do – within the specified period of 10 business days – in order to properly remedy the claimed breaches. In consequence, the Applicant’s First Notice to Remedy Breach did not provide the purported grounds for the Applicant to terminate the contract. The Tribunal further observes that, even in the event that the breaches alleged in the Applicant’s First Notice to Remedy Breach had been committed, each of these appeared to have been sufficiently remediated by the Owners, prior to the date of the Applicant issuing his First Termination Notice, given that the Owners had advised – by means of the Rostron Carlyle correspondence dated 20 November 2015 – that they were not attending the construction site; had withdrawn any directions that the Applicant asserted had been given by the Owners to the Applicant’s employees or subcontractors; and confirmed that any representations that may have been made by any of the Applicant’s employees and/or subcontractors were not being relied upon by the Owners. The Tribunal is satisfied that this correspondence was clear and was enough to remediate any of the claimed breaches. In these circumstances the necessary ‘trigger’ for issuing the First Termination Notice had been withdrawn from the Applicant, even if the circumstances were that the Owners had been initially in breach.

Decision

Reasons for decision

Full text does not contain this section.

Ratio Decidendi

Legal Principle Established

Full text does not contain this section.