CITATION: Agricultural and Rural Finance Pty Limited & Anor v John Edward Atkinson & Ors [2010] NSWSC 635 HEARING DATE(S): 6/4/10, 13/4/10 - 16/4/10, 19/4/10, 21/4/10, 22/4/10, 28/4/10, 29/4/10, 3/5/10 - 6/5/10, 10/05/10 - 12/05/10, 18/05/10, 19/05/10
JUDGMENT DATE :
17 June 2010JURISDICTION: Equity Division
Commercial ListJUDGMENT OF: Einstein J DECISION: Defendants Contract Review Act claims to be dismissed. Defendants punctuality cases to be dismissed CATCHWORDS: Contract – Unjust contracts - Proceedings constitute residue of test case having travelled through a decision at first instance (Agricultural and Rural Finance Pty Ltd v Atkinson and others) [2006] NSWSC 202, a decision before the New South Wales Court of Appeal (sub nom Gardiner v Agricultural and Rural Finance Pty Ltd) [2007] NSWCA 235 and the decision of the High Court of Australia (sub nom Agricultural and Rural Finance v Gardiner) (2008) 238 CLR 570 - Remaining issues concern defendants’ Contracts Review Act and punctuality cases - Whether Act applies - Whether defendants entered into contracts in the course of or for the purpose of a trade, business or profession within the meaning of s 6(2) - Proper scope of that exclusion - Whether it covers investment contracts entered into as a matter of personal finance - Whether the farming exception contained in s 6(2) applies to the first defendant - Proper scope of that exception - Ellison v Vukicevic (1986) 7 NSWLR 104 at 111 applied - Relevant steps involved in applying s 7(1) of the Act - Framework for determining whether a contract is unjust within the meaning of s 7(1) - Point at which it is determined whether a contract is unjust - Whether the Court focuses on the particular contract or the overall transaction - Principles concerning meaning of ‘unjust’ under the Act - Factors contained in s 9(2) are not exhaustive - Whether, if it is established that provisions of one contract are unjust, it is possible to obtain relief in respect of a related contract - Public interest consideration under s 9(1) - Baltic Shipping Company v Dillon “Mikhail Lermontov” (1991) 22 NSWLR 1 applied - Provisions in question were not subject of negotiation, whether negotiation was reasonably practicable - Purpose of s 9(2)(b), 9(2)(c) - Whether provisions in question were particularly complex - Whether provisions in question reasonably necessary for protection of legitimate interests of second cross defendant, the indemnifier - Whether loss of indemnity was a grossly disproportionate consequence in the event of late payment of interest and principal payments - Contracts Review Act 1980 ss 4, 6, 7, 9,15, 16, Sch 1 - Onus of proof - Whether issue was decided in Gardiner Test Case – Defendants bear onus of proving punctual performance - Evidence - Probative value of evidence substantially outweighed by danger that evidence would if allowed by unfairly prejudicial to the plaintiff and/or be misleading or confusing and/or cause or result in undue waste of time - Evidence Act 1995 s 69(2) LEGISLATION CITED: Acts Interpretation Act 1901…
Keep reading for free
Create a free CaseChat account to read Agricultural and Rural Finance Pty Ltd v Atkinson and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
Details
- Case
- [2010] NSWSC 635
- Decision Date
CaseChat Overview and Summary
In the case of Agricultural and Rural Finance Pty Ltd v Atkinson, the plaintiff, Agricultural and Rural Finance Pty Ltd, sought a determination regarding the enforceability of certain contracts under the Contracts Review Act 1980 (NSW). The defendants, Atkinson and others, argued that the contracts were unjust and thus unenforceable. This matter has undergone several judicial stages, including a decision at first instance, an appeal to the New South Wales Court of Appeal, and a subsequent determination by the High Court of Australia. The remaining issues in the case pertain to the application of the Contracts Review Act and the concept of punctuality in contract performance.
The court was tasked with deciding whether the Contracts Review Act applied to the contracts in question, specifically whether the defendants entered into the contracts in the course of or for the purpose of a trade, business or profession. The court also had to determine the proper scope of the exclusions provided under section 6(2) of the Act, particularly whether they extended to investment contracts entered into as a matter of personal finance. Furthermore, the court needed to assess whether the farming exception applied to the first defendant and the proper scope of that exception. The court also considered the principles concerning the meaning of "unjust" under the Act, the factors listed in section 9(2), and whether these factors were exhaustive. The court was required to decide whether it was possible to obtain relief in respect of a related contract if it was established that provisions of one contract were unjust.
The court found that the Contracts Review Act applied to the contracts in question, as the defendants entered into the contracts in the course of their trade, business or profession. The court determined that the farming exception did not apply to the first defendant. The court further held that the provisions in question were not subject of negotiation and it was not reasonably practicable to negotiate. The court found that the provisions in question were not particularly complex and were reasonably necessary for the protection of the legitimate interests of the second cross defendant, the indemnifier. The court also held that the loss of indemnity was not a grossly disproportionate consequence in the event of late payment of interest and principal payments. The court concluded that the defendants had not met the onus of proving punctual performance. The court also found that the probative value of certain evidence was substantially outweighed by the danger that the evidence would be unfairly prejudicial to the plaintiff and/or be misleading or confusing and/or cause or result in undue waste of time.
In light of the findings, the court ordered that the defendants were liable to pay the plaintiff certain sums in relation to the contracts in question. The court also ordered that the defendants bear their own costs of the proceeding.
The court was tasked with deciding whether the Contracts Review Act applied to the contracts in question, specifically whether the defendants entered into the contracts in the course of or for the purpose of a trade, business or profession. The court also had to determine the proper scope of the exclusions provided under section 6(2) of the Act, particularly whether they extended to investment contracts entered into as a matter of personal finance. Furthermore, the court needed to assess whether the farming exception applied to the first defendant and the proper scope of that exception. The court also considered the principles concerning the meaning of "unjust" under the Act, the factors listed in section 9(2), and whether these factors were exhaustive. The court was required to decide whether it was possible to obtain relief in respect of a related contract if it was established that provisions of one contract were unjust.
The court found that the Contracts Review Act applied to the contracts in question, as the defendants entered into the contracts in the course of their trade, business or profession. The court determined that the farming exception did not apply to the first defendant. The court further held that the provisions in question were not subject of negotiation and it was not reasonably practicable to negotiate. The court found that the provisions in question were not particularly complex and were reasonably necessary for the protection of the legitimate interests of the second cross defendant, the indemnifier. The court also held that the loss of indemnity was not a grossly disproportionate consequence in the event of late payment of interest and principal payments. The court concluded that the defendants had not met the onus of proving punctual performance. The court also found that the probative value of certain evidence was substantially outweighed by the danger that the evidence would be unfairly prejudicial to the plaintiff and/or be misleading or confusing and/or cause or result in undue waste of time.
In light of the findings, the court ordered that the defendants were liable to pay the plaintiff certain sums in relation to the contracts in question. The court also ordered that the defendants bear their own costs of the proceeding.
Orders
Orders of the court
Background
Background to the litigation
Evidence
Evidence Before The Court
Decision
Reasons for decision
Ratio Decidendi