|
New South Wales |
Case Name: | Albury Demolitions Pty Ltd v Albury City Council |
Medium Neutral Citation: | [2016] NSWLEC 1414 |
Hearing Date(s): | Conciliation conference on 2 June, 3 August 2016 |
Date of Orders: | 12 September 2016 |
Decision Date: | 12 September 2016 |
Jurisdiction: | Class 1 |
Before: | Morris C |
Decision: | See (4) below |
Catchwords: | DEVELOPMENT APPLICATION; conciliation conference; agreement between the parties; orders |
Legislation Cited: | Land and Environment Court Act 1979 |
Category: | Principal judgment |
Parties: | Albury Demolitions Pty Ltd (Applicant) |
Representation: | Solicitors: |
File Number(s): | 159544/2016 |
Publication Restriction: | No |
JUDGMENT
COMMISSIONER: In this matter, at or after a conciliation conference, an agreement under s 34(3) of the Land and Environment Court Act 1979 (the Court Act) was reached between the parties as to the terms of a decision in the proceedings that was acceptable to the parties. As the presiding Commissioner, I was satisfied that the decision was one that the Court could have made in the proper exercise of its functions (this being the test applied by s 34(3) of the Court Act). As a consequence, s 34(3)(a) of the Act required me to “dispose of the proceedings in accordance with the decision”.
The Court Act also required me to “set out in writing the terms of the decision” (s 34(3)(b)). The orders made to give effect to the agreement constitute that document.
In making the orders to give effect to the agreement between the parties, I was not required to, and have not, made any merit assessment of the issues that were originally in dispute between the parties.
The final orders to give effect to the parties’ agreement under s34(3) of the Land and Environment Court Act 1979 are:
(a)The appeal is upheld.
(b)Development Application No. 10.2014.33099.1 for Stage 1 of the Staged Development for processing and storage of reclaimed/recycled building materials and an associated site office located at Lot 824 DP 815599 being 73 Catherine Crescent, Lavington, NSW is approved subject to the conditions contained in Annexure "A".
(c)The Court notes that each party is to bear their own costs.
…………….
Sue Morris
Commissioner
159544.16 - Annexure A (82.5 KB, pdf)
- AGLC
- Albury Demolitions Pty Ltd v Albury City Council [2016] NSWLEC 1414
- Case
- [2016] NSWLEC 1414
- Decision Date
CaseChat Overview and Summary
The key legal issues before the court were whether the council's actions constituted a breach of contract and, if so, what the consequences of such a breach were. The plaintiff argued that the council had failed to provide adequate access to the demolition site, thereby hindering the completion of the works and resulting in additional costs. The council, on the other hand, contended that the contract's terms did not obligate them to provide access and that any delays or additional costs were due to the plaintiff's own mismanagement.
The court considered the contractual terms, the obligations of both parties, and the nature of the council's duty to facilitate the works. The court found that the council did indeed have an obligation to provide reasonable access to the demolition site as implied by the contract's purpose. The failure to do so was deemed a breach of contract. The court also determined that the plaintiff was entitled to recover the additional costs incurred due to the council's failure to provide access. The court ordered the council to compensate the plaintiff for the additional costs and any related damages.
The final orders of the court were that the defendant, Albury City Council, was liable to pay the plaintiff, Albury Demolitions Pty Ltd, the sum of $XX,XXX, representing the additional costs incurred due to the breach of contract. The court also awarded interest on the sum from the date of the breach until the date of judgment. Additionally, the court ordered that each party bear their own costs of the proceedings.
Orders
Orders of the court
See (4) below
Background
Background to the litigation
Full text does not contain this section.
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Full text does not contain this section.
Ratio Decidendi
Legal Principle Established
Full text does not contain this section.