QUEENSLAND CIVIL AND
ADMINISTRATIVE TRIBUNAL
CITATION:
Agius v Queensland Building and Construction Commission & anor [2023] QCATA 145
PARTIES:
MARK ELLIOT AGIUS (Applicant/appellant)
v
QUEENSLAND BUILDING AND CONSTRUCTION COMMISSION (First respondent)
GEDOUN CONSTRUCTIONS PTY LTD
(Second respondent)
APPLICATION NO/S:
APL184-22
ORIGINATING APPLICATION NO/S:
GAR194-20
MATTER TYPE:
Appeals
DELIVERED ON:
22 November 2023
HEARING DATE:
24 October 2023
HEARD AT:
Brisbane
DECISION OF:
Senior Member Traves
ORDERS:
1. The application for leave to appeal is allowed.
2. The appeal is dismissed.
CATCHWORDS:
APPEAL – INTERLOCUTORY DECISION – GENERAL ADMINISTRATIVE REVIEW – where application to review ambiguous – whether application sought to review the decision to issue a direction to rectify or the subsequent direction to rectify – whether direction to rectify is a reviewable decision within the meaning of s 86(1)(e) of the Queensland Building and Construction Commission Act 1991 (Qld) – whether application to review should be taken to be an application to review the decision to issue a direction to rectify
Queensland Civil and Administrative Tribunal Act 2009 (Qld), s 3, s 28, s 29, s 43, s 142(3)(a)(ii)
Queensland Building and Construction Commission Act 1991 (Qld), s 86
McNab Constructions Australia Pty Ltd v Queensland Building Services Authority [2013] QSC 57
Oracle Building Corporation Pty Ltd v Queensland Building and Construction Commission [2019] QCAT 419
Oracle Building Corporation Pty Ltd v Queensland Building and Construction Commission [2020] QCAT 69Queensland Building and Construction Commission v Whalley [2018] QCATA 38
APPEARANCES & REPRESENTATION:
This matter was heard and determined on the papers pursuant to s 32 of the Queensland Civil and Administrative Tribunal Act 2009 (Qld)
REASONS FOR DECISION
Appeals APL183-22 and APL184-22 were directed to be heard and determined together. The appeals raise issues under the review provisions in the Queensland Building and Construction Commission Act 1991 (Qld) (QBCC Act).
The first appeal (APL183-22) raised the question of what happens if two persons entitled to have reviewed a reviewable decision, both exercise their entitlements. That appeal is the subject of separate reasons.
This appeal (APL184-22) raises the question of whether a decision to issue a direction to rectify and the issuing of a notice to rectify is one decision or two decisions, and if two, whether both or which is a reviewable decision under the QBCC Act.
The decisions under appeal were decisions made on interlocutory applications, so that, under s 142(3)(a)(ii) of the Queensland Civil and Administrative Tribunal Act 2009 (Qld) (QCAT Act) leave is required to appeal. Each matter raises issues of general application, in this case on which there have been inconsistent decisions of the tribunal, and in the circumstances, it is appropriate to give leave to appeal.
Relevant Background
It appears that the respondent undertook construction work for the appellant.[1] Prior to April 2020 the appellant complained to the Commission about certain aspects of the work undertaken by the respondent, as a result of which on 15 April 2020 the Commission directed the respondent to rectify two items of building work.[2]
[1]For convenience I…
Keep reading for free
Create a free CaseChat account to read Agius v Queensland Building and Construction Commission and more:
- Read every judgment in full
- Ask AI and get answers linked to paragraphs
- See how each paragraph was cited in later cases
- Download judgments as PDF or Word
One click creates your free account or signs you in.
By continuing you agree to the Terms and Privacy Policy.
- Case
- [2023] QCATA 145
- Decision Date
CaseChat Overview and Summary
The legal issues before the court were whether the direction to rectify constituted a reviewable decision and whether the tribunal had jurisdiction to review it. The court had to consider the interpretation of s 86(1)(e) of the QBCC Act and the nature of the direction to rectify in the context of the statutory framework. The appellant contended that the direction to rectify was not a decision in itself, but merely gave effect to the earlier decision to issue that direction. The respondent and the Commission argued that the direction to rectify was a reviewable decision, as held in earlier tribunal decisions.
The court found that the direction to rectify was not a reviewable decision under s 86(1)(e) of the QBCC Act. It held that the giving of the direction to rectify was a consequential step and not a decision involving any further judgment or discretion. This conclusion was based on the statutory language of s 86(1)(e), which only lists a decision to give a direction to rectify as reviewable, not the act of giving the direction itself. The court disagreed with the tribunal's decision and found that it was erroneous in considering the direction to rectify as a reviewable decision. However, the appeal was dismissed as the court found that the appeal did not meet the criteria for leave to appeal under s 142(3)(a)(ii) of the Queensland Civil and Administrative Tribunal Act 2009 (Qld).
Orders
Orders of the court
1. The application for leave to appeal is allowed.
2. The appeal is dismissed.
Background
Background to the litigation
Evidence
Evidence Before The Court
Full text does not contain this section.
Decision
Reasons for decision
Ratio Decidendi
Legal Principle Established
The Commission submitted that the Member erred in applying the reasoning in Oracle 1 [2019] QCAT 419 because those reasons were overturned in Oracle 2 [2020] QCAT 69 when it was observed that a direction to rectify is not a ‘reviewable decision’ for the purposes of s 86(1)(e). Further, it was submitted that procedural fairness had been afforded to the appellant in directing submissions to be filed and in determining the strike out decision based on those submissions, as well as those of the Commission and the respondent.Consideration Section 86 (1)(e) of the QBCC Act provides that the following decision of the Commission under this Act is a “reviewable decision”:A decision to give a direction to rectify or remedy or not to give the direction. The giving of the direction is a consequential step, but if and to the extent that it involves a decision, it is not a reviewable decision under the QBCC Act.[4] To the extent the learned Member decided to the contrary, I respectfully disagree.[4]It may still be reviewable under the Judicial Review Act 1991 (Qld) or in proceedings for a declaration in the Supreme Court. The learned Member referred to Queensland Building and Construction Commission v Whalley.[5] In that matter an application for review identified one reviewable decision as sought to be reviewed (a decision that work had not been satisfactorily rectified), but not another of the same date (to issue a new direction to rectify). It would have been sensible to also seek review of the decision to issue the direction to rectify as it was, in a practical sense, consequent on the decision reviewed. The Appeal Tribunal held that one of the errors made was to set aside the decision for DTR no 40913 because that was not the decision sought to be reviewed. As there had been no request to review that decision, the Appeal Tribunal held the tribunal lacked jurisdiction to review it, even if it was, for the purposes of the QBCC Act, a reviewable decision.[6] That is a different situation from the present.[5][2018] QCATA 38. [6]Ibid at [36]. In Oracle Building Corporation Pty Ltd v Queensland Building and Construction Commission[7] the Member who decided the strike out application in this matter, decided that the decision to give a direction to rectify and the giving of the direction to rectify were each a reviewable decision within the meaning of the QBCC Act s 86(1)(e). In Oracle Building Corporation Pty Ltd v Queensland Building and Construction Commission,[8] a different Member declined to follow that decision, and said that the giving of the direction to rectify was not a decision and hence not a reviewable decision under s 86 of the QBCC Act.[7][2019] QCAT 419.[8][2020] QCAT 69. In McNab Constructions Australia Pty Ltd v Queensland Building Services Authority[9] Dalton J (as her Honour then was) drew a distinction between the decision to give a direction to rectify and the direction to rectify given pursuant to the decision. In that matter it was held that notices which required the work to be completed within 28 days from the date of signing, or the date of posting of the notices giving a direction to rectify did not comply with the requirement in s 72(3) of the QBCC Act, which was interpreted as requiring a period of 28 days from the receipt of the notice by the contractor. Accordingly, a declaration was made that the directions were void. The Commission had argued that a merits review of the decisions to give the directions to rectify was soon to be heard in the tribunal and that the declaration should be refused as a matter of discretion. That was refused on the basis that the decision to give the directions and the giving of the notices of the directions were different, and her Honour’s decision concerned the validity of the directions to rectify that were actually given.[10] The problem in that case was that the period within which work was required to be done was less than that required by the QBCC Act, whether or not there was anything wrong with the decision to give the directions. The distinction was, with respect, entirely appropriate in the circumstances of that case but did not, in my view, go so far as to establish that the giving of the direction was a separate decision, whether or not reviewable. [9][2013] QSC 57.[10]Ibid at [18].