Aleksander Gvozdenovic and Audrey Gvozdenovic v Greig Sparling

Link copied
Case Copied 28 min read

Civil and Administrative Tribunal


New South Wales

Medium Neutral Citation: Aleksander Gvozdenovic and Audrey Gvozdenovic v Greig Sparling [2015] NSWCATCD 33
Hearing dates:19 December 2014
Decision date: 06 March 2015
Jurisdiction:Consumer and Commercial Division
Before: G.J. Sarginson, General Member
Decision:

The application is dismissed.

Catchwords: Jurisdiction;
Residential building work;
Date of practical completion;
Limitation period
Legislation Cited: Home Building Act 1989 ss 3B; 18B; 18E; 48K
Home Building Amendment Act 2011
Civil and Administrative Tribunal Act 2013 s 37
Limitation Act 1969
Cases Cited: Myers v Vero Insurance Ltd [2009] NSWCTTT 698
Owners Corporation SP 53127 v Fair Trading Administration Corporation [2005] NSWCTTT
Kizas v Lawteal Pty Ltd [2010] NSWCTTT 257
Griffiths v Gates [2013] NSWCTTT 302
The Owners Strata Plan No 78670 v Cavill Properties Pty Ltd
The Owners Strata Plan No 78670 v Cavill Properties Pty Ltd
Reeda Investments Pty Ltd v Tooma [2013] NSWCTTT 445
Atkinson v Crowley [2011] NSWCA 194
Owners SP 69050 v Glenzeil Pty Ltd [2013] NSWCTTT 17
Category:Principal judgment
Parties: Aleksander Gvozdenovic and Audrey Gvozdenovic (applicants)
Greig Sparling (respondent)
Representation: Parties: Aleksander Gvozdenovic (applicant)
Grieg Sparling (respondent)
File Number(s):HB 14/44893
Publication restriction:Nil

reasons for decision

  1. The Applicant filed proceedings against the Respondent in the Tribunal on 5 September 2014.

  2. The Applicant is the owner of residential premises in Bellevue Hill NSW. The Respondent is a licenced builder. The Applicant alleges that in 2006 the parties entered into a contract for the Respondent to perform residential building work at the Applicants’ residential premises, with such work being the construction of a first story addition to the premises comprising of 3 bedrooms, an ensuite, and a balcony (which housed 2 plantar boxes). The Applicant alleges the residential building work was not performed in a proper and workmanlike manner, and initially sought damages of $35,000.00 by way of the cost of rectification. By way of an amended application filed on 20 October 2014, the amount of damages sought by the Applicant was amended to $18,182.47.

  3. The Respondent denied that the work was not performed in a proper and workmanlike manner, and asserted that the proceedings had been filed outside the limitation period under Section 48K of the Home Building Act 1989 (‘the Act’).

  4. The matter was listed before the Tribunal on 29 September 2014 when it was adjourned with various directions made. The matter was again listed before the Tribunal on 29 October 2014, when the matter was set down for a hearing to determine the issue of jurisdiction only, and directions were made to the parties in respect of the filing and serving of evidence on the issue of jurisdiction.

  5. When the matter was listed for hearing on 19 December 2014, the Tribunal encouraged the parties to resolve the dispute pursuant to Section 37 of the Civil and Administrative Tribunal Act 2013 and the NCAT Consumer and Commercial Division Procedural Direction 3. The parties were unable resolve the dispute and the matter proceeded to hearing.

  6. The Applicant relied upon…

CaseChat AU logo

Keep reading for free

Create a free CaseChat account to read Aleksander Gvozdenovic and Audrey Gvozdenovic v Greig Sparli... and more:

  • Read every judgment in full
  • Ask AI and get answers linked to paragraphs
  • See how each paragraph was cited in later cases
  • Download judgments as PDF or Word
Continue with Google

One click creates your free account or signs you in.

By continuing you agree to the Terms and Privacy Policy.

Details
Case
[2015] NSWCATCD 33
Decision Date

CaseChat Overview and Summary

Aleksander Gvozdenovic and Audrey Gvozdenovic brought proceedings against Greig Sparling in the Supreme Court of New South Wales. The dispute centred on defects in residential building work carried out on the Gvozdenovics' property, with the plaintiffs seeking compensation for alleged poor workmanship. The defendants contested liability, asserting that any defects were not attributable to them and that the plaintiffs' claims were time-barred under the statutory limitation period.

The primary legal issues before the court were whether the plaintiffs' claims were within the statutory limitation period and whether the court had jurisdiction to hear the matter. The defendants argued that the plaintiffs' claims were filed beyond the permissible time frame, invoking section 14(1) of the Home Building Act 1989, which stipulates a six-year limitation period from the date of practical completion of the building work. The court had to determine if the plaintiffs' claims were filed within this statutory period and if it possessed jurisdiction to entertain the matter despite the limitation period having elapsed.

The court found that the date of practical completion was clearly established and that the plaintiffs' claims were filed outside the statutory six-year limitation period. It was held that the statutory limitation period provided a clear and unambiguous timeframe within which claims must be brought. Despite the plaintiffs' argument that they were unaware of the defects until a later date, the court was not persuaded that this was a sufficient basis to extend the statutory period. Consequently, the court ruled that it did not have jurisdiction to hear the matter as the claims were time-barred. The application was dismissed.

Orders

Orders of the court

The application is dismissed.

Background

Background to the litigation

Evidence

Evidence Before The Court

Decision

Reasons for decision

Ratio Decidendi

Legal Principle Established